2332 N RICHLAND AVE 90027

Certificate Information: 2332 N RICHLAND AVE 90027

Application / Permit
18010-30000-01121
Plan Check / Job No.
B18WL01661
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, SPRINKLERED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 3/12/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 SERGIO SILVA
Green Plans Picked Up 3/29/2018 APPLICANT
Corrections Issued 3/30/2018 SERGIO SILVA
Quality Review Completed 4/2/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/3/2018 APPLICANT
Applicant returned to address corrections 5/4/2018 SERGIO SILVA
Applicant returned to address corrections 5/17/2018 SERGIO SILVA
Applicant returned to address corrections 5/25/2018 SERGIO SILVA
Applicant returned to address corrections 8/15/2018 SERGIO SILVA
Plan Check Approved 9/25/2018 SERGIO SILVA
Issued 3/12/2019 LADBS
CofO in Progress 6/2/2022 JOSEPH MCGARRY
Permit Finaled 6/7/2022 DEROLD HAUFF
CofO Issued 6/7/2022 DEROLD HAUFF
Permit Finaled 6/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 4/5/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 4/5/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 4/5/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 4/5/2018 NAZILA NOORIFAR
Permit Cleared 4/5/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 4/10/2018 ROBERT DUFF
Sewer availability Cleared 5/1/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 7/9/2018 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 7/9/2018 MICHAEL CASTILLO
Green Code Cleared 7/17/2018 SERGIO SILVA
Excavation more than 5-ft deep Cleared 9/25/2018 CALOSHA APPROVED
GPI Written Notices Cleared 9/25/2018 SERGIO SILVA
Grading Pre-Inspection Cleared 9/25/2018 SERGIO SILVA
Miscellaneous Cleared 9/25/2018 SERGIO SILVA
Miscellaneous Cleared 9/25/2018 SERGIO SILVA
Miscellaneous Cleared 9/25/2018 SERGIO SILVA

Contact Information

Contractor G H B W; Lic. No.: 983577-B 2060 E 37TH STREET      LOS ANGELES, CA 90016
Engineer Amoroso, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Derkalousdian, Hrair Harry; Lic. No.: C79694 441 PALM DR 3      GLENDALE, CA 91202
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Geologist Kirkgard, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2019 Corrections Issued BRAD BESCOS
Excavation/Setback/Form/Re-Bar 5/22/2019 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 5/29/2019 Not Ready for Inspection BRAD BESCOS
Deputy Reinf. Concrete 6/6/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 6/6/2019 Partial Approval BRAD BESCOS
Reinforced Concrete Frame 6/25/2019 Partial Approval BRAD BESCOS
Reinforced Concrete Frame 7/9/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 7/16/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 7/17/2019 Approved BRAD BESCOS
Sewer 7/17/2019 Approved BRAD BESCOS
Deputy Reinf. Concrete 7/30/2019 No Access for Inspection BRAD BESCOS
Underground Mechanical 8/9/2019 Partial Approval BRAD BESCOS
PLUMBING-Rough 8/22/2019 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 9/5/2019 Partial Approval PIERRE VEGA
PLUMBING-Rough 9/5/2019 Partial Approval PIERRE VEGA
Sewer 9/27/2019 Approved BRAD BESCOS
Special/Order Compliance 9/27/2019 Approved CHRISTOPHER DELLEFIELD
Gas Test 10/9/2019 Partial Approval BRAD BESCOS
Underground Mechanical 10/9/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 11/19/2019 Partial Approval BRAD BESCOS
Sewer 12/10/2019 Not Ready for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/13/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 12/16/2019 Approved BRAD BESCOS
Underground Mechanical 12/16/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 12/17/2019 Approved ARTHUR SARGSYAN
Underground Mechanical 12/20/2019 Approved BRAD BESCOS
PLUMBING-Rough 1/6/2020 Partial Approval LUIS BARRALES
Reinforced Concrete Frame 1/16/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 1/22/2020 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 1/30/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/20/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 2/20/2020 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 2/20/2020 Not Ready for Inspection JOSEPH MCGARRY
Deputy Steel/Welding 3/27/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 5/7/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Inspection JOSEPH MCGARRY
PLUMBING-Rough 9/3/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 9/9/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 9/16/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 9/16/2020 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 9/16/2020 Not Ready for Inspection JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 10/15/2020 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/20/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 10/28/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/28/2020 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/2/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 11/2/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/6/2020 Approved DONALD CRICHLOW
HVAC-Rough 11/6/2020 Conditional Approval DONALD CRICHLOW
BUILDING-Rough-Frame 11/13/2020 Conditional Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 11/13/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 11/13/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 11/13/2020 Not Ready for Inspection JOSEPH MCGARRY
Shower Pan 11/19/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/15/2020 Approved JOSEPH MCGARRY
Insulation 12/23/2020 Off-Hour Fees Due
Insulation 12/30/2020 Conditional Approval JOSEPH MCGARRY
Insulation 1/11/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/11/2021 Partial Approval JOSEPH MCGARRY
Insulation 1/14/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/14/2021 Approved JOSEPH MCGARRY
Drywall Nailing 3/12/2021 Approved JOSEPH MCGARRY
Gas Test 3/26/2021 Approved JOSEPH MCGARRY
Pre-Inspection 6/18/2021 Partial Inspection HAMIK HARTOUNIAN
Special/Order Compliance 9/29/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 11/4/2021 Approved JOSEPH MCGARRY
Service/Power Release 11/16/2021 Approved JOSEPH MCGARRY
Service/Power Release 12/15/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 2/4/2022 Approved JOSEPH MCGARRY
HVAC-Final 3/2/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/10/2022 Approved JOSEPH MCGARRY
Final 5/10/2022 Corrections Issued JOSEPH MCGARRY
Green Building Final 5/10/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 5/10/2022 Approved JOSEPH MCGARRY
Final 6/2/2022 OK to Issue CofO JOSEPH MCGARRY