12341 W ADDISON ST 91607

Certificate Information: 12341 W ADDISON ST 91607

Application / Permit
18010-20000-05997
Plan Check / Job No.
B18VN21407
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 58'-6" x 35'-6" IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE AND TRELLIS Tentative Tract No.: 60421 ." NFPA-13D FIRE SPRINKLERS THRU-OUT".
Permit Issued
Issued on 6/17/2022
Issuing Office
Current Status
CofO Issued on 5/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 SARKIS HARABEDIAN
Green Plans Picked Up 1/24/2019 APPLICANT
Corrections Issued 1/25/2019 SARKIS HARABEDIAN
Quality Review Completed 1/25/2019 OMID HEDAYAT
Applicant returned to address corrections 12/17/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 3/1/2022 SARKIS HARABEDIAN
Building Plans Picked Up 3/3/2022 APPLICANT
Plan Check Approved 4/25/2022 SARKIS HARABEDIAN
Issued 6/17/2022 APPLICANT
CofO in Progress 4/26/2024 JOSE AVILA
Permit Finaled 5/30/2024 RUBEN SALAS
CofO Issued 5/30/2024 RUBEN SALAS
Permit Finaled 5/30/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2021 LEE GUILBEAUX
Highway dedication Cleared 7/1/2021 LEE GUILBEAUX
Miscellaneous Cleared 7/1/2021 LAUREN PADICK
Permit Cleared 7/1/2021 LEE GUILBEAUX
ZA Case Cleared 7/1/2021 LAUREN PADICK
Public Works-Highway Ded. Cleared 7/1/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/10/2021 LEE GUILBEAUX
Sewer availability Cleared 7/10/2021 LEE GUILBEAUX
Specific Plan Cleared 7/19/2021 CORREY KITCHENS
Trees in Parkway Cleared 8/19/2021 JOHN KIM
Hydrant and Access approval Cleared 9/3/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/21/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/27/2021 CARLOS AGUILERA
Green Code Cleared 12/19/2021 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/1/2022 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/14/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval JOHN COLEMAN
Wood Frame 12/5/2022 Partial Approval JOHN COLEMAN
Deputy Wood Construction 1/4/2023 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 2/6/2023 Approved KIRK SANDERS
HVAC-Rough 2/6/2023 Approved KIRK SANDERS
PLUMBING-Rough 2/6/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 2/15/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Approved KIRK SANDERS
Green Building Rough 2/15/2023 Approved KIRK SANDERS
PLUMBING-Rough 2/15/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 2/15/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 3/14/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 3/21/2023 Partial Approval JACK KARGODORIAN
Shower Pan 3/31/2023 Approved KIRK SANDERS
Insulation 4/18/2023 Corrections Issued THOMAS FINNILA
Insulation 4/24/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/28/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 4/28/2023 Approved KIRK SANDERS
Drywall Nailing 5/8/2023 Approved MISAEL ESPARZA
Underground Mechanical 5/8/2023 Not Ready for Inspection MISAEL ESPARZA
Sewer 5/11/2023 Approved KIRK SANDERS
Underground Mechanical 5/11/2023 Approved KIRK SANDERS
ELECTRICAL-Final 2/2/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/2/2024 Corrections Issued JOSE AVILA
Gas Test 2/6/2024 Approved JOSE AVILA
ELECTRICAL-Final 3/14/2024 Approved JOSE AVILA
HVAC-Final 3/14/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 3/14/2024 Approved JOSE AVILA
HVAC-Final 4/10/2024 Approved JOSE AVILA
Service/Power Release 4/16/2024 Approved JUAN VALENZUELA
Final 4/25/2024 OK to Issue CofO JOSE AVILA
Footing/Foundation/Slab 4/25/2024 Approved JOSE AVILA
Green Building Final 4/25/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 4/25/2024 Approved JOSE AVILA