715 N ALFRED ST 1-8 90069
Certificate Information: 715 N ALFRED ST 1-8 90069
- Application / Permit
- 18010-20000-05774
- Plan Check / Job No.
- B18VN20506
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW TYPE VA, 8 UNIT 4-STORY, APT OVER TYPE IA SUBTERR. GARAGE. FULLY SPRINKLERED NFPA-13. COMPLY WITH DEPARTMENT ORDER effective date 03/10/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2018 | APPLICANT |
| Green Plans Picked Up | 1/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | RODNEY SAMIIAN |
| Disabled Access Plans Picked Up | 1/4/2019 | APPLICANT |
| Corrections Issued | 1/11/2019 | RODNEY SAMIIAN |
| Quality Review Completed | 1/14/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 1/16/2019 | APPLICANT |
| Applicant returned to address corrections | 6/25/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 7/24/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 8/12/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 8/13/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 9/9/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 9/20/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 10/24/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 5/29/2020 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/8/2020 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/15/2020 | RODNEY SAMIIAN |
| Plan Check Approved | 7/6/2020 | RODNEY SAMIIAN |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 6/17/2024 | JAMES JENSEN |
| CofO in Progress | 6/17/2024 | DEXTER JACKSON |
| CofO Issued | 6/17/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/17/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2019 | JEANETTE VONG |
| Highway dedication | Cleared | 2/8/2019 | JEANETTE VONG |
| Permit | Cleared | 2/8/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 4/12/2019 | GEORGE SUCHAND |
| Opn space landscape/Water mgmt | Cleared | 7/10/2019 | MARITZA PRZEKOP |
| DAS Clearance | Cleared | 8/8/2019 | RODNEY SAMIIAN |
| Frnt yard landscape/Water mgmt | Cleared | 10/7/2019 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 10/23/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 12/6/2019 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 2/5/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/5/2020 | JOHN TRIANTAFYLLOS |
| "Q" conditions | Cleared | 5/5/2020 | MAY SIRINOPWONGSAGO |
| ZI | Cleared | 5/5/2020 | MAY SIRINOPWONGSAGO |
| Fire Marshall Fire Life Safety | Cleared | 5/14/2020 | VIDAL GARCIA |
| Work Adjacent to Public Way | Cleared | 5/28/2020 | ROSA SILVA |
| Building over 3-story or 36-ft | Cleared | 5/29/2020 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/29/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Rocha,, Carlos Joel; Lic. No.: C19775 | 28025 DOROTHY DRIVE SUITE 206 AGOURA HILLS, CA 91301 |
| Contractor | Rocha Nuez Abdoh Construction Inc; Lic. No.: 791474-B | 28025 DOROTHY DRIVE #100 AGOURA HILLS, CA 91301 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2021 | Conditional Approval | LARRY ARNICK |
| METHANE-Barrier | 1/21/2021 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 1/21/2021 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Reinf. Concrete | 4/26/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 5/5/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 5/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 5/7/2021 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 5/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 5/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 5/7/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Shotcrete | 5/11/2021 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 5/24/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 6/30/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 7/2/2021 | Partial Approval | RUSSELL BONVOULOIR |
| METHANE-Rough | 7/2/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 7/2/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 7/2/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 8/26/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 8/31/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/1/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/2/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/3/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/23/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/24/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 9/30/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/1/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/5/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/6/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/14/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/15/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/28/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 11/5/2021 | Conditional Approval | TED RIES |
| Green Building Rough | 11/5/2021 | Not Ready for Inspection | TED RIES |
| METHANE-Rough | 11/5/2021 | Not Ready for Inspection | TED RIES |
| Verify Sprinkler Sign Off | 11/5/2021 | Not Ready for Inspection | TED RIES |
| Wood Frame | 11/5/2021 | Partial Approval | TED RIES |
| Special/Order Compliance | 11/30/2021 | Approved | TED RIES |
| Deputy Steel/Welding | 12/3/2021 | Conditional Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 12/3/2021 | Approved | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | DAVID BURKHEAD |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 12/3/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 12/3/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Steel/Welding | 12/6/2021 | Conditional Approval | NICK DANERI |
| Deputy Steel/Welding | 12/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 12/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 12/9/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 12/10/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 1/6/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 1/7/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 1/7/2022 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 1/7/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Wood Construction | 2/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 4/1/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 4/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 5/24/2022 | Conditional Approval | ERNESTO CORRAL |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 6/14/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 6/14/2022 | Partial Inspection | EDWIN GREGORYONA |
| Insulation | 7/12/2022 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 9/22/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Insulation | 9/29/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 1/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 1/31/2023 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 7/28/2023 | Partial Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 8/17/2023 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 8/17/2023 | Approved | EDWIN GREGORYONA |
| Green Building Final | 5/6/2024 | Partial Inspection | EDWIN GREGORYONA |
| Final | 5/28/2024 | Conditional Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Green Building Final | 5/28/2024 | Approved | EDWIN GREGORYONA |
| METHANE-Barrier | 5/28/2024 | Approved | EDWIN GREGORYONA |
| METHANE-Subgrade | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 5/28/2024 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | EDWIN GREGORYONA |
| Wood Frame | 5/28/2024 | Approved | EDWIN GREGORYONA |