7404 N DENNY AVE 91352

Certificate Information: 7404 N DENNY AVE 91352

Application / Permit
18010-20000-06166
Plan Check / Job No.
B18VN21759
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 44' X 54'7" IRREGULAR SHAPED SFD WITH ATTACHED TWO CAR GARAGE AND WITH 4'8" X 8' ATTACHED FRONT PORCH, NFPA-13D SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/14/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 RARES BODEA
Corrections Issued 1/5/2019 RARES BODEA
Quality Review Completed 1/8/2019 OMID HEDAYAT
Building Plans Picked Up 1/15/2019 APPLICANT
Green Plans Picked Up 1/15/2019 APPLICANT
Applicant returned to address corrections 7/14/2020 RARES BODEA
Applicant returned to address corrections 12/7/2020 RARES BODEA
Plan Check Approved 12/14/2020 RARES BODEA
Issued 1/14/2021 APPLICANT
CofO in Progress 4/4/2023 JOHN HAYES
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 5/29/2019 PARISA ZAHABI
Address approval Cleared 7/29/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/29/2019 ELENA LOPEZ
Permit Cleared 7/29/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 7/30/2019 GEORGE SUCHAND
Trees in Parkway Cleared 8/16/2019 JOHN KIM
Low Impact Development Cleared 10/30/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/4/2020 JEANIE LAM
Sewer availability Cleared 11/4/2020 JEANIE LAM

Contact Information

Contractor Luna Construction Llc; Lic. No.: 671281-B 7463 DENNY AVENUE      SUN VALLEY, CA 91352
Engineer Casillas,, Rafael Ortega; Lic. No.: C68234 1937 S BRADSHAWE AVE      MONTEREY PARK, CA 91754

Inspector Information

JOSE AVILA, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2021 Partial Approval WILLIAM KUEHN
Footing/Foundation/Slab 11/23/2021 Corrections Issued THOMAS FINNILA
Sewer 11/23/2021 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 12/1/2021 Approved JACK KARGODORIAN
Sewer 12/1/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval RAUL OLAGI
PLUMBING-Rough 12/8/2021 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 12/21/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 12/29/2021 Approved JOHN KIDWELL
HVAC-Rough 12/29/2021 Approved JOHN KIDWELL
PLUMBING-Rough 12/29/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/10/2022 Conditional Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/10/2022 Partial Approval CHRISTOPHE COCHRAN
Grading Pre-Inspection 1/11/2022 Not Ready for Inspection BRIAN MILLER
Excavation/Setback/Form/Re-Bar 1/14/2022 Approved MATT KELLERMAN
Green Building Rough 1/14/2022 Approved MATT KELLERMAN
Insulation 1/27/2022 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 2/1/2022 Approved JENNIFER RABUCHIN
Insulation 2/1/2022 Conditional Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 2/1/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 3/18/2022 Approved CALEB MEISTER
Insulation 3/18/2022 Approved CALEB MEISTER
Shower Pan 3/18/2022 Approved CALEB MEISTER
Service/Power Release 5/23/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 6/1/2022 Approved MICHEL ABAJAN
HVAC-Final 6/1/2022 Approved MICHEL ABAJAN
PLUMBING-Final 6/1/2022 Approved MICHEL ABAJAN
Green Building Final 7/29/2022 Corrections Issued MISAEL ESPARZA
Final 10/5/2022 Corrections Issued JOHN HAYES
Green Building Final 10/5/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 10/5/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 10/5/2022 Not Ready for Inspection JOHN HAYES
Final 2/22/2023 Corrections Issued JOHN HAYES
Green Building Final 2/22/2023 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 2/22/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 2/22/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 4/4/2023 Approved JOHN HAYES
Final 4/4/2023 OK to Issue CofO JOHN HAYES
Grading Pre-Inspection 4/4/2023 Approved JOHN HAYES
Green Building Final 4/4/2023 Approved JOHN HAYES
Masonry Wall/Backfill 4/4/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved JOHN HAYES
Service/Power Release 4/4/2023 Approved JOHN HAYES
Smoke Detectors 4/4/2023 Approved JOHN HAYES
Special/Order Compliance 4/10/2023 Corrections Issued JOHN HAYES