1919-1921 N PINEHURST ROAD 90068

Certificate Information: 1919-1921 N PINEHURST ROAD 90068

Application / Permit
18010-20000-05535
Plan Check / Job No.
B18VN19807
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ BASEMENT & ATTACHED GARAGE & ACCESSORY DWELLING UNIT PER AB494 & SB229 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/17/2020
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 NILOOFAR MEHRAIN
Corrections Issued 11/26/2018 NILOOFAR MEHRAIN
Quality Review Completed 11/30/2018 CHON CHIO KUO
Green Plans Picked Up 11/30/2018 APPLICANT
Building Plans Picked Up 12/4/2018 APPLICANT
Applicant returned to address corrections 5/30/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/31/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/5/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/30/2019 NILOOFAR MEHRAIN
Plan Check Approved 10/3/2019 NILOOFAR MEHRAIN
Issued 7/17/2020 APPLICANT
CofO in Progress 10/5/2022 BRIAN SULLIVAN
Permit Finaled 10/22/2022 DEROLD HAUFF
Permit Finaled 10/22/2022 DEROLD HAUFF
CofO Issued 10/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/12/2019 LEE GUILBEAUX
Permit Cleared 4/12/2019 LEE GUILBEAUX
Sewer availability Cleared 4/12/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/18/2019 GEORGE SUCHAND
Low Impact Development Cleared 6/21/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/3/2019 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 7/18/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/18/2019 CALOSHA APPROVED
GPI Written Notices Cleared 7/18/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 7/18/2019 NILOOFAR MEHRAIN
Green Code Cleared 7/23/2019 DAVID MATSON
Encroachment in public way Cleared 7/29/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 7/29/2019 LEE GUILBEAUX
Address approval Cleared 10/3/2019 ADRIAN CASTRO

Contact Information

Contractor Forte Build & Design Inc; Lic. No.: 1026084-B 127 S BRAND BLVD #104      GLENDALE, CA 91204
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/6/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 1/6/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/7/2021 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 1/11/2021 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/22/2021 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/27/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 3/10/2021 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 3/10/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/11/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 3/24/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 3/26/2021 Partial Approval BRIAN SULLIVAN
Underground Mechanical 3/26/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/6/2021 Approved BRIAN SULLIVAN
Deputy Steel/Welding 4/23/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Inspection RAUL BARAJAS
Green Building Rough 5/18/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 5/18/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Corrections Issued RAUL BARAJAS
Deputy Wood Construction 6/28/2021 Approved RONALD KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval BRIAN SULLIVAN
HVAC-Rough 7/27/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 7/27/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 7/28/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 7/28/2021 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 8/24/2021 Partial Approval SCOTT FINNILA
HVAC-Rough 8/24/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 8/24/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 9/10/2021 Approved BRIAN SULLIVAN
HVAC-Rough 9/10/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/10/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 11/10/2021 Approved BRIAN SULLIVAN
Green Building Rough 11/10/2021 Approved BRIAN SULLIVAN
Shower Pan 11/10/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 11/10/2021 Approved BRIAN SULLIVAN
Wood Frame 11/10/2021 Approved BRIAN SULLIVAN
Deputy Wood Construction 11/15/2021 No Access for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 11/16/2021 Approved BRIAN SULLIVAN
Insulation 11/16/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 11/30/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/30/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 12/20/2021 Approved BRIAN SULLIVAN
Gas Test 3/9/2022 Corrections Issued RUBEN SALAS
Underground Mechanical 3/9/2022 Conditional Approval RUBEN SALAS
Gas Test 3/21/2022 Partial Approval BRIAN SULLIVAN
Sewer 3/21/2022 Approved BRIAN SULLIVAN
Gas Test 3/23/2022 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 3/23/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 6/22/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 6/22/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 7/29/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 7/29/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/3/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 8/3/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 8/3/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 8/9/2022 Partial Approval BRIAN SULLIVAN
Service/Power Release 8/9/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Final 8/17/2022 Approved BRIAN SULLIVAN
HVAC-Final 8/17/2022 Approved BRIAN SULLIVAN
SUSMP-Std. Urban Storm Water 8/17/2022 Approved BRIAN SULLIVAN
Final 9/28/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 9/28/2022 Approved BRIAN SULLIVAN
Green Building Final 9/28/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 9/28/2022 Approved BRIAN SULLIVAN
Smoke Detectors 9/28/2022 Approved BRIAN SULLIVAN
Final 10/5/2022 OK to Issue CofO BRIAN SULLIVAN
Service/Power Release 10/5/2022 Approved BRIAN SULLIVAN