7030 N FORBES AVE 91406

Certificate Information: 7030 N FORBES AVE 91406

Application / Permit
18010-20000-05569
Plan Check / Job No.
B18VN19942
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 4'-8" x 33'-4", 12'-3" x 8'-0", 6'-0" x 15'-1", and 30'-10" x 21'-3" TO (E)SINGLE FAMILY DWELLING. REMOVE (E)DETACHED GARAGE AND ADD 18'-2" x 34'-6" (N)ATT. GARAGE WITH ATT. REC ROOM TO (E)SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 SARKIS HARABEDIAN
Corrections Issued 12/21/2018 SARKIS HARABEDIAN
Quality Review Completed 12/31/2018 OMID HEDAYAT
Building Plans Picked Up 1/3/2019 APPLICANT
Green Plans Picked Up 1/3/2019 APPLICANT
Applicant returned to address corrections 9/3/2019 SARKIS HARABEDIAN
Plan Check Approved 9/19/2019 SARKIS HARABEDIAN
Issued 9/19/2019 LADBS
TCO Issued (Expire Date: 06-20-2022) 12/22/2021 MICHAEL SMITH
CofO in Progress 8/10/2022 RAUL OLAGI
CofO Issued 8/10/2022 MICHAEL SMITH
Permit Finaled 8/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/28/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 8/28/2019 RINA LARA
Permit Cleared 8/28/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 8/28/2019 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 9/10/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 9/16/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/16/2019 JEANIE LAM
Green Code Cleared 9/19/2019 DAVID MATSON
Hydrant and Access approval Cleared 9/19/2019 GILBERT URREA

Contact Information

Architect Parker,, David Matthew; Lic. No.: C18851 25671 LE PARK #30      LAKE FOREST, CA 92630
Contractor Oxford Construction; Lic. No.: 593365-B 2081 BUSINESS CENTER DRIVE 205      IRVINE, CA 92612

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/29/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 12/30/2019 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 1/6/2020 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 1/14/2020 Approved JACK KARGODORIAN
ELECTRICAL-Rough 6/22/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval MICHEL ABAJAN
HVAC-Rough 6/22/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 6/22/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/2/2020 Approved DANIEL DREW
Insulation 7/7/2020 Approved ROBERT MINASSIANS
Drywall Nailing 7/16/2020 Approved DANIEL DREW
Green Building Rough 7/16/2020 Approved DANIEL DREW
Interior/Exterior Lathing 7/16/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 4/9/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 4/9/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 4/9/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Not Ready ARTHUR SARGSYAN
Smoke Detectors 4/9/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/13/2021 Approved ARTHUR SARGSYAN
Final 5/13/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 5/13/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Gas Company ARTHUR SARGSYAN
Smoke Detectors 5/13/2021 Approved ARTHUR SARGSYAN
Special/Order Compliance 5/25/2022 Partial Inspection MICHAEL TEMPLE
Final 8/10/2022 OK to Issue CofO RAUL OLAGI