7244 N JELLICO AVE 91406

Certificate Information: 7244 N JELLICO AVE 91406

Application / Permit
18010-20000-06348
Plan Check / Job No.
B18VN22185
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 25' X 24' 2-STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 3/11/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 GURUNATH NESARAJAH
Corrections Issued 1/30/2019 GURUNATH NESARAJAH
Quality Review Completed 1/30/2019 OMID HEDAYAT
Building Plans Picked Up 2/1/2019 APPLICANT
Green Plans Picked Up 2/1/2019 APPLICANT
Applicant returned to address corrections 6/1/2020 GURUNATH NESARAJAH
Plan Check Approved 7/29/2020 GURUNATH NESARAJAH
Issued 3/11/2021 APPLICANT
CofO in Progress 12/17/2025 GAREN HAYRAPETYAN
Permit Finaled 12/19/2025 RUBEN SALAS
CofO Issued 12/19/2025 RUBEN SALAS
Permit Finaled 12/19/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 7/16/2019 RIDWAN HARDY
Address approval Cleared 7/30/2019 ERIK BEASLEY
Low Impact Development Cleared 3/13/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 3/13/2020 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/17/2020 CELINA MORENO
Hydrant and Access approval Cleared 3/17/2020 ROBERT DUFF
Sewer availability Cleared 3/17/2020 CELINA MORENO
Green Code Cleared 3/24/2020 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/8/2021 Partial Inspection JACK KARGODORIAN
PLUMBING-Rough 7/19/2021 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 8/6/2021 Approved JACK KARGODORIAN
Pre-Inspection 8/23/2021 Partial Approval DAVID STEPANYAN
Pre-Inspection 10/4/2021 Partial Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Corrections Issued RAUL OLAGI
Deputy Wood Construction 12/7/2021 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/6/2022 Approved RAUL OLAGI
Pre-Inspection 1/20/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 4/13/2022 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 4/27/2022 Corrections Issued RAUL OLAGI
Green Building Rough 4/27/2022 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 4/27/2022 Approved RAUL OLAGI
HVAC-Rough 5/5/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 6/2/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/2/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/28/2022 Approved ALAN MORELOS
ELECTRICAL-Rough 6/28/2022 Approved ALAN MORELOS
Insulation 9/19/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 9/19/2022 Partial Approval ALAN MORELOS
Pre-Inspection 12/15/2022 Approved DAVID ANDERSON
Sewer 1/24/2023 Corrections Issued RAUL OLAGI
Sewer 1/26/2023 Approved RAUL OLAGI
Pre-Inspection 1/31/2023 Approved DAVID ANDERSON
Underground Mechanical 2/14/2023 Partial Approval RAUL OLAGI
Insulation 4/12/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 4/25/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/27/2023 Approved RAUL OLAGI
Green Building Rough 4/27/2023 Approved RAUL OLAGI
Drywall Nailing 5/16/2023 Approved RAUL OLAGI
PLUMBING-Rough 6/5/2023 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 6/5/2023 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 6/30/2023 Approved RAUL OLAGI
Final 8/7/2023 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 8/7/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Not Ready RAUL OLAGI
Service/Power Release 8/7/2023 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 8/7/2023 Approved RAUL OLAGI
Final 4/23/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 4/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 4/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 12/17/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 12/17/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 12/17/2025 Approved GAREN HAYRAPETYAN