6905 N BEN AVE 1-5 91605
Certificate Information: 6905 N BEN AVE 1-5 91605
- Application / Permit
- 18010-20000-06355
- Plan Check / Job No.
- B18VN22226
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3-STORY 5 UNIT APARTMENT OVER GARAGE ON GRADE.
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | SAM CHANG |
| Disabled Access Plans Picked Up | 2/11/2019 | APPLICANT |
| Green Plans Picked Up | 2/11/2019 | APPLICANT |
| Corrections Issued | 2/15/2019 | SAM CHANG |
| Quality Review Completed | 2/25/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 10/1/2019 | SAM CHANG |
| Applicant returned to address corrections | 12/13/2019 | SAM CHANG |
| Plan Check Approved | 3/24/2022 | SAM CHANG |
| Issued | 3/17/2023 | APPLICANT |
| TCO Issued (Expire Date: 06-18-2025) | 12/20/2024 | JEFFREY DURAN |
| CofO in Progress | 5/6/2025 | JOHN KITCKO |
| CofO in Progress | 5/6/2025 | JOHN KITCKO |
| Permit Finaled | 5/13/2025 | RICKEY JACKSON |
| CofO Issued | 5/13/2025 | RICKEY JACKSON |
| Permit Finaled | 5/13/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2019 | LEE GUILBEAUX |
| Permit | Cleared | 3/11/2019 | LEE GUILBEAUX |
| CPC | Cleared | 8/21/2019 | RINA LARA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2019 | GUILLERMO PETRA |
| Frnt yard landscape/Water mgmt | Cleared | 8/21/2019 | RINA LARA |
| Sewer availability | Cleared | 8/21/2019 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 8/21/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 8/22/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 9/17/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/2/2019 | SAFA JAVANMARDI |
| Green Code | Cleared | 10/31/2019 | MICHAEL AYERS |
| Fire Marshall Fire Life Safety | Cleared | 12/26/2019 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 2/10/2020 | SAM CHANG |
| Hold | Cleared | 4/30/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alrayes,, Nidham Aram; Lic. No.: C65487 | 10346 SAMOA AVE TUJUNGA, CA 91042 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/20/2023 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 6/20/2023 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 6/21/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 6/30/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/3/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/11/2023 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/13/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/13/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/19/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/20/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/21/2023 | Approved | JOHN KITCKO |
| Reinforced Masonry Frame | 7/21/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/24/2023 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 8/17/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/17/2023 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 8/18/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/23/2023 | Approved | JOHN KITCKO |
| Green Building Rough | 9/21/2023 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 9/21/2023 | Approved | JOHN KITCKO |
| Wood Frame | 9/21/2023 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Partial Approval | JOHN KITCKO |
| Pre-Inspection | 11/2/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Wood Construction | 11/9/2023 | Approved | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 1/16/2024 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 1/19/2024 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Not Ready for Inspection | JOHN KITCKO |
| Light Gage Steel Frame | 2/13/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 2/15/2024 | Partial Inspection | JOHN KITCKO |
| Light Gage Steel Frame | 2/15/2024 | Not Ready for Inspection | JOHN KITCKO |
| Special/Order Compliance | 2/15/2024 | Partial Inspection | STEVEN LEVITT |
| Wood Frame | 2/21/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 2/23/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 2/23/2024 | Partial Approval | JOHN KITCKO |
| Insulation | 3/1/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 3/1/2024 | Partial Inspection | BRIAN KELLY |
| Insulation | 3/13/2024 | Approved | JOHN KITCKO |
| Drywall Nailing | 3/19/2024 | Partial Approval | JOHN KITCKO |
| T-Bar Ceiling | 3/28/2024 | Not Ready for Inspection | JOHN KITCKO |
| Light Gage Steel Frame | 4/1/2024 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 4/15/2024 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 9/30/2024 | Partial Inspection | JOHN KITCKO |
| Final | 12/9/2024 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 12/9/2024 | Approved | JOHN KITCKO |
| Green Building Final | 12/9/2024 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 12/9/2024 | Approved | JOHN KITCKO |
| Reinforced Concrete Frame | 12/9/2024 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 12/9/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 12/9/2024 | Approved | JOHN KITCKO |
| Pre-Inspection | 12/10/2024 | Partial Inspection | JOHN KITCKO |
| Final | 12/17/2024 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 12/17/2024 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 12/17/2024 | Approved | JOHN KITCKO |
| Final | 12/19/2024 | OK to Issue CofO | JOHN KITCKO |
| Pre-Inspection | 12/19/2024 | Approved | JOHN KITCKO |