21023 W SATICOY ST 91304

Certificate Information: 21023 W SATICOY ST 91304

Application / Permit
18010-20000-05875
Plan Check / Job No.
B18VN20999
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-0" X 40'-0" DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK DONE PER WFPP.
Permit Issued
Issued on 6/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2018 APPLICANT
Green Plans Picked Up 1/4/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 SARKIS HARABEDIAN
Corrections Issued 1/15/2019 SARKIS HARABEDIAN
Quality Review Completed 1/18/2019 OMID HEDAYAT
Building Plans Picked Up 1/23/2019 APPLICANT
Plan Check Approved 6/12/2019 SARKIS HARABEDIAN
Issued 6/12/2019 LADBS
CofO in Progress 6/6/2024 ALEXANDER HANDY
CofO Issued 7/24/2024 JOHN JANSON
Permit Finaled 7/24/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/1/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/1/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/1/2019 MARKOS PEREZ-BRAN
Green Code Cleared 4/11/2019 DAVID MATSON
Low Impact Development Cleared 4/11/2019 SARAH YOUSSEF
Hydrant and Access approval Cleared 6/4/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 6/4/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/7/2019 Corrections Issued JOHN JANSON
Footing/Foundation/Slab 11/7/2019 Not Ready for Inspection JOHN JANSON
Footing/Foundation/Slab 12/18/2019 Approved HENRY KIM
BUILDING-Rough-Frame 5/7/2020 Partial Approval HENRY KIM
Green Building Rough 5/7/2020 Not Ready for Inspection HENRY KIM
Verify Sprinkler Sign Off 5/7/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 5/13/2020 Partial Approval HENRY KIM
Verify Sprinkler Sign Off 5/13/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 5/18/2020 Partial Approval HENRY KIM
Green Building Rough 5/18/2020 No Access for Inspection HENRY KIM
Insulation 5/18/2020 Partial Approval HENRY KIM
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 9/21/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval HENRY KIM
Green Building Rough 9/21/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 3/12/2021 Corrections Issued HENRY KIM
Sewer 3/12/2021 Approved HENRY KIM
Underground Mechanical 3/12/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 3/17/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 3/17/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Corrections Issued HENRY KIM
HVAC-Rough 3/17/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 3/17/2021 Approved HENRY KIM
Underground Mechanical 3/17/2021 Partial Approval HENRY KIM
BUILDING-Rough-Frame 4/12/2021 Approved HENRY KIM
ELECTRICAL-Rough 4/12/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Approved HENRY KIM
Green Building Rough 4/12/2021 Approved HENRY KIM
HVAC-Rough 4/12/2021 Approved HENRY KIM
Interior/Exterior Lathing 4/12/2021 Approved HENRY KIM
Verify Sprinkler Sign Off 4/12/2021 Approved HENRY KIM
Insulation 5/17/2021 Approved STEPHANIE SWANSON
Drywall Nailing 6/14/2021 Approved HENRY KIM
Shower Pan 10/13/2021 Approved STEVEN BACK
Underground Mechanical 10/13/2021 Approved STEVEN BACK
Interior/Exterior Lathing 12/13/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Required MORRIS JACKSON
Final 1/4/2024 Corrections Issued ALEXANDER HANDY
Green Building Final 1/4/2024 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 1/4/2024 Not Required ALEXANDER HANDY
Smoke Detectors 1/4/2024 Approved ALEXANDER HANDY
Final 4/29/2024 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 4/29/2024 Not Ready for Inspection ALEXANDER HANDY
Final 5/28/2024 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 5/28/2024 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 6/5/2024 Approved ALEXANDER HANDY
Final 6/5/2024 OK to Issue CofO ALEXANDER HANDY
Green Building Final 6/5/2024 Approved ALEXANDER HANDY
HVAC-Final 6/5/2024 Approved ALEXANDER HANDY
PLUMBING-Final 6/5/2024 Approved ALEXANDER HANDY