1938 S CHARITON ST 90034
Certificate Information: 1938 S CHARITON ST 90034
- Application / Permit
- 18010-20002-02774
- Plan Check / Job No.
- B19VN12435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT # 18010-20000-02773 TO REVISE SITE PLAN, FLOOR/FRAMING PLANS, FOUNDATION PLAN, STRUCTURAL INVENTORY AND WORK DESCRIPTION TO READ "NEW 35'-0" x 28'-0" IRREGULAR SHAPED THREE STORY SINGLE FAMILY DWELLING WITH 19'-10" x 19' ATTACHED 2-CAR GARAGE " DUE TO A SMALL LOT SUBDIVISION PERSUANT TO PRELIMINARY PARCEL MAP NO. AA-2018-4916-PMLA-SL. A CERTIIFICATE OF OCCUPANCY (TEMPORARY OF FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
- Permit Issued
- Issued on 10/21/2019
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/16/2019 | SARKIS HARABEDIAN |
| Issued | 10/21/2019 | LADBS |
| Permit Finaled | 4/15/2021 | EVAN COOPER |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/21/2019 | RINA LARA |
| Miscellaneous | Cleared | 8/21/2019 | RINA LARA |
| Miscellaneous | Cleared | 9/27/2019 | LINDA MARGARET |
| Sewer availability | Cleared | 10/3/2019 | JOHN LIN |
| Address approval | Cleared | 10/7/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2019 | CELINA MORENO |
Contact Information
| Architect | Janev,, Valentine S; Lic. No.: C19379 | 19261 WELLS DRIVE TARZANA, CA 91356 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/14/2019 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/3/2019 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/19/2019 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/19/2019 | Corrections Issued | EVAN COOPER |
| Pre-Inspection | 1/10/2020 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 2/12/2020 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2020 | Partial Approval | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 4/9/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | EVAN COOPER |
| Pre-Inspection | 6/30/2020 | Approved | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 7/28/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/14/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 8/20/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 8/20/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 8/25/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/26/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/26/2020 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 8/28/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/1/2020 | Partial Approval | EVAN COOPER |
| Insulation | 9/10/2020 | Partial Approval | EVAN COOPER |
| Shower Pan | 9/10/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/14/2020 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 9/17/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/18/2020 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 11/20/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 11/23/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 11/23/2020 | Corrections Issued | EVAN COOPER |
| Gas Test | 11/25/2020 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/25/2020 | Approved | EVAN COOPER |
| HVAC-Final | 12/3/2020 | Approved | EVAN COOPER |
| Service/Power Release | 3/11/2021 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 4/15/2021 | Approved | EVAN COOPER |
| Final | 4/15/2021 | Permit Finaled | EVAN COOPER |
| Footing/Foundation/Slab | 4/15/2021 | Approved | EVAN COOPER |
| Green Building Final | 4/15/2021 | Approved | EVAN COOPER |
| Green Building Rough | 4/15/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 4/15/2021 | Approved | EVAN COOPER |