14243 W VICTORY BLVD 91401

Certificate Information: 14243 W VICTORY BLVD 91401

Application / Permit
18010-20002-02073
Plan Check / Job No.
B20VN00117
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SUPPLEMENT TO 18010-20000-02073 TO CORRECT SITE PLAN, REDUCE BLDG LENGTH & REVISE EXIT STAIRS. ALL WORK PER ENG. CHANGE OF CONTRACTOR FROM SACHI DEVELOPMENT LIC # 821150 TO SO CAL CONSTRUCTION ENT. LIC # 832488
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
Permit Finaled on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 JEFFREY TANGONAN
Corrections Issued 1/24/2020 JEFFREY TANGONAN
Quality Review Completed 1/24/2020 STEVEN KIM
Building Plans Picked Up 1/24/2020 APPLICANT
Disabled Access Plans Picked Up 1/30/2020 APPLICANT
Plan Check Approved 2/13/2020 JEFFREY TANGONAN
Issued 2/13/2020 LADBS
Permit Finaled 12/23/2021 JOHN KITCKO

Permit Application Clearance Information

DAS Clearance Cleared 2/7/2020 HAYATO TSUCHIYA
Fire Marshall Fire Life Safety Cleared 2/12/2020 OSCAR SALGADO JR
Hydrant and Access approval Cleared 2/12/2020 GEORGE SUCHAND

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778
Engineer Michael, Papayans; Lic. No.: C44891       ,
Engineer Sassan, Salehipour; Lic. No.: GE2579       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2020 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/27/2020 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 3/31/2020 Approved ROBERT DAVIS
Deputy Steel/Welding 4/15/2020 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 6/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/10/2020 Partial Inspection ANDREW DORSO
Wood Frame 7/20/2020 Approved ROBERT DAVIS
Insulation 7/24/2020 Partial Inspection ANDREW DORSO
Insulation 8/20/2020 Corrections Issued ANDREW DORSO
Insulation 8/24/2020 Partial Inspection ANDREW DORSO
Interior/Exterior Lathing 8/25/2020 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 8/31/2020 Corrections Issued DANIEL VARNUM
Interior/Exterior Lathing 8/31/2020 Approved DANIEL VARNUM
Interior/Exterior Lathing 9/14/2020 Approved ANDREW DORSO
Final 8/24/2021 Not Ready for Inspection CAMERON CHABAN
Final 12/13/2021 Partial Inspection CAMERON CHABAN
Final 12/23/2021 Permit Finaled JOHN KITCKO