20363 W WINDSOR LANE 91326
Certificate Information: 20363 W WINDSOR LANE 91326
- Application / Permit
- 18010-20000-06237
- Plan Check / Job No.
- B18VN21878
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- THREE STORY SFD AND ATTACHED 3 CAR GARAGE WITH RECREATION ROOM/OPEN DECK AT 3RD FLOOR _STANDARD PLAN #648_ PLAN 3XB (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D)
- Permit Issued
- Issued on 4/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2018 | APPLICANT |
| Green Plans Picked Up | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | DAWN MC NULTY |
| Corrections Issued | 1/28/2019 | DAWN MC NULTY |
| Quality Review Completed | 2/8/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 2/11/2019 | APPLICANT |
| Plan Check Approved | 4/1/2019 | DAWN MC NULTY |
| Issued | 4/2/2019 | LADBS |
| CofO in Progress | 8/27/2020 | SEAN WIRCH |
| Permit Finaled | 9/2/2020 | DONALD SUNSERI |
| CofO Issued | 9/2/2020 | DONALD SUNSERI |
| Permit Finaled | 9/2/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2019 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2019 | JOHN LIN |
| Permit | Cleared | 2/14/2019 | JOHN LIN |
| Sewer availability | Cleared | 2/14/2019 | JOHN LIN |
| "T" removal | Cleared | 2/20/2019 | EDBER MACEDO |
| CPC | Cleared | 2/20/2019 | EDBER MACEDO |
| Miscellaneous | Cleared | 2/20/2019 | EDBER MACEDO |
| Miscellaneous | Cleared | 2/20/2019 | EDBER MACEDO |
| Miscellaneous | Cleared | 2/20/2019 | EDBER MACEDO |
| Miscellaneous | Cleared | 2/20/2019 | EDBER MACEDO |
| Specific Plan | Cleared | 2/20/2019 | EDBER MACEDO |
| Tract Map conditions | Cleared | 2/20/2019 | EDBER MACEDO |
| ZA Case | Cleared | 2/20/2019 | EDBER MACEDO |
| ZA Case | Cleared | 2/20/2019 | EDBER MACEDO |
| Hydrant and Access approval | Cleared | 2/21/2019 | ROBERT DUFF |
| Low Impact Development | Cleared | 2/27/2019 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/7/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 3/14/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/11/2019 | Approved | BRUCE ROZAK |
| Underground Mechanical | 4/23/2019 | Approved | BRUCE ROZAK |
| Footing/Foundation/Slab | 5/13/2019 | Approved | BRUCE ROZAK |
| Sewer | 5/22/2019 | Approved | BRUCE ROZAK |
| Deputy Steel/Welding | 6/19/2019 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2019 | Approved | BRUCE ROZAK |
| BUILDING-Rough-Frame | 11/12/2019 | Approved | BRUCE ROZAK |
| ELECTRICAL-Rough | 11/12/2019 | Approved | BRUCE ROZAK |
| Green Building Rough | 11/12/2019 | Approved | BRUCE ROZAK |
| HVAC-Rough | 11/12/2019 | Approved | BRUCE ROZAK |
| PLUMBING-Rough | 11/12/2019 | Approved | BRUCE ROZAK |
| Verify Sprinkler Sign Off | 11/12/2019 | Approved | BRUCE ROZAK |
| Drywall Nailing | 11/26/2019 | Approved | DONALD SUNSERI |
| Interior/Exterior Lathing | 11/26/2019 | Approved | DONALD SUNSERI |
| Gas Test | 1/10/2020 | Approved | DONALD SUNSERI |
| Service/Power Release | 1/22/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Service/Power Release | 1/28/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Service/Power Release | 1/30/2020 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 2/14/2020 | SGSOV Approved | SEAN WIRCH |
| ELECTRICAL-Final | 4/17/2020 | Approved | SEAN WIRCH |
| HVAC-Final | 4/17/2020 | Approved | SEAN WIRCH |
| PLUMBING-Final | 4/17/2020 | Approved | SEAN WIRCH |
| Final | 8/27/2020 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 8/27/2020 | Approved | SEAN WIRCH |
| Smoke Detectors | 8/27/2020 | Approved | SEAN WIRCH |