12241 W CANTARA ST 91605
Certificate Information: 12241 W CANTARA ST 91605
- Application / Permit
- 18010-20000-06375
- Plan Check / Job No.
- B18VN22303
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. CONSTRUCTION PER "WFPP" SHEET.
- Permit Issued
- Issued on 7/11/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | RODNEY SAMIIAN |
| Corrections Issued | 1/28/2019 | RODNEY SAMIIAN |
| Quality Review Completed | 1/29/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 1/31/2019 | APPLICANT |
| Green Plans Picked Up | 3/18/2019 | APPLICANT |
| Applicant returned to address corrections | 6/27/2019 | RODNEY SAMIIAN |
| Plan Check Approved | 7/11/2019 | RODNEY SAMIIAN |
| Issued | 7/11/2019 | LADBS |
| CofO in Progress | 8/27/2020 | MATTHEW NELSON |
| Permit Finaled | 11/9/2020 | MICHAEL SMITH |
| CofO Issued | 11/9/2020 | MICHAEL SMITH |
| Permit Finaled | 11/9/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2019 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2019 | SAFA JAVANMARDI |
| Permit | Cleared | 5/29/2019 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/29/2019 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 5/30/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 7/10/2019 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 7/11/2019 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 7/11/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2019 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 9/6/2019 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/18/2019 | Partial Approval | JOHN HAYES |
| Green Building Rough | 9/18/2019 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/18/2019 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/18/2019 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2019 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 10/8/2019 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/8/2019 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/8/2019 | Corrections Issued | JOHN HAYES |
| Gas Test | 10/10/2019 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/10/2019 | Approved | JOHN HAYES |
| PLUMBING-Rough | 10/17/2019 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/25/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/25/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 10/25/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/25/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2019 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 11/26/2019 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 11/27/2019 | Approved | WILLIAM KUEHN |
| Green Building Rough | 11/27/2019 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/27/2019 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 11/27/2019 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 11/27/2019 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 12/16/2019 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 12/23/2019 | Approved | MICHEL ABAJAN |
| Insulation | 12/31/2019 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 1/9/2020 | Approved | JOHN HAYES |
| Shower Pan | 1/9/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 2/3/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/19/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 8/26/2020 | Approved | MATTHEW NELSON |
| Final | 8/26/2020 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 8/26/2020 | Approved | MATTHEW NELSON |
| HVAC-Final | 8/26/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/26/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/26/2020 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 8/26/2020 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/26/2020 | Approved | MATTHEW NELSON |