20111 W DELITA DR 91364

Certificate Information: 20111 W DELITA DR 91364

Application / Permit
18010-20000-06058
Plan Check / Job No.
B18VN21582
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 49' 8" X 27' 6" IRREGULAR-SHAPED SINGLE FAMILY DWELLING AND 11' 5" X 19' 1" 1-CAR GARAGE PER SB9. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/8/2022
Issuing Office
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 GURUNATH NESARAJAH
Corrections Issued 2/12/2019 GURUNATH NESARAJAH
Quality Review Completed 2/12/2019 OMID HEDAYAT
Green Plans Picked Up 2/12/2019 APPLICANT
Applicant returned to address corrections 12/25/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 2/3/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 3/4/2022 GURUNATH NESARAJAH
Building Plans Picked Up 3/4/2022 APPLICANT
Plan Check Approved 3/16/2022 GURUNATH NESARAJAH
No Progress 5/11/2022 GURUNATH NESARAJAH
Plan Check Approved 5/23/2022 GURUNATH NESARAJAH
Issued 6/8/2022 APPLICANT
CofO in Progress 3/3/2024 MORRIS JACKSON
CofO in Progress 4/10/2024 SEAN WIRCH
Permit Finaled 4/10/2024 JOHN JANSON
CofO Issued 4/10/2024 JOHN JANSON
Permit Finaled 4/10/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/24/2021 ABDULLAH SADOZAI
BHO/Hillside ordinance Cleared 6/24/2021 ABDULLAH SADOZAI
BHO/Hillside ordinance Cleared 6/24/2021 ABDULLAH SADOZAI
BHO/Hillside ordinance Cleared 6/24/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 6/24/2021 ABDULLAH SADOZAI
Permit Cleared 6/24/2021 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 6/25/2021 KURT CORRAL
Distance to fire station Cleared 6/28/2021 GILBERT URREA
ZI Cleared 7/1/2021 NOAH MCCOY
Trees in Parkway Cleared 8/11/2021 GURUNATH NESARAJAH
Low Impact Development Cleared 9/22/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/27/2021 ABDULLAH SADOZAI
Sewer availability Cleared 12/15/2021 ABDULLAH SADOZAI
GPI Written Notices Cleared 2/3/2022 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 2/3/2022 GURUNATH NESARAJAH
Green Code Cleared 2/3/2022 PARISA ZAHABI
BHO/Hillside ordinance Cleared 5/17/2022 ABDULLAH SADOZAI
BHO/Hillside ordinance Cleared 5/17/2022 ABDULLAH SADOZAI
Street width determination Cleared 5/17/2022 ABDULLAH SADOZAI

Contact Information

Contractor Valenzuela Pancho Construction; Lic. No.: 1067736-B 544 ORANGE GROVE AVE      SAN FERNANDO, CA 91340
Engineer Yepremian,, Shaun J; Lic. No.: C66912 7653 MARY ELLEN AVENUE      NORTH HOLLYWOOD, CA 91605

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 8/4/2022 Partial Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 8/4/2022 Partial Approval DAVID SANDOVAL
Wood Frame 8/12/2022 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Approved PETER FOLLING
PLUMBING-Rough 9/26/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 10/14/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 10/14/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 10/14/2022 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 10/14/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 11/8/2022 Approved PETER FOLLING
Interior/Exterior Lathing 11/8/2022 Not Ready for Inspection PETER FOLLING
Wood Frame 11/8/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 11/17/2022 Approved PETER FOLLING
Green Building Rough 11/17/2022 Approved PETER FOLLING
Interior/Exterior Lathing 11/17/2022 Partial Approval PETER FOLLING
Shower Pan 11/17/2022 Approved PETER FOLLING
Special/Order Compliance 11/17/2022 Partial Inspection JESUS PINEDA
Insulation 11/23/2022 Approved MORRIS JACKSON
Drywall Nailing 12/1/2022 Approved MORRIS JACKSON
Final 3/1/2024 OK to Issue CofO MORRIS JACKSON
Green Building Final 3/1/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved MORRIS JACKSON
Service/Power Release 3/1/2024 Approved MORRIS JACKSON
Smoke Detectors 3/1/2024 Approved MORRIS JACKSON