20150 W RINALDI ST 91326

Certificate Information: 20150 W RINALDI ST 91326

Application / Permit
18010-20000-06305
Plan Check / Job No.
B18VN22051
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
NEW 4-STORY, TYPE VA, HOTEL WITH 100 GUESTS ROOMS.
Permit Issued
Issued on 1/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Building Plans Picked Up 3/26/2016 APPLICANT
Submitted 12/24/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 KESETE HAREGOT
Disabled Access Plans Picked Up 1/31/2019 APPLICANT
Green Plans Picked Up 1/31/2019 APPLICANT
Corrections Issued 3/19/2019 KESETE HAREGOT
Quality Review Completed 3/22/2019 QUAN NGHIEM
Applicant returned to address corrections 10/2/2019 KESETE HAREGOT
Applicant returned to address corrections 2/3/2020 KESETE HAREGOT
Applicant returned to address corrections 6/28/2021 KESETE HAREGOT
Applicant returned to address corrections 7/29/2021 KESETE HAREGOT
Plan Check Approved 1/19/2022 KESETE HAREGOT
Issued 1/24/2022 APPLICANT
Permit Closed-Status Void 3/29/2023 JEFFREY FULTON
Re-Activate Permit 3/30/2023 JEFFREY FULTON
TCO Issued (Expire Date: 05-07-2025) 11/8/2024 RICKEY JACKSON
TCO Issued (Expire Date: 11-02-2025) 5/6/2025 JEFFREY DURAN
TCO Issued (Expire Date: 05-02-2026) 11/3/2025 JEFFREY DURAN
CofO in Progress 2/17/2026 GREGORY POMISH
Permit Finaled 3/19/2026 RICKEY JACKSON
CofO Issued 3/19/2026 RICKEY JACKSON
Permit Finaled 3/19/2026 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 1/24/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/3/2020 THAN WIN
Sewer availability Cleared 2/21/2020 EMIL KYUPELYAN
DAS Clearance Cleared 7/22/2020 NORLITO MEDRANO
GPI Written Notices Cleared 8/13/2020 KESETE HAREGOT
Grading Pre-Inspection Cleared 8/13/2020 KESETE HAREGOT
Green Code Cleared 10/20/2020 MICHAEL AYERS
"D" conditions Cleared 11/12/2020 RUBEN VASQUEZ
"T" removal Cleared 11/12/2020 RUBEN VASQUEZ
Certificate of Compliance Cleared 11/12/2020 RUBEN VASQUEZ
Certificate of Compliance Cleared 11/12/2020 RUBEN VASQUEZ
Miscellaneous Cleared 11/12/2020 RUBEN VASQUEZ
Prkng lot landscape/Water mgmt Cleared 11/12/2020 RUBEN VASQUEZ
Specific Plan Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 11/12/2020 RUBEN VASQUEZ
ZA Case Cleared 11/12/2020 RUBEN VASQUEZ
ZA Case Cleared 11/12/2020 RUBEN VASQUEZ
Building over 3-story or 36-ft Cleared 3/24/2021 CALOSHA APPROVED
Internal circulation Cleared 4/5/2021 SHEILA AHORAIAN
Specific Plan Cleared 4/5/2021 SHEILA AHORAIAN
Fire Marshall Fire Life Safety Cleared 5/17/2021 WILLIAM JOHNS
Hydrant and Access approval Cleared 5/17/2021 MATTHEW CRAIG
Work Adjacent to Public Way Cleared 7/27/2021 GABRIEL ROBLES
Highway dedication Cleared 8/3/2021 CARLOS AGUILERA
Permit Cleared 8/3/2021 CARLOS AGUILERA
Trees in Parkway Cleared 8/26/2021 JOHN KIM
Low Impact Development Cleared 8/28/2021 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 8/30/2021 CARLOS AGUILERA
Disturb/Remove Protected Trees Cleared 10/6/2021 ADALBERTO VERA

Contact Information

Architect Cechavicius,, Kastytis; Lic. No.: C33294 1712 WINNERS CUP DRIVE      LAS VEGAS, NV 89117
Contractor Tharaldson Hospitality Development Llc; Lic. No.: 990076-B 4520 36TH AVE S      FARGO, ND 58104
Engineer Hatch,, Robert Joseph; Lic. No.: S4634 1677 EUREKA RD STE 101      ROSEVILLE, CA 95661
Engineer Jacoby,, Samuel J; Lic. No.: C74309 8881 RESEARCH DR      IRVINE, CA 92618
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Landscape Architect Baldovin,, James Eugene; Lic. No.: LA4176 3195 C AIRPORT LOOP DRIVE      COSTA MESA, CA 92626

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/4/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/7/2022 Partial Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 5/16/2022 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 6/3/2022 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/21/2022 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 6/21/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/24/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/27/2022 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 7/1/2022 Partial Inspection JEFFREY FULTON
Pre-Inspection 7/6/2022 Corrections Issued JEFFREY FULTON
Footing/Foundation/Slab 7/11/2022 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 7/21/2022 No Access for Inspection JEFFREY FULTON
Masonry Wall/Backfill 8/1/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 8/5/2022 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/17/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 8/19/2022 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/29/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 8/30/2022 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 9/6/2022 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 9/14/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 9/15/2022 Conditional Approval JEFFREY FULTON
Green Building Rough 9/19/2022 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 9/19/2022 Not Ready for Inspection ANDREW DORSO
Wood Frame 9/19/2022 Not Ready for Inspection ANDREW DORSO
Deputy Steel/Welding 9/22/2022 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/23/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 9/26/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/4/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/12/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/19/2022 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/20/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/24/2022 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/26/2022 Conditional Approval JEFFREY DURAN
Drywall Nailing 10/27/2022 Not Ready for Inspection KENNETH ROBERTS
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval KENNETH ROBERTS
Deputy Wood Construction 10/28/2022 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 10/28/2022 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Corrections Issued JEFFREY FULTON
Green Building Rough 11/30/2022 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 11/30/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/30/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 12/5/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 12/7/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Wood Construction 12/8/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 12/16/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/22/2022 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/22/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/22/2022 Partial Inspection JEFFREY FULTON
Special/Order Compliance 12/23/2022 No Access for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 1/17/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 1/18/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 1/19/2023 Corrections Issued JEFFREY FULTON
Deputy Wood Construction 1/23/2023 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/6/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Inspection JEFFREY FULTON
Insulation 2/9/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/22/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 2/22/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 2/22/2023 Not Ready for Inspection STEVEN LEVITT
Drywall Nailing 2/23/2023 Partial Inspection JEFFREY FULTON
Insulation 2/23/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 2/23/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 2/27/2023 Partial Inspection JEFFREY FULTON
Wood Frame 2/27/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/28/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 2/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/2/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/8/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 3/8/2023 Partial Approval STEVEN LEVITT
Wood Frame 3/8/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 3/9/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/13/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Partial Inspection JEFFREY FULTON
Insulation 3/13/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/14/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/15/2023 Partial Inspection JEFFREY FULTON
Wood Frame 3/15/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/17/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/24/2023 Partial Inspection JEFFREY FULTON
Wood Frame 3/24/2023 Partial Inspection JEFFREY FULTON
Insulation 3/29/2023 Partial Inspection JEFFREY FULTON
Wood Frame 3/29/2023 Partial Inspection JEFFREY FULTON
Insulation 3/31/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/5/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/11/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/13/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 4/13/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/17/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/17/2023 Partial Approval STEVEN LEVITT
Insulation 4/19/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/19/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 4/26/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/3/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/8/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/11/2023 Partial Inspection JEFFREY FULTON
Insulation 5/11/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/16/2023 Partial Inspection JEFFREY FULTON
Wood Frame 5/16/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 5/23/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 5/23/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 5/30/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 5/30/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/30/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 5/30/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 6/6/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 6/6/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/6/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/6/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 6/9/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 6/13/2023 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/21/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 6/23/2023 Conditional Approval JEFFREY FULTON
Drywall Nailing 6/23/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 6/23/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 6/27/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 6/28/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/28/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 6/29/2023 Partial Inspection JEFFREY FULTON
Wood Frame 6/29/2023 Partial Inspection JEFFREY FULTON
Insulation 7/5/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/14/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/18/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/20/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Partial Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 8/1/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/1/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/1/2023 Partial Inspection JEFFREY FULTON
Insulation 8/2/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 8/3/2023 Partial Inspection JEFFREY FULTON
Wood Frame 8/8/2023 Partial Inspection JEFFREY FULTON
Insulation 8/10/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/14/2023 Partial Inspection JEFFREY FULTON
Insulation 8/14/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/16/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/16/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/16/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 8/18/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/22/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 9/5/2023 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 9/5/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/5/2023 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/8/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/11/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/11/2023 Partial Inspection JEFFREY FULTON
Insulation 9/12/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/22/2023 No Access for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/26/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 9/28/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/3/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/3/2023 Partial Inspection JEFFREY FULTON
Insulation 10/5/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/10/2023 Partial Inspection JEFFREY FULTON
Insulation 11/14/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/20/2023 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/28/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 11/28/2023 Partial Inspection JEFFREY FULTON
Piling/Pier/Caisson 11/30/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 11/30/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/30/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/4/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/4/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/5/2023 Partial Inspection JEFFREY FULTON
Insulation 12/11/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/18/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/26/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 1/2/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/12/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 1/12/2024 Partial Inspection MELVIN GIRTON
Deputy Drilled-In Anchors 1/17/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 1/18/2024 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 1/18/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/23/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/25/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 1/25/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/30/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/6/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/6/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 3/20/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/3/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 4/3/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 4/3/2024 Partial Inspection GREGORY POMISH
Special/Order Compliance 4/4/2024 Not Ready for Inspection GREGORY POMISH
Deputy Other (see comments) 4/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/5/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 4/10/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 4/10/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 4/15/2024 Partial Approval GREGORY POMISH
T-Bar Ceiling 4/15/2024 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 5/14/2024 Not Ready for Inspection GREGORY POMISH
Piling/Pier/Caisson 5/14/2024 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 5/16/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 5/17/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/28/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 5/28/2024 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/3/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/6/2024 Conditional Approval GREGORY POMISH
Special/Order Compliance 6/17/2024 Partial Inspection GREGORY POMISH
T-Bar Ceiling 7/1/2024 Corrections Issued ROBERT DAVIS
T-Bar Ceiling 7/3/2024 Partial Approval ROBERT DAVIS
Piling/Pier/Caisson 7/29/2024 Partial Inspection GREGORY POMISH
T-Bar Ceiling 7/31/2024 Not Ready for Inspection GREGORY POMISH
Special/Order Compliance 8/7/2024 Partial Inspection GREGORY POMISH
Final 8/12/2024 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 8/12/2024 Approved GREGORY POMISH
Green Building Final 8/12/2024 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 8/12/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/12/2024 Partial Inspection GREGORY POMISH
Wood Frame 8/12/2024 Partial Inspection GREGORY POMISH
Special/Order Compliance 8/14/2024 Corrections Issued GREGORY POMISH
Special/Order Compliance 9/4/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 9/5/2024 Partial Inspection GREGORY POMISH
Final 9/12/2024 Partial Inspection GREGORY POMISH
Green Building Final 9/12/2024 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 9/12/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 9/12/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 9/12/2024 Partial Inspection GREGORY POMISH
Final 9/30/2024 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready GREGORY POMISH
Verify Sprinkler Sign Off 9/30/2024 Partial Inspection GREGORY POMISH
Wood Frame 9/30/2024 Partial Approval GREGORY POMISH
Final 10/21/2024 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved GREGORY POMISH
Verify Sprinkler Sign Off 10/21/2024 Approved GREGORY POMISH
Wood Frame 10/21/2024 Approved GREGORY POMISH
Final 10/23/2024 Partial Inspection GREGORY POMISH
Final 10/31/2024 Partial Inspection GREGORY POMISH
Final 11/4/2024 Partial Inspection GREGORY POMISH
Special/Order Compliance 11/5/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 12/5/2024 Not Ready for Inspection GREGORY POMISH
Special/Order Compliance 4/8/2025 Partial Inspection GREGORY POMISH
Light Gage Steel Frame 4/10/2025 Approved GREGORY POMISH
Drywall Nailing 4/11/2025 Approved GREGORY POMISH
Grading Pre-Inspection 4/22/2025 Approved GREGORY POMISH
Special/Order Compliance 10/7/2025 Partial Inspection GREGORY POMISH
Final 1/30/2026 OK to Issue CofO GREGORY POMISH