11225 N ALTA AVE 91345

Certificate Information: 11225 N ALTA AVE 91345

Application / Permit
18010-20000-05705
Plan Check / Job No.
B18VN20450
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD/GARAGE, PLAN 1, "Small lot subdivision pursuant to Tentative Tract Maps No 77105-SL. A certificate of occupancy (temporary or final) shall not be issued until after th efinal map has been recorded"
Permit Issued
Issued on 7/17/2020
Issuing Office
Current Status
CofO Issued on 4/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 CHON CHIO KUO
Green Plans Picked Up 12/19/2018 APPLICANT
Corrections Issued 12/27/2018 CHON CHIO KUO
Quality Review Completed 12/28/2018 STEVEN KIM
Building Plans Picked Up 12/28/2018 APPLICANT
Applicant returned to address corrections 2/14/2019 CHON CHIO KUO
Applicant returned to address corrections 4/24/2019 CHON CHIO KUO
Applicant returned to address corrections 5/3/2019 CHON CHIO KUO
Applicant returned to address corrections 5/7/2019 CHON CHIO KUO
Applicant returned to address corrections 5/21/2019 CHON CHIO KUO
Applicant returned to address corrections 5/23/2019 CHON CHIO KUO
Applicant returned to address corrections 6/6/2019 CHON CHIO KUO
Applicant returned to address corrections 6/13/2019 CHON CHIO KUO
Applicant returned to address corrections 6/20/2019 CHON CHIO KUO
Applicant returned to address corrections 6/25/2019 CHON CHIO KUO
Applicant returned to address corrections 6/27/2019 CHON CHIO KUO
Applicant returned to address corrections 8/9/2019 CHON CHIO KUO
Applicant returned to address corrections 9/18/2019 CHON CHIO KUO
Applicant returned to address corrections 9/25/2019 CHON CHIO KUO
Applicant returned to address corrections 12/2/2019 CHON CHIO KUO
Applicant returned to address corrections 1/16/2020 CHON CHIO KUO
Applicant returned to address corrections 3/17/2020 CHON CHIO KUO
Applicant returned to address corrections 3/25/2020 CHON CHIO KUO
Plan Check Approved 3/26/2020 CHON CHIO KUO
Issued 7/17/2020 APPLICANT
CofO in Progress 4/26/2021 JOSEPH SAGEN
Permit Finaled 4/26/2021 MICHAEL SMITH
CofO Issued 4/26/2021 MICHAEL SMITH
Permit Finaled 4/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 2/21/2019 MARTIN FRAGOSO
Address approval Cleared 4/9/2019 HOWARD COOPER
Miscellaneous Cleared 5/7/2019 CHON CHIO KUO
Hydrant and Access approval Cleared 5/16/2019 GEORGE SUCHAND
Green Code Cleared 5/22/2019 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 2/6/2020 ADRIAN CASTRO
Highway dedication Cleared 2/6/2020 ADRIAN CASTRO
Miscellaneous Cleared 2/6/2020 ADRIAN CASTRO
Permit Cleared 2/6/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/6/2020 ADRIAN CASTRO
Sewer availability Cleared 2/6/2020 ADRIAN CASTRO
Work Adjacent to Public Way Cleared 2/6/2020 ADRIAN CASTRO
Opn space landscape/Water mgmt Cleared 3/3/2020 TERRI OSBORNE
Tract Map conditions Cleared 3/3/2020 TERRI OSBORNE
ZA Case Cleared 3/3/2020 TERRI OSBORNE
ZA Case Cleared 3/3/2020 TERRI OSBORNE
ZA Case Cleared 3/3/2020 TERRI OSBORNE
Building over 3-story or 36-ft Cleared 3/26/2020 CALOSHA APPROVED

Contact Information

Architect Cunningham,, Gary Lynn; Lic. No.: C29285 18162 LILLIAN WAY      TUSTIN, CA 92780
Contractor D R Horton America'S Builder; Lic. No.: 765023-B 2280 WARDLOW CIRCLE STE 100      CORONA, CA 92880
Engineer Deihimi,, Amir Hossein; Lic. No.: C78194 23172 PLAZA POINTE DR STE 145      LAGUNA HILLS, CA 92653
Engineer Toney,, Noelle Camille; Lic. No.: C84700 2085 HIGHPOINTE DRIVE UNIT 204      CORONA, CA 92879

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/18/2020 Approved JOSEPH SAGEN
Underground Mechanical 9/18/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 10/9/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Partial Approval JOSEPH SAGEN
Insulation 12/22/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 1/26/2021 Approved JOSEPH SAGEN
HVAC-Rough 1/26/2021 Approved JOSEPH SAGEN
PLUMBING-Rough 1/26/2021 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 1/28/2021 Approved JOSEPH SAGEN
Green Building Rough 1/28/2021 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 1/28/2021 Approved JOSEPH SAGEN
Drywall Nailing 2/9/2021 Approved JOSEPH SAGEN
Interior/Exterior Lathing 2/12/2021 Partial Approval JOSEPH SAGEN
Gas Test 3/4/2021 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved JOSEPH SAGEN
Service/Power Release 4/6/2021 Approved JOSEPH SAGEN
HVAC-Final 4/14/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/14/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 4/23/2021 Approved JOSEPH SAGEN
Final 4/23/2021 OK to Issue CofO JOSEPH SAGEN
Green Building Final 4/23/2021 Approved JOSEPH SAGEN
HVAC-Final 4/23/2021 Approved JOSEPH SAGEN
PLUMBING-Final 4/23/2021 Approved JOSEPH SAGEN
Smoke Detectors 4/23/2021 Approved JOSEPH SAGEN