18920 W VICTORY BLVD 91335

Certificate Information: 18920 W VICTORY BLVD 91335

Application / Permit
18010-20000-06368
Plan Check / Job No.
B18VN22273
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 28' 6" X 27' 6" 2-STORY IRREGULAR-SHAPED ACCESSORY DWELLING UNIT WITH ATTACHED 16' 2" X 11' 1-CAR GARAGE PER AB 494 AND SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 12/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 MUKUL GUPTA
Corrections Issued 1/25/2019 MUKUL GUPTA
Quality Review Completed 1/29/2019 MOHAMMAD FIROUZBAKHT
Building Plans Picked Up 2/20/2019 APPLICANT
Green Plans Picked Up 2/20/2019 APPLICANT
Plan Check Approved 8/6/2019 GURUNATH NESARAJAH
Issued 12/1/2020 APPLICANT
CofO in Progress 12/2/2021 SEAN HAUPT
CofO Issued 12/7/2021 MICHAEL SMITH
Permit Finaled 12/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/30/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 4/30/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 4/30/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 5/7/2019 ANDRES COVARRUBIAS
ZI Cleared 5/14/2019 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 5/22/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 5/30/2019 GUILLERMO PETRA
Green Code Cleared 6/12/2019 DAVID MATSON

Contact Information

Contractor Apex G B C Inc; Lic. No.: 896883-B 18653 VENTURA BLVD #273      TARZANA, CA 91356
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Salehi,, Mohammad Reza Tom; Lic. No.: C50447 P O BOX 17881      ENCINO, CA 91416

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/9/2020 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 12/9/2020 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 12/9/2020 Not Ready for Inspection STEVEN BACK
Pre-Inspection 12/9/2020 Approved STEVEN BACK
PLUMBING-Rough 12/23/2020 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 12/24/2020 Approved STEVEN BACK
Footing/Foundation/Slab 12/24/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 2/2/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 2/10/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Approved STEVEN BACK
HVAC-Rough 2/10/2021 Approved STEVEN BACK
PLUMBING-Rough 2/10/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 2/24/2021 Corrections Issued STEVEN BACK
Green Building Rough 2/24/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/24/2021 Partial Approval STEVEN BACK
Verify Sprinkler Sign Off 2/24/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 2/26/2021 Approved STEVEN BACK
Insulation 2/26/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/26/2021 Partial Approval STEVEN BACK
Drywall Nailing 3/5/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 3/5/2021 Approved DAVID STEPANYAN
Sewer 3/30/2021 Approved STEVEN BACK
Underground Mechanical 5/10/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Final 9/9/2021 Not Ready for Inspection STEVEN BACK
Final 9/9/2021 Corrections Issued STEVEN BACK
Green Building Final 9/9/2021 Approved STEVEN BACK
HVAC-Final 9/9/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 9/9/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready STEVEN BACK
Service/Power Release 9/9/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 9/9/2021 Approved STEVEN BACK
Final 10/29/2021 Conditional Approval SEAN HAUPT
HVAC-Final 10/29/2021 Conditional Approval SEAN HAUPT
PLUMBING-Final 10/29/2021 Conditional Approval SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved SEAN HAUPT
Service/Power Release 10/29/2021 Approved SEAN HAUPT