11260 N ADOBE LANE 91345
Certificate Information: 11260 N ADOBE LANE 91345
- Application / Permit
- 18010-20000-05762
- Plan Check / Job No.
- B18VN20450
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD/GARAGE, PLAN 2B, "Small lot subdivision pursuant to Tentative Tract Maps No 77105-SL. A certificate of occupancy (temporary or final) shall not be issued until after th efinal map has been recorded"
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | CHON CHIO KUO |
| Green Plans Picked Up | 12/19/2018 | APPLICANT |
| Corrections Issued | 12/27/2018 | CHON CHIO KUO |
| Quality Review Completed | 12/28/2018 | STEVEN KIM |
| Building Plans Picked Up | 12/28/2018 | APPLICANT |
| Applicant returned to address corrections | 2/14/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/24/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/3/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/7/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/21/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/23/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/6/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/13/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/20/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/25/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/27/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/9/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/18/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/25/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/2/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/16/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/17/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/25/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/26/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/10/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/14/2020 | CHON CHIO KUO |
| Plan Check Approved | 9/15/2020 | CHON CHIO KUO |
| Issued | 10/2/2020 | APPLICANT |
| CofO in Progress | 6/30/2021 | JOSEPH SAGEN |
| CofO Issued | 6/30/2021 | MICHAEL SMITH |
| Permit Finaled | 6/30/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/21/2019 | MARTIN FRAGOSO |
| Miscellaneous | Cleared | 5/7/2019 | CHON CHIO KUO |
| Hydrant and Access approval | Cleared | 5/16/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 5/22/2019 | MICHAEL AYERS |
| Address approval | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Highway dedication | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Miscellaneous | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Permit | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Work Adjacent to Public Way | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/17/2020 | GUILLERMO PETRA |
| Opn space landscape/Water mgmt | Cleared | 8/25/2020 | TERRI OSBORNE |
| Tract Map conditions | Cleared | 8/25/2020 | TERRI OSBORNE |
| ZA Case | Cleared | 8/25/2020 | TERRI OSBORNE |
| ZA Case | Cleared | 8/25/2020 | TERRI OSBORNE |
| ZA Case | Cleared | 8/25/2020 | TERRI OSBORNE |
| Building over 3-story or 36-ft | Cleared | 9/10/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Cunningham,, Gary Lynn; Lic. No.: C29285 | 18162 LILLIAN WAY TUSTIN, CA 92780 |
| Contractor | D R Horton America'S Builder; Lic. No.: 765023-B | 2280 WARDLOW CIRCLE STE 100 CORONA, CA 92880 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
| Engineer | Toney,, Noelle Camille; Lic. No.: C84700 | 2085 HIGHPOINTE DRIVE UNIT 204 CORONA, CA 92879 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/19/2020 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 10/19/2020 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 11/4/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Partial Approval | JOSEPH SAGEN |
| Deputy Pre-Stress Concrete | 12/21/2020 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 3/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Rough | 3/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Rough | 3/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 3/23/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 3/23/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 3/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Rough | 3/24/2021 | Approved | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 3/30/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Rough | 3/30/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 3/30/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Interior/Exterior Lathing | 4/8/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 4/9/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 4/9/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 4/9/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 4/15/2021 | Approved | JOSEPH SAGEN |
| Gas Test | 5/12/2021 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Approved | JOSEPH SAGEN |
| Service/Power Release | 5/24/2021 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 6/21/2021 | Approved | JOSEPH SAGEN |
| Final | 6/21/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 6/21/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 6/21/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 6/21/2021 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 6/21/2021 | Approved | JOSEPH SAGEN |
| Final | 6/29/2021 | OK to Issue CofO | JOSEPH SAGEN |