128 N LAUREL AVE 90048

Certificate Information: 128 N LAUREL AVE 90048

Application / Permit
18010-20000-06069
Plan Check / Job No.
B18VN21613
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/BASEMENT & ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 6/17/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2018 APPLICANT
Assigned to Plan Check Engineer 12/27/2018 NILOOFAR MEHRAIN
Corrections Issued 1/2/2019 NILOOFAR MEHRAIN
Quality Review Completed 1/2/2019 CHON CHIO KUO
Building Plans Picked Up 1/2/2019 APPLICANT
Green Plans Picked Up 1/2/2019 APPLICANT
Applicant returned to address corrections 2/14/2019 NILOOFAR MEHRAIN
Plan Check Approved 3/20/2019 NILOOFAR MEHRAIN
Issued 6/17/2019 LADBS
CofO in Progress 4/28/2021 EVAN COOPER
Permit Finaled 5/12/2021 KENNETH NAGLE
CofO Issued 5/12/2021 KENNETH NAGLE
Permit Finaled 5/12/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 1/16/2019 APEKSHYA BAJRACHARYA
CPC Cleared 1/16/2019 SHEILA GERSHON
CPC Cleared 1/16/2019 SHEILA GERSHON
Eng Process Fee Ord 176,300 Cleared 1/16/2019 APEKSHYA BAJRACHARYA
Permit Cleared 1/16/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/16/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 1/31/2019 OSCAR SALGADO JR
Green Code Cleared 2/13/2019 MICHAEL AYERS
Excavation more than 5-ft deep Cleared 2/14/2019 CALOSHA APPROVED
Low Impact Development Cleared 2/14/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 2/19/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor New Horizon Development Inc; Lic. No.: 937911-B 316 N CRESCENT HEIGHTS BLVD      LOS ANGELES, CA 90048
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Valencia,, Byron Steve; Lic. No.: C87372 13719 OXNARD ST 101      VAN NUYS, CA 91401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/30/2019 Partial Approval EVAN COOPER
Deputy Methane Barrier 11/25/2019 Approved KEVIN BEAULIEU
Deputy Methane Barrier 11/26/2019 No Access for Inspection ROBERT SHELLY
Deputy Methane Barrier 12/2/2019 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 12/27/2019 Partial Approval EVAN COOPER
METHANE-Barrier 12/27/2019 Partial Approval EVAN COOPER
METHANE-Subgrade 12/27/2019 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 12/31/2019 Conditional Approval EVAN COOPER
Deputy Drilled-In Anchors 1/29/2020 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/29/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval EVAN COOPER
Deputy Steel/Welding 3/19/2020 Conditional Approval RONALD WEBER
Deputy Steel/Welding 3/23/2020 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 5/12/2020 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 5/12/2020 Approved EVAN COOPER
Green Building Rough 5/12/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 5/12/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 5/12/2020 Approved EVAN COOPER
PLUMBING-Rough 5/12/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 5/12/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 5/14/2020 Approved EVAN COOPER
PLUMBING-Rough 5/14/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 5/18/2020 Corrections Issued EVAN COOPER
Green Building Rough 5/18/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 6/2/2020 Partial Approval KENNETH NAGLE
Interior/Exterior Lathing 6/3/2020 Partial Approval KENNETH NAGLE
Shower Pan 6/3/2020 Approved KENNETH NAGLE
BUILDING-Rough-Frame 6/5/2020 Partial Approval EVAN COOPER
Green Building Rough 6/5/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 6/5/2020 Not Ready for Inspection EVAN COOPER
Insulation 6/12/2020 Not Ready for Inspection EVAN COOPER
Insulation 6/16/2020 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 6/24/2020 Partial Approval OGANES TARAKHCHYAN
Insulation 7/9/2020 Approved KEVIN SARGSYAN
Drywall Nailing 7/14/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/31/2020 Approved EVAN COOPER
HVAC-Final 12/11/2020 Partial Approval EVAN COOPER
ELECTRICAL-Final 12/15/2020 Approved EVAN COOPER
PLUMBING-Final 12/18/2020 Corrections Issued EVAN COOPER
PLUMBING-Final 1/28/2021 Approved EVAN COOPER
Service/Power Release 3/12/2021 Approved KENNETH NAGLE
BUILDING-Rough-Frame 4/28/2021 Approved EVAN COOPER
Final 4/28/2021 OK to Issue CofO EVAN COOPER
Footing/Foundation/Slab 4/28/2021 Approved EVAN COOPER
Green Building Final 4/28/2021 Approved EVAN COOPER
Green Building Rough 4/28/2021 Approved EVAN COOPER
METHANE-Barrier 4/28/2021 Approved EVAN COOPER
METHANE-Subgrade 4/28/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 4/28/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 4/28/2021 Approved EVAN COOPER