13487 W BROWNELL ST 91340

Certificate Information: 13487 W BROWNELL ST 91340

Application / Permit
18010-20001-04737
Plan Check / Job No.
B19VN14309
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PERMIT # 18010-20000-04737 TO REVISE NEW DETACHED ADU TO 2-STORY (23'-1 3/4"x 26'-0") FLOOR AREA FROM 658 SF TO 1,137 SF PER AB494 AND SB229. WORK PER ENGINEER.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
Permit Finaled on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 TROY DEGUZMAN
Corrections Issued 9/26/2019 TROY DEGUZMAN
Quality Review Completed 9/26/2019 CHON CHIO KUO
Building Plans Picked Up 11/12/2019 APPLICANT
Applicant returned to address corrections 12/31/2019 TROY DEGUZMAN
Applicant returned to address corrections 3/9/2020 TROY DEGUZMAN
Applicant returned to address corrections 5/21/2020 TROY DEGUZMAN
Plan Check Approved 3/18/2021 TROY DEGUZMAN
Issued 3/18/2021 APPLICANT
Permit Finaled 11/23/2021 MICHEL ABAJAN

Permit Application Clearance Information

CPC Cleared 12/19/2019 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 12/19/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/19/2019 GEORGE SUCHAND
Low Impact Development Cleared 12/19/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/19/2019 ADRIAN CASTRO
Sewer availability Cleared 12/19/2019 ADRIAN CASTRO
ZA Case Cleared 12/19/2019 HERMINIGILDO AGUSTIN
Green Code Cleared 3/17/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Morales,, Carlos A; Lic. No.: C69972 38100 SAN MATEO AVE      PALMDALE, CA 93551

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/17/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval MICHEL ABAJAN
Drywall Nailing 11/23/2021 Approved MICHEL ABAJAN
Final 11/23/2021 Permit Finaled MICHEL ABAJAN
Smoke Detectors 11/23/2021 Approved MICHEL ABAJAN
Wood Frame 11/23/2021 Approved MICHEL ABAJAN