7522 N LEMP AVE 91605

Certificate Information: 7522 N LEMP AVE 91605

Application / Permit
18010-20000-06326
Plan Check / Job No.
B18VN22077
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRREGULAR SHAPED 48'-4"X 33'-11" ACCESSORY DWELLING UNIT PER AB494 AND SB229 ALL PER WOOD FRAMED PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 7/24/2020
Issuing Office
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 ALYSSA N NARCISO
Corrections Issued 1/30/2019 ALYSSA N NARCISO
Quality Review Completed 1/30/2019 OMID HEDAYAT
Building Plans Picked Up 2/1/2019 APPLICANT
Green Plans Picked Up 2/1/2019 APPLICANT
Applicant returned to address corrections 7/6/2020 ALYSSA N NARCISO
Plan Check Approved 7/24/2020 ALYSSA N NARCISO
Issued 7/24/2020 APPLICANT
CofO in Progress 10/30/2024 ROBERTO PALACIOS-LOPEZ
CofO Issued 11/1/2024 DANIEL ORRANTE
Permit Finaled 11/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/5/2019 HOWARD COOPER
Low Impact Development Cleared 7/9/2019 MITESH PATEL
Construction near power lines Cleared 8/22/2019 RIDWAN HARDY
Hydrant and Access approval Cleared 5/27/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 5/29/2020 GUILLERMO PETRA
Sewer availability Cleared 6/3/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 6/4/2020 GUILLERMO PETRA
Green Code Cleared 7/1/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/31/2021 Not Ready for Inspection DANIEL DREW
Green Building Rough 8/31/2021 Not Ready for Inspection DANIEL DREW
Verify Sprinkler Sign Off 8/31/2021 Not Ready for Inspection DANIEL DREW
Pre-Inspection 9/1/2021 Not Ready for Inspection DANIEL DREW
Wood Frame 9/1/2021 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 10/4/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/4/2021 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/13/2021 Not Ready for Inspection DANIEL DREW
Excavation/Setback/Form/Re-Bar 10/18/2021 Approved DANIEL DREW
Special/Order Compliance 10/18/2021 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval DANIEL DREW
Rough-Elec/Plmb/HVAC 12/30/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/1/2022 Approved MICHEL ABAJAN
Green Building Rough 2/1/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/1/2022 Approved MICHEL ABAJAN
Insulation 2/7/2022 Conditional Approval CALEB MEISTER
Drywall Nailing 2/15/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/15/2022 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 4/4/2022 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 4/29/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 5/3/2022 Approved CALEB MEISTER
ELECTRICAL-Final 8/31/2022 Not Ready for Inspection JOHN HAYES
Final 12/8/2022 Corrections Issued JOHN HAYES
Service/Power Release 12/8/2022 Not Ready for Inspection JOHN HAYES
Service/Power Release 12/9/2022 No Access for Inspection JORDAN KUTZLY
Gas Test 5/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/10/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 8/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/24/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 10/21/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/30/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/30/2024 Approved ROBERTO PALACIOS-LOPEZ