1919-1921 N PINEHURST ROAD 90068
Certificate Information: 1919-1921 N PINEHURST ROAD 90068
- Application / Permit
- 18010-20000-05535
- Plan Check / Job No.
- B18VN19807
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ BASEMENT & ATTACHED GARAGE & ACCESSORY DWELLING UNIT PER AB494 & SB229 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/26/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/30/2018 | CHON CHIO KUO |
| Green Plans Picked Up | 11/30/2018 | APPLICANT |
| Building Plans Picked Up | 12/4/2018 | APPLICANT |
| Applicant returned to address corrections | 5/30/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/31/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/5/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/30/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/3/2019 | NILOOFAR MEHRAIN |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 10/5/2022 | BRIAN SULLIVAN |
| Permit Finaled | 10/22/2022 | DEROLD HAUFF |
| Permit Finaled | 10/22/2022 | DEROLD HAUFF |
| CofO Issued | 10/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2019 | LEE GUILBEAUX |
| Permit | Cleared | 4/12/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/12/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 4/18/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/21/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/3/2019 | LEE GUILBEAUX |
| Building over 3-story or 36-ft | Cleared | 7/18/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 7/18/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/18/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 7/18/2019 | NILOOFAR MEHRAIN |
| Green Code | Cleared | 7/23/2019 | DAVID MATSON |
| Encroachment in public way | Cleared | 7/29/2019 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 7/29/2019 | LEE GUILBEAUX |
| Address approval | Cleared | 10/3/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Forte Build & Design Inc; Lic. No.: 1026084-B | 127 S BRAND BLVD #104 GLENDALE, CA 91204 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Markov,, George P; Lic. No.: C55855 | 1623 THOMPSON AVE GLENDALE, CA 91201 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 1/11/2021 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/22/2021 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/27/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 3/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/11/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/24/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/26/2021 | Partial Approval | BRIAN SULLIVAN |
| Underground Mechanical | 3/26/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Approved | BRIAN SULLIVAN |
| Deputy Steel/Welding | 4/23/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Corrections Issued | RAUL BARAJAS |
| Deputy Wood Construction | 6/28/2021 | Approved | RONALD KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 7/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 7/28/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/28/2021 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/24/2021 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 8/24/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 8/24/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/10/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 9/10/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/10/2021 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/10/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/10/2021 | Approved | BRIAN SULLIVAN |
| Shower Pan | 11/10/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 11/10/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 11/10/2021 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 11/15/2021 | No Access for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 11/16/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/16/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 11/30/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/20/2021 | Approved | BRIAN SULLIVAN |
| Gas Test | 3/9/2022 | Corrections Issued | RUBEN SALAS |
| Underground Mechanical | 3/9/2022 | Conditional Approval | RUBEN SALAS |
| Gas Test | 3/21/2022 | Partial Approval | BRIAN SULLIVAN |
| Sewer | 3/21/2022 | Approved | BRIAN SULLIVAN |
| Gas Test | 3/23/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 3/23/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 6/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 7/29/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 7/29/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 7/29/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 8/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 8/3/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 8/9/2022 | Partial Approval | BRIAN SULLIVAN |
| Service/Power Release | 8/9/2022 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/17/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 8/17/2022 | Approved | BRIAN SULLIVAN |
| SUSMP-Std. Urban Storm Water | 8/17/2022 | Approved | BRIAN SULLIVAN |
| Final | 9/28/2022 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/28/2022 | Approved | BRIAN SULLIVAN |
| Green Building Final | 9/28/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 9/28/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 9/28/2022 | Approved | BRIAN SULLIVAN |
| Final | 10/5/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| Service/Power Release | 10/5/2022 | Approved | BRIAN SULLIVAN |