7639 N BECK AVE 91605

Certificate Information: 7639 N BECK AVE 91605

Application / Permit
18010-20000-05834
Plan Check / Job No.
B18VN20733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (18'-0"x 27'6") DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
Permit Issued
Issued on 11/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 JOSE MENDOZA
Green Plans Picked Up 1/3/2019 APPLICANT
Corrections Issued 1/7/2019 JOSE MENDOZA
Quality Review Completed 1/11/2019 STEVEN KIM
Building Plans Picked Up 1/14/2019 APPLICANT
Plan Check Approved 10/30/2019 TROY DEGUZMAN
Issued 11/15/2019 LADBS
Permit Finaled 2/21/2026 MICHAEL PELHAM
CofO Issued 2/21/2026 MICHAEL PELHAM
Permit Finaled 2/21/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 1/18/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/18/2019 JOHN LIN
Hydrant and Access approval Cleared 1/18/2019 JOHN DALLAS
Sewer availability Cleared 1/18/2019 JOHN LIN
Construction near power lines Cleared 6/10/2019 RIDWAN HARDY
Green Code Cleared 9/27/2019 MICHAEL AYERS
Roof/Waste drainage to street Cleared 10/29/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Tabar,, Mehrdad; Lic. No.: C37433 14252 CULVER DR A349      IRVINE, CA 92604

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2020 Corrections Issued PIERRE VEGA
PLUMBING-Rough 5/5/2020 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 7/24/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 9/2/2020 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/30/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 12/11/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 12/11/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 12/11/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/11/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/11/2020 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 12/11/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/4/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 3/4/2021 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/4/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 3/4/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/4/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 3/4/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/20/2021 Approved JOHN HAYES
Green Building Rough 4/20/2021 Approved JOHN HAYES
Interior/Exterior Lathing 4/20/2021 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 4/20/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 4/20/2021 Approved JOHN HAYES
Insulation 7/1/2021 Approved JOHN HAYES
Drywall Nailing 7/7/2021 Approved MORRIS JACKSON
Sewer 7/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 7/18/2022 Approved WILLIAM WREN
Underground Mechanical 7/18/2022 Approved WILLIAM WREN
Underground Mechanical 6/23/2023 Approved MATTHEW NELSON
Final 3/1/2024 Corrections Issued MATTHEW NELSON
Green Building Final 3/1/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/1/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 3/1/2024 Approved MATTHEW NELSON
Final 3/8/2024 Partial Approval MATTHEW NELSON
Green Building Final 3/8/2024 Approved MATTHEW NELSON
Service/Power Release 3/8/2024 Approved MATTHEW NELSON