11268 W MONTANA AVE 90049

Certificate Information: 11268 W MONTANA AVE 90049

Application / Permit
18010-30000-01066
Plan Check / Job No.
B18WL01592
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story single family residence
Permit Issued
Issued on 1/18/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 TARIK SAOUD
Corrections Issued 4/16/2018 TARIK SAOUD
Quality Review Completed 4/27/2018 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/6/2018 APPLICANT
Plan Check Approved 1/8/2019 TARIK SAOUD
Issued 1/18/2019 LADBS
Building Plans Picked Up 11/24/2020 APPLICANT
CofO in Progress 10/18/2021 CARLOS MATAMOROS
Permit Finaled 12/17/2021 DANIEL ORRANTE
CofO Issued 12/17/2021 DANIEL ORRANTE
Permit Finaled 12/17/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/26/2018 CHRISTOPHER LAW
Sewer availability Cleared 9/26/2018 CHRISTOPHER LAW
Hydrant and Access approval Cleared 10/26/2018 GEORGE SUCHAND
Green Code Cleared 11/8/2018 RICHARD GARCIA
Low Impact Development Cleared 12/17/2018 AMMAR ELTAWIL
Permit Cleared 12/27/2018 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/27/2018 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 1/3/2019 TARIK SAOUD

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 5/8/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 6/14/2019 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 8/12/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 8/14/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 9/9/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 9/11/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 9/12/2019 Conditional Approval TIM CHRISTENSEN
Deputy Wood Construction 10/15/2019 Conditional Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 11/22/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 11/25/2019 Conditional Approval TIM CHRISTENSEN
PLUMBING-Rough 11/25/2019 Corrections Issued TIM CHRISTENSEN
Deputy Drilled-In Anchors 12/11/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Wood Construction 12/13/2019 Conditional Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 12/18/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 12/23/2019 Corrections Issued CARLOS MATAMOROS
Deputy Wood Construction 1/16/2020 Conditional Approval CARLOS MATAMOROS
HVAC-Rough 1/22/2020 Approved CARLOS MATAMOROS
Deputy Steel/Welding 6/17/2020 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 7/14/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/16/2020 Approved CARLOS MATAMOROS
Green Building Rough 7/16/2020 Approved CARLOS MATAMOROS
MERV13>=Rough 7/16/2020 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/16/2020 Approved CARLOS MATAMOROS
Insulation 8/6/2020 Approved CARLOS MATAMOROS
Insulation 8/17/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/17/2020 Approved CARLOS MATAMOROS
Shower Pan 8/17/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/21/2020 Approved CARLOS MATAMOROS
Drywall Nailing 8/31/2020 Approved CARLOS MATAMOROS
Sewer 2/16/2021 Approved CARLOS MATAMOROS
Sewer 2/18/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 5/12/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
Final 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 8/4/2021 Approved CARLOS MATAMOROS
Gas Test 8/4/2021 Approved CARLOS MATAMOROS
Green Building Final 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Final 8/4/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 8/4/2021 Not Ready for Inspection CARLOS MATAMOROS
Structural Steel Frame 8/4/2021 Approved CARLOS MATAMOROS
Service/Power Release 8/6/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/23/2021 Approved CARLOS MATAMOROS
Final 8/23/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 8/23/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 8/23/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 8/23/2021 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 8/23/2021 Approved CARLOS MATAMOROS
Final 9/20/2021 Corrections Issued CARLOS MATAMOROS
Green Building Final 9/20/2021 Approved CARLOS MATAMOROS
Final 9/30/2021 Corrections Issued JUAN VALENZUELA
Final 10/18/2021 OK to Issue CofO CARLOS MATAMOROS