12401 W MATTESON AVE 1-7 90066
Certificate Information: 12401 W MATTESON AVE 1-7 90066
- Application / Permit
- 18010-20000-05991
- Plan Check / Job No.
- B18VN21400
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 59'8" X 41'2" 3 STORY , 7 UNIT APARTMENT BUILDING TYPE VA OVER PARKING GARAGE , TYPE I A, NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | ABDUL CHEGENI |
| Disabled Access Plans Picked Up | 1/18/2019 | APPLICANT |
| Green Plans Picked Up | 1/18/2019 | APPLICANT |
| Corrections Issued | 2/1/2019 | ABDUL CHEGENI |
| Quality Review Completed | 2/6/2019 | STEVEN KIM |
| Building Plans Picked Up | 2/7/2019 | APPLICANT |
| Applicant returned to address corrections | 8/3/2021 | RARES BODEA |
| Applicant returned to address corrections | 10/27/2021 | RARES BODEA |
| Plan Check Approved | 12/27/2021 | RARES BODEA |
| Issued | 12/29/2021 | APPLICANT |
| CofO in Progress | 4/24/2023 | DERRICK SPENCER |
| Permit Finaled | 4/28/2023 | DAVID TSAU |
| CofO Issued | 4/28/2023 | DAVID TSAU |
| Permit Finaled | 4/28/2023 | DAVID TSAU |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/26/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 12/3/2020 | ANTHONY MAINEZ |
| Permit | Cleared | 12/3/2020 | ANTHONY MAINEZ |
| Highway dedication | Cleared | 7/12/2021 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/28/2021 | HISASHI KOBAYAKAWA |
| Frnt yard landscape/Water mgmt | Cleared | 8/5/2021 | DANG NGUYEN |
| Opn space landscape/Water mgmt | Cleared | 8/5/2021 | DANG NGUYEN |
| Green Code | Cleared | 8/31/2021 | PARISA ZAHABI |
| Fire Marshall Fire Life Safety | Cleared | 10/5/2021 | WILLIAM JOHNS |
| Low Impact Development | Cleared | 10/14/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 10/22/2021 | DENNIS BRAGIN |
| DAS Clearance | Cleared | 11/22/2021 | ABDUL CHEGENI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/13/2022 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 1/13/2022 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 1/19/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Rough | 1/19/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 1/19/2022 | Partial Approval | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 1/19/2022 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 1/20/2022 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Masonry | 1/24/2022 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 1/25/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Masonry Frame | 1/25/2022 | Conditional Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 2/7/2022 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 3/8/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 3/8/2022 | Partial Approval | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 3/10/2022 | Approved | JEFF BYTHEWAY |
| Deputy Wood Construction | 3/25/2022 | Approved | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | JEFF BYTHEWAY |
| Deputy Wood Construction | 4/18/2022 | Approved | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Approved | JEFF BYTHEWAY |
| Wood Frame | 6/30/2022 | Partial Approval | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 7/20/2022 | Partial Approval | NICK LAROCCA |
| Green Building Rough | 7/27/2022 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 7/27/2022 | Partial Approval | JEFF BYTHEWAY |
| Green Building Rough | 8/29/2022 | Approved | JEFF BYTHEWAY |
| Wood Frame | 8/29/2022 | Partial Inspection | JEFF BYTHEWAY |
| Insulation | 9/2/2022 | Approved | JEFF BYTHEWAY |
| Drywall Nailing | 9/15/2022 | Approved | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 9/15/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 9/22/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 1/5/2023 | Approved | DERRICK SPENCER |
| Final | 3/30/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 3/30/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Reinforced Concrete Frame | 3/30/2023 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 3/30/2023 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 3/30/2023 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 3/30/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 3/30/2023 | Approved | DERRICK SPENCER |
| Final | 4/14/2023 | OK to Issue CofO | DERRICK SPENCER |
| Green Building Final | 4/14/2023 | Approved | DERRICK SPENCER |