2580 W VENICE BLVD 90019
Certificate Information: 2580 W VENICE BLVD 90019
- Application / Permit
- 18010-20000-06158
- Plan Check / Job No.
- B18VN21741
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW 109'-6 1/2" X 54'-10", MAX HEIGHT 21'-4" RETAIL BUILDING - (CORE & SHELL ONLY)
- Permit Issued
- Issued on 6/8/2020
- Issuing Office
- Current Status
- CofO Issued on 2/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | MOHAMMAD FIROUZBAKHT |
| Corrections Issued | 1/22/2019 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 1/23/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 1/24/2019 | APPLICANT |
| Building Plans Picked Up | 1/31/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/31/2019 | APPLICANT |
| Applicant returned to address corrections | 6/26/2019 | JOHNNY WU |
| Applicant returned to address corrections | 6/27/2019 | JOHNNY WU |
| Applicant returned to address corrections | 7/2/2019 | JOHNNY WU |
| Applicant returned to address corrections | 7/9/2019 | JOHNNY WU |
| Applicant returned to address corrections | 7/10/2019 | JOHNNY WU |
| Applicant returned to address corrections | 7/30/2019 | JOHNNY WU |
| Applicant returned to address corrections | 8/1/2019 | JOHNNY WU |
| Applicant returned to address corrections | 9/13/2019 | JOHNNY WU |
| Plan Check Approved | 9/27/2019 | JOHNNY WU |
| Issued | 6/8/2020 | APPLICANT |
| TCO Issued (Expire Date: 06-21-2022) | 12/23/2021 | ERNESTO CORRAL |
| TCO Revoked (Expire Date: 06-21-2022) | 12/23/2021 | ERNESTO CORRAL |
| CofO in Progress | 2/16/2022 | ERNESTO CORRAL |
| Permit Finaled | 2/16/2022 | ERNESTO CORRAL |
| CofO Issued | 2/16/2022 | ERNESTO CORRAL |
| Permit Finaled | 2/16/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Permit | Cleared | 3/14/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2019 | ELAINE LEI |
| Highway dedication | Cleared | 3/21/2019 | ELAINE LEI |
| Green Code | Cleared | 6/11/2019 | DAVID MATSON |
| Sewer availability | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 6/18/2019 | GEORGE SUCHAND |
| ZI | Cleared | 6/18/2019 | SOPHIE GABEL-SCHEINBAU |
| Comm Cor/Mini-Mall | Cleared | 9/6/2019 | LATANYA ROUX |
| Comm Cor/Mini-Mall | Cleared | 9/6/2019 | LATANYA ROUX |
| ZA Case | Cleared | 9/6/2019 | LATANYA ROUX |
| Low Impact Development | Cleared | 9/11/2019 | JORGE MEJIA LEMUS |
| DAS Clearance | Cleared | 9/16/2019 | MOHAMMAD FIROUZBAKHT |
| Roof/Waste drainage to street | Cleared | 9/19/2019 | EMIL KYUPELYAN |
Contact Information
| Architect | Epstein,, Matthew D; Lic. No.: C29433 | 18100 BURBANK BLVD #22 TARZANA, CA 91356 |
| Contractor | Dynamic Design Build Inc; Lic. No.: 747205-B | 11777 SAN VICENTE BLVD STE 800 LOS ANGELES, CA 90049 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Peyton,, David E; Lic. No.: S3288 | 5722 E THE TOLEDO LONG BEACH, CA 90803 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/21/2020 | Partial Approval | RAFAEL ESPINOZA |
| METHANE-Barrier | 9/21/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Subgrade | 9/21/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Deputy Methane Barrier | 9/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| METHANE-Rough | 9/28/2020 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Methane Barrier | 9/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 10/7/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Barrier | 10/7/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 10/7/2020 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 10/16/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 10/19/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 10/19/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 10/21/2020 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 10/26/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 10/27/2020 | Partial Approval | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 10/30/2020 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 11/20/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 11/20/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 11/20/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 11/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Insulation | 12/15/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/17/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Insulation | 12/18/2020 | Partial Approval | RAFAEL ESPINOZA |
| Special/Order Compliance | 12/18/2020 | Approved | RAFAEL ESPINOZA |
| Insulation | 12/28/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 1/7/2021 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 1/14/2021 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 1/19/2021 | Approved | RAFAEL ESPINOZA |
| Final | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Final | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Final | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Rough | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Not Ready | RAFAEL ESPINOZA |
| Smoke Detectors | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 8/18/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 8/20/2021 | Partial Approval | RAFAEL ESPINOZA |
| Final | 9/30/2021 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 9/30/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Final | 9/30/2021 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 9/30/2021 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Not Ready | RAFAEL ESPINOZA |
| Smoke Detectors | 9/30/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 9/30/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 9/30/2021 | Partial Approval | RAFAEL ESPINOZA |
| Final | 10/12/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Final | 10/12/2021 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | RAFAEL ESPINOZA |
| Smoke Detectors | 10/12/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 10/12/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 10/12/2021 | Partial Approval | RAFAEL ESPINOZA |
| Special/Order Compliance | 12/21/2021 | Approved | TED RIES |
| Final | 12/22/2021 | Conditional Approval | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV No Gas | TED RIES |
| Smoke Detectors | 12/22/2021 | Approved | TED RIES |
| Verify Sprinkler Sign Off | 12/22/2021 | Approved | TED RIES |
| Wood Frame | 12/22/2021 | Approved | TED RIES |