11612 N MANCHESTER WAY 91326

Certificate Information: 11612 N MANCHESTER WAY 91326

Application / Permit
18010-20000-05942
Plan Check / Job No.
B18VN21205
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED 3 CAR GARAGE (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D)_STANDARD PLAN # 643 _ PLAN 8D
Permit Issued
Issued on 3/7/2019
Issuing Office
Valley
Current Status
CofO Corrected on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2018 APPLICANT
Assigned to Plan Check Engineer 12/19/2018 DAWN MC NULTY
Plans on Hold 12/20/2018 OMID HEDAYAT
Hold Released 1/7/2019 DAWN MC NULTY
Green Plans Picked Up 1/8/2019 APPLICANT
Corrections Issued 1/9/2019 DAWN MC NULTY
Quality Review Completed 1/10/2019 CHON CHIO KUO
Building Plans Picked Up 1/16/2019 APPLICANT
Applicant returned to address corrections 1/29/2019 DAWN MC NULTY
Plan Check Approved 3/7/2019 DAWN MC NULTY
Issued 3/7/2019 LADBS
CofO in Progress 3/2/2020 DONALD SUNSERI
CofO Issued-Status Void 3/5/2020 DONALD SUNSERI
Permit Finaled-Status Void 3/5/2020 DONALD SUNSERI
Re-Activate Permit 11/21/2020 DONALD SUNSERI
Permit Finaled 11/21/2020 DONALD SUNSERI
CofO Corrected 11/21/2020 DONALD SUNSERI

Permit Application Clearance Information

"T" removal Cleared 1/30/2019 EDBER MACEDO
CPC Cleared 1/30/2019 EDBER MACEDO
Miscellaneous Cleared 1/30/2019 EDBER MACEDO
Miscellaneous Cleared 1/30/2019 EDBER MACEDO
Miscellaneous Cleared 1/30/2019 EDBER MACEDO
Specific Plan Cleared 1/30/2019 EDBER MACEDO
Tract Map conditions Cleared 1/30/2019 EDBER MACEDO
ZA Case Cleared 1/30/2019 EDBER MACEDO
ZA Case Cleared 1/30/2019 EDBER MACEDO
Hydrant and Access approval Cleared 2/21/2019 ROBERT DUFF
Low Impact Development Cleared 2/27/2019 AMMAR ELTAWIL
Address approval Cleared 2/28/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/28/2019 LEE GUILBEAUX
Permit Cleared 2/28/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/28/2019 LEE GUILBEAUX
Sewer availability Cleared 2/28/2019 LEE GUILBEAUX
Green Code Cleared 3/5/2019 MICHAEL AYERS

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/2/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 8/5/2019 Not Ready for Inspection BRUCE ROZAK
Green Building Rough 8/5/2019 Not Ready for Inspection BRUCE ROZAK
Verify Sprinkler Sign Off 8/5/2019 Not Ready for Inspection BRUCE ROZAK
Footing/Foundation/Slab 8/21/2019 Approved BRUCE ROZAK
Sewer 8/28/2019 Approved BRUCE ROZAK
Deputy Pre-Stress Concrete 9/3/2019 Approved DONALD SUNSERI
Underground Mechanical 9/3/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 9/18/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Partial Approval BRUCE ROZAK
Deputy Wood Construction 11/1/2019 Partial Approval BRUCE ROZAK
ELECTRICAL-Rough 11/6/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 11/6/2019 Approved BRUCE ROZAK
HVAC-Rough 11/6/2019 Approved BRUCE ROZAK
PLUMBING-Rough 11/6/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 11/7/2019 Approved BRUCE ROZAK
Green Building Rough 11/7/2019 Approved BRUCE ROZAK
Verify Sprinkler Sign Off 11/7/2019 Approved BRUCE ROZAK
Drywall Nailing 11/15/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 11/15/2019 Approved BRUCE ROZAK
Gas Test 12/6/2019 Approved BRUCE ROZAK
Service/Power Release 12/26/2019 Approved BRUCE ROZAK
Service/Power Release 1/7/2020 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 1/10/2020 SGSOV Approved DONALD SUNSERI
ELECTRICAL-Final 2/12/2020 Approved SEAN WIRCH
HVAC-Final 2/12/2020 Approved SEAN WIRCH
Final 2/19/2020 Not Ready for Inspection SEAN WIRCH
Green Building Final 2/19/2020 Approved SEAN WIRCH
PLUMBING-Final 2/19/2020 Approved SEAN WIRCH
Smoke Detectors 2/19/2020 Approved SEAN WIRCH
Final 2/28/2020 OK to Issue CofO DONALD SUNSERI