14927 W VOSE ST 91405

Certificate Information: 14927 W VOSE ST 91405

Application / Permit
18010-20000-05580
Plan Check / Job No.
B18VN19969
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 40' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 SELLA BENYAMIN
Green Plans Picked Up 12/20/2018 APPLICANT
Corrections Issued 12/27/2018 SELLA BENYAMIN
Quality Review Completed 12/27/2018 CHON CHIO KUO
Building Plans Picked Up 1/2/2019 APPLICANT
Plan Check Approved 6/29/2022 SELLA BENYAMIN
Issued 9/6/2023 APPLICANT
CofO in Progress 10/3/2025 RYAN SALAZAR
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/7/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/12/2021 CARLOS AGUILERA
Sewer availability Cleared 10/12/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/10/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 2/28/2022 CARLOS AGUILERA
Low Impact Development Cleared 6/10/2022 TA ANH
Construction near power lines Cleared 6/29/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/8/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 11/29/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/31/2024 Approved RYAN SALAZAR
PLUMBING-Rough 1/31/2024 Approved RYAN SALAZAR
Insulation 2/23/2024 Approved RYAN SALAZAR
Shower Pan 2/23/2024 Approved RYAN SALAZAR
Drywall Nailing 3/6/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/6/2024 Approved RYAN SALAZAR
Service/Power Release 10/17/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 1/27/2025 Corrections Issued RAUL OLAGI
Final 1/27/2025 Corrections Issued RAUL OLAGI
Green Building Final 1/27/2025 Approved RAUL OLAGI
HVAC-Final 1/27/2025 Corrections Issued RAUL OLAGI
PLUMBING-Final 1/27/2025 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/27/2025 Approved RAUL OLAGI
Verify Sprinkler Sign Off 1/27/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/2/2025 Approved RYAN SALAZAR
Final 10/2/2025 OK to Issue CofO RYAN SALAZAR
Green Building Rough 10/2/2025 Approved RYAN SALAZAR