14186 W ALISAL LANE 90402

Certificate Information: 14186 W ALISAL LANE 90402

Application / Permit
18010-30000-00315
Plan Check / Job No.
B18WL00548
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH BASEMENT, SPRINKLERED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 7/19/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2018 APPLICANT
Green Plans Picked Up 2/13/2018 APPLICANT
Assigned to Plan Check Engineer 2/15/2018 SERGIO SILVA
Corrections Issued 2/21/2018 SERGIO SILVA
Quality Review Completed 3/2/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/2/2018 APPLICANT
Applicant returned to address corrections 4/20/2018 SERGIO SILVA
Applicant returned to address corrections 5/11/2018 SERGIO SILVA
Applicant returned to address corrections 5/22/2018 SERGIO SILVA
Plan Check Approved 7/17/2018 SERGIO SILVA
Issued 7/19/2018 LADBS
CofO in Progress 10/14/2021 JOHN KIDWELL
Permit Finaled 10/19/2021 DANIEL ORRANTE
CofO Issued 10/19/2021 DANIEL ORRANTE
Permit Finaled 10/19/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/19/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 3/19/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 3/19/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 3/19/2018 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 3/19/2018 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/19/2018 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 3/20/2018 ROBERT DUFF
Excavation more than 5-ft deep Cleared 5/11/2018 CALOSHA APPROVED
Low Impact Development Cleared 5/21/2018 AMMAR ELTAWIL
Green Code Cleared 7/10/2018 RICHARD GARCIA
Permit Cleared 7/11/2018 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 7/11/2018 MAHELET GEBEYHU
Watercourse Cleared 7/11/2018 MAHELET GEBEYHU
Disturb/Remove Protected Trees Cleared 7/16/2018 ADRIAN SANCHEZ
GPI Written Notices Cleared 7/17/2018 SERGIO SILVA
Grading Pre-Inspection Cleared 7/17/2018 SERGIO SILVA

Contact Information

Contractor Bruder Construction Inc; Lic. No.: 700657-B 286 BELL CANYON ROAD      BELL CANYON, CA 91307
Engineer Amoroso, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Baad, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/18/2018 Partial Approval VINCENT SCIPIONI
FLOOD-Elevation Certificate 9/21/2018 Approved VINCENT SCIPIONI
Footing/Foundation/Slab 9/21/2018 Partial Approval VINCENT SCIPIONI
Footing/Foundation/Slab 10/15/2018 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/9/2018 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 11/16/2018 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/20/2018 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 12/14/2018 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 12/17/2018 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 12/19/2018 Conditional Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 1/8/2019 Approved DANIEL ORRANTE
Footing/Foundation/Slab 1/8/2019 Partial Approval DANIEL ORRANTE
Deputy Reinf. Concrete 1/30/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 1/30/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 2/22/2019 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/19/2019 Corrections Issued ANDREW NAVE
Deputy Wood Construction 3/22/2019 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/22/2019 Partial Approval ANDREW NAVE
Deputy Wood Construction 4/5/2019 No Access for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 4/30/2019 Partial Approval TIM CHRISTENSEN
Deputy Wood Construction 5/28/2019 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 6/11/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/15/2019 Conditional Approval DANNY TOLENTINO
ELECTRICAL-Rough 12/6/2019 Approved DANNY TOLENTINO
HVAC-Rough 12/10/2019 Corrections Issued DANNY TOLENTINO
PLUMBING-Rough 12/10/2019 Approved DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 12/13/2019 Partial Approval DANNY TOLENTINO
HVAC-Rough 12/24/2019 Approved DANNY TOLENTINO
Shower Pan 12/24/2019 Approved DANNY TOLENTINO
BUILDING-Rough-Frame 1/7/2020 Partial Inspection ANDREW NAVE
FLOOD-Proofing Certificate 1/7/2020 Approved ANDREW NAVE
Green Building Rough 1/7/2020 Approved ANDREW NAVE
Verify Sprinkler Sign Off 1/7/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 1/8/2020 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 1/10/2020 Approved DANNY TOLENTINO
Insulation 1/24/2020 Approved DANNY TOLENTINO
Drywall Nailing 2/7/2020 Partial Approval DANNY TOLENTINO
Interior/Exterior Lathing 2/7/2020 Partial Approval DANNY TOLENTINO
Drywall Nailing 2/11/2020 Approved DANNY TOLENTINO
Interior/Exterior Lathing 5/22/2020 Partial Approval DANNY TOLENTINO
Underground Mechanical 5/22/2020 Partial Approval DANNY TOLENTINO
Gas Test 6/9/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 9/16/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Final 9/17/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 9/17/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 9/20/2021 Approved ANDREW NAVE
ELECTRICAL-Final 9/21/2021 Approved ANDREW NAVE
HVAC-Final 9/21/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 9/21/2021 Approved JUAN VALENZUELA
PLUMBING-Final 9/21/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 9/21/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 9/23/2021 Approved ANDREW NAVE
PLUMBING-Final 9/23/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready ANDREW NAVE
Service/Power Release 9/23/2021 Not Ready for Inspection ANDREW NAVE
Structural Steel Frame 9/23/2021 Approved ANDREW NAVE
Final 9/29/2021 Not Ready for Inspection JOHN KIDWELL
Green Building Final 9/29/2021 Approved JOHN KIDWELL
HVAC-Final 9/29/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved JOHN KIDWELL
Service/Power Release 9/29/2021 Approved JOHN KIDWELL
Smoke Detectors 9/29/2021 Approved JOHN KIDWELL
HVAC-Final 9/30/2021 Approved JOHN KIDWELL
Final 10/13/2021 OK to Issue CofO JOHN KIDWELL