12345 W ADDISON ST 91607
Certificate Information: 12345 W ADDISON ST 91607
- Application / Permit
- 18010-20000-05998
- Plan Check / Job No.
- B18VN21407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 58'-6" x 35'-6" IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE AND TRELLIS PER Tentative Tract No.: 60421 ." NFPA-13D FIRE SPRINKLERS THRU-OUT".
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 1/24/2019 | APPLICANT |
| Corrections Issued | 1/25/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 1/25/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/17/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/1/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| Plan Check Approved | 4/25/2022 | SARKIS HARABEDIAN |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 7/16/2024 | RYAN SALAZAR |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2021 | LEE GUILBEAUX |
| Highway dedication | Cleared | 7/1/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/1/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 7/1/2021 | LEE GUILBEAUX |
| Permit | Cleared | 7/1/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/1/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/10/2021 | LEE GUILBEAUX |
| Specific Plan | Cleared | 7/19/2021 | CORREY KITCHENS |
| Trees in Parkway | Cleared | 8/19/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/3/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 10/22/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/27/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 12/21/2021 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/1/2022 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 1/4/2023 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 2/6/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 2/6/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 2/6/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 2/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 2/15/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 2/15/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/10/2023 | Conditional Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 3/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/21/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/31/2023 | Approved | KIRK SANDERS |
| Shower Pan | 3/31/2023 | Approved | KIRK SANDERS |
| Insulation | 4/18/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 4/24/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 4/28/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/28/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 4/28/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 5/8/2023 | Approved | MISAEL ESPARZA |
| Sewer | 8/2/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 2/2/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 2/2/2024 | Corrections Issued | JOSE AVILA |
| Gas Test | 2/6/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 3/14/2024 | Approved | JOSE AVILA |
| HVAC-Final | 3/14/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 3/14/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | JOSE AVILA |
| HVAC-Final | 4/10/2024 | Approved | JOSE AVILA |
| Service/Power Release | 4/16/2024 | Approved | JUAN VALENZUELA |
| Final | 7/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 7/15/2024 | OK to Issue CofO | RYAN SALAZAR |