13713 W OXNARD ST 91401
Certificate Information: 13713 W OXNARD ST 91401
- Application / Permit
- 18010-20000-06115
- Plan Check / Job No.
- B18VN21704
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 4 STORY 16 UNIT APARTMENT WITH ON GRADE PARKING
- Permit Issued
- Issued on 12/18/2020
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 1/3/2019 | APPLICANT |
| Corrections Issued | 1/14/2019 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 1/17/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 1/17/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 2/5/2019 | APPLICANT |
| Plan Check Approved | 12/2/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 12/18/2020 | APPLICANT |
| TCO Issued (Expire Date: 03-16-2023) | 9/17/2022 | JEFFREY DURAN |
| CofO in Progress | 3/10/2023 | JOHN KITCKO |
| Permit Finaled | 3/29/2023 | RICKEY JACKSON |
| CofO Issued | 3/29/2023 | RICKEY JACKSON |
| Permit Finaled | 3/29/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/31/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 2/6/2019 | JOHN DALLAS |
| Building over 3-story or 36-ft | Cleared | 2/15/2019 | CALOSHA APPROVED |
| Highway dedication | Cleared | 3/7/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 8/15/2019 | COLIN LOREDO |
| DAS Clearance | Cleared | 9/12/2019 | VLADIMIR ARUTYUNYAN |
| Density Bonus 12.22.A.25 | Cleared | 11/12/2019 | KENNETH LE |
| Low Impact Development | Cleared | 11/14/2019 | JORGE MEJIA LEMUS |
| Fire Marshall Fire Life Safety | Cleared | 9/23/2020 | WILLIAM JOHNS |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | GUILLERMO PETRA |
| Permit | Cleared | 10/16/2020 | MARKOS PEREZ-BRAN |
| "Q" conditions | Cleared | 11/4/2020 | LAUREN PADICK |
| "T" removal | Cleared | 11/4/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 11/4/2020 | LAUREN PADICK |
Contact Information
| Contractor | K P D Builders Inc; Lic. No.: 1051760-B | 7203 N RUBIO AVENUE #101 LAKE BALBOA, CA 91406 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 1/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/5/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 3/15/2021 | Partial Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 3/16/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 3/25/2021 | Partial Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 3/30/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 3/31/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 4/1/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/5/2021 | Conditional Approval | RICKEY JACKSON |
| Deputy Reinf. Masonry | 4/5/2021 | Conditional Approval | RICKEY JACKSON |
| Deputy Reinf. Concrete | 4/6/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 4/6/2021 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 4/6/2021 | Partial Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 4/7/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 4/7/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 4/8/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 4/8/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/9/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 4/9/2021 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 4/12/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Masonry | 4/13/2021 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/13/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/16/2021 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 4/23/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 6/2/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 6/3/2021 | Conditional Approval | ROBERT DAVIS |
| Green Building Rough | 6/3/2021 | No Access for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 6/3/2021 | Conditional Approval | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 6/3/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/4/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 6/17/2021 | Approved | JOHN KITCKO |
| Deputy Wood Construction | 6/21/2021 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 6/30/2021 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/1/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 7/1/2021 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 7/1/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Wood Construction | 7/2/2021 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 7/6/2021 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 7/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Wood Construction | 7/14/2021 | Conditional Approval | JEFFREY DURAN |
| Green Building Rough | 7/14/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 7/14/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/14/2021 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 8/3/2021 | Approved | JOHN KITCKO |
| Deputy Wood Construction | 8/4/2021 | Approved | JOHN KITCKO |
| Deputy Wood Construction | 8/5/2021 | Approved | JOHN KITCKO |
| Green Building Rough | 8/6/2021 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 8/6/2021 | Approved | JOHN KITCKO |
| Wood Frame | 8/6/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 8/13/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 8/13/2021 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 8/17/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 8/17/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 8/23/2021 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 9/3/2021 | Conditional Approval | JOHN KITCKO |
| Green Building Rough | 9/3/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 9/3/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 9/15/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 9/28/2021 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | JOHN KITCKO |
| Deputy Wood Construction | 10/1/2021 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 10/8/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/8/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 10/12/2021 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 10/15/2021 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 10/19/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/20/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 10/26/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 10/26/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/28/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/29/2021 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 11/1/2021 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 11/1/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 11/2/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 11/2/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 11/3/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 11/9/2021 | Partial Approval | KENNETH ROBERTS |
| Green Building Rough | 11/16/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 11/16/2021 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 11/22/2021 | Partial Approval | JOHN KITCKO |
| Insulation | 11/22/2021 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 11/24/2021 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 12/6/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 12/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 12/7/2021 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/10/2021 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 12/16/2021 | Partial Approval | JOHN KITCKO |
| Wood Frame | 12/16/2021 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 12/17/2021 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/21/2021 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 3/17/2022 | Partial Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 3/22/2022 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 5/12/2022 | Partial Approval | JOHN KITCKO |
| Final | 7/6/2022 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/6/2022 | Approved | JOHN KITCKO |
| Green Building Final | 7/6/2022 | Approved | JOHN KITCKO |
| Green Building Rough | 7/6/2022 | Approved | JOHN KITCKO |
| Reinforced Concrete Frame | 7/6/2022 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 7/6/2022 | Approved | JOHN KITCKO |
| Wood Frame | 7/6/2022 | Approved | JOHN KITCKO |
| Final | 8/17/2022 | Not Ready for Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | JOHN KITCKO |
| Special/Order Compliance | 2/15/2023 | Partial Inspection | JOHN KITCKO |
| Final | 3/9/2023 | Partial Inspection | JOHN KITCKO |
| Final | 3/10/2023 | OK to Issue CofO | JOHN KITCKO |