128 N LAUREL AVE 90048
Certificate Information: 128 N LAUREL AVE 90048
- Application / Permit
- 18010-20000-06069
- Plan Check / Job No.
- B18VN21613
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/BASEMENT & ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 6/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/2/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/2/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 1/2/2019 | APPLICANT |
| Green Plans Picked Up | 1/2/2019 | APPLICANT |
| Applicant returned to address corrections | 2/14/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/20/2019 | NILOOFAR MEHRAIN |
| Issued | 6/17/2019 | LADBS |
| CofO in Progress | 4/28/2021 | EVAN COOPER |
| Permit Finaled | 5/12/2021 | KENNETH NAGLE |
| CofO Issued | 5/12/2021 | KENNETH NAGLE |
| Permit Finaled | 5/12/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2019 | APEKSHYA BAJRACHARYA |
| CPC | Cleared | 1/16/2019 | SHEILA GERSHON |
| CPC | Cleared | 1/16/2019 | SHEILA GERSHON |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2019 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 1/16/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/16/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/31/2019 | OSCAR SALGADO JR |
| Green Code | Cleared | 2/13/2019 | MICHAEL AYERS |
| Excavation more than 5-ft deep | Cleared | 2/14/2019 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 2/14/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/19/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | New Horizon Development Inc; Lic. No.: 937911-B | 316 N CRESCENT HEIGHTS BLVD LOS ANGELES, CA 90048 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 13719 OXNARD ST 101 VAN NUYS, CA 91401 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/30/2019 | Partial Approval | EVAN COOPER |
| Deputy Methane Barrier | 11/25/2019 | Approved | KEVIN BEAULIEU |
| Deputy Methane Barrier | 11/26/2019 | No Access for Inspection | ROBERT SHELLY |
| Deputy Methane Barrier | 12/2/2019 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 12/27/2019 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 12/27/2019 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 12/27/2019 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 12/31/2019 | Conditional Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 1/29/2020 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/29/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 3/19/2020 | Conditional Approval | RONALD WEBER |
| Deputy Steel/Welding | 3/23/2020 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/12/2020 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/12/2020 | Approved | EVAN COOPER |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/12/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 5/12/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/12/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/12/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/14/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/14/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/18/2020 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 5/18/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/18/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 6/2/2020 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/3/2020 | Partial Approval | KENNETH NAGLE |
| Shower Pan | 6/3/2020 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/5/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/5/2020 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 6/12/2020 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 6/16/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 6/24/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 7/9/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 7/14/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/31/2020 | Approved | EVAN COOPER |
| HVAC-Final | 12/11/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 12/15/2020 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/18/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 1/28/2021 | Approved | EVAN COOPER |
| Service/Power Release | 3/12/2021 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/28/2021 | Approved | EVAN COOPER |
| Final | 4/28/2021 | OK to Issue CofO | EVAN COOPER |
| Footing/Foundation/Slab | 4/28/2021 | Approved | EVAN COOPER |
| Green Building Final | 4/28/2021 | Approved | EVAN COOPER |
| Green Building Rough | 4/28/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 4/28/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 4/28/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/28/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/28/2021 | Approved | EVAN COOPER |