1938 S CHARITON ST 90034

Certificate Information: 1938 S CHARITON ST 90034

Application / Permit
18010-20002-02774
Plan Check / Job No.
B19VN12435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO PERMIT # 18010-20000-02773 TO REVISE SITE PLAN, FLOOR/FRAMING PLANS, FOUNDATION PLAN, STRUCTURAL INVENTORY AND WORK DESCRIPTION TO READ "NEW 35'-0" x 28'-0" IRREGULAR SHAPED THREE STORY SINGLE FAMILY DWELLING WITH 19'-10" x 19' ATTACHED 2-CAR GARAGE " DUE TO A SMALL LOT SUBDIVISION PERSUANT TO PRELIMINARY PARCEL MAP NO. AA-2018-4916-PMLA-SL. A CERTIIFICATE OF OCCUPANCY (TEMPORARY OF FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 10/21/2019
Issuing Office
Valley
Current Status
Permit Finaled on 4/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/16/2019 SARKIS HARABEDIAN
Plan Check Approved 10/16/2019 SARKIS HARABEDIAN
Issued 10/21/2019 LADBS
Permit Finaled 4/15/2021 EVAN COOPER

Permit Application Clearance Information

Miscellaneous Cleared 8/21/2019 RINA LARA
Miscellaneous Cleared 8/21/2019 RINA LARA
Miscellaneous Cleared 9/27/2019 LINDA MARGARET
Sewer availability Cleared 10/3/2019 JOHN LIN
Address approval Cleared 10/7/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/7/2019 CELINA MORENO

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Yuzon, Benigno S Jr; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/14/2019 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/3/2019 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/19/2019 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/19/2019 Corrections Issued EVAN COOPER
Pre-Inspection 1/10/2020 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 2/12/2020 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval EVAN COOPER
Verify Rec and Parks Fee Memo 4/9/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Partial Approval EVAN COOPER
Pre-Inspection 6/30/2020 Approved EVAN COOPER
Verify Rec and Parks Fee Memo 7/28/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 8/14/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 8/20/2020 Approved EVAN COOPER
HVAC-Rough 8/20/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 8/25/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/26/2020 Partial Approval EVAN COOPER
Green Building Rough 8/26/2020 Not Ready for Inspection EVAN COOPER
Shower Pan 8/28/2020 Approved EVAN COOPER
Interior/Exterior Lathing 9/1/2020 Partial Approval EVAN COOPER
Insulation 9/10/2020 Partial Approval EVAN COOPER
Shower Pan 9/10/2020 Approved EVAN COOPER
Interior/Exterior Lathing 9/14/2020 Partial Approval EVAN COOPER
Drywall Nailing 9/17/2020 Approved EVAN COOPER
ELECTRICAL-Final 11/18/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 11/20/2020 Not Ready for Inspection EVAN COOPER
HVAC-Final 11/23/2020 Corrections Issued EVAN COOPER
PLUMBING-Final 11/23/2020 Corrections Issued EVAN COOPER
Gas Test 11/25/2020 Approved EVAN COOPER
PLUMBING-Final 11/25/2020 Approved EVAN COOPER
HVAC-Final 12/3/2020 Approved EVAN COOPER
Service/Power Release 3/11/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 4/15/2021 Approved EVAN COOPER
Final 4/15/2021 Permit Finaled EVAN COOPER
Footing/Foundation/Slab 4/15/2021 Approved EVAN COOPER
Green Building Final 4/15/2021 Approved EVAN COOPER
Green Building Rough 4/15/2021 Approved EVAN COOPER
Smoke Detectors 4/15/2021 Approved EVAN COOPER