5332 N NATICK AVE 91411

Certificate Information: 5332 N NATICK AVE 91411

Application / Permit
18010-20000-05532
Plan Check / Job No.
B18VN19802
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'10" x 37'0" ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 11/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 JEFFREY TANGONAN
Corrections Issued 12/18/2018 JEFFREY TANGONAN
Quality Review Completed 12/20/2018 STEVEN KIM
Building Plans Picked Up 1/10/2019 APPLICANT
Green Plans Picked Up 1/10/2019 APPLICANT
Applicant returned to address corrections 3/12/2019 JEFFREY TANGONAN
Plan Check Approved 6/12/2019 JEFFREY TANGONAN
Issued 11/8/2019 LADBS
CofO in Progress 9/26/2020 CHARLES POWELL
CofO Issued 1/14/2021 DANIEL ORRANTE
Permit Finaled 1/14/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/20/2019 ELENA LOPEZ
CPC Cleared 2/20/2019 STEVEN WECHSLER
CPC Cleared 2/20/2019 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 2/20/2019 ELENA LOPEZ
Low Impact Development Cleared 2/20/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 2/20/2019 ELENA LOPEZ
Sewer availability Cleared 2/20/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 2/22/2019 JOHN DALLAS
Green Code Cleared 2/26/2019 MICHAEL AYERS
Construction near power lines Cleared 5/21/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/14/2020 Approved CHRISTOPHE COCHRAN
Underground Mechanical 1/14/2020 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 1/17/2020 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/22/2020 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 2/14/2020 Partial Approval CHRISTOPHE COCHRAN
Sewer 2/14/2020 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/19/2020 Approved CHRISTOPHE COCHRAN
HVAC-Rough 2/19/2020 Approved CHRISTOPHE COCHRAN
Gas Test 2/27/2020 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/27/2020 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 3/4/2020 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/4/2020 Approved CHRISTOPHE COCHRAN
Shower Pan 3/9/2020 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/11/2020 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/10/2020 Approved RAYMOND KEHOE
ELECTRICAL-Final 4/10/2020 Not Ready for Inspection RAYMOND KEHOE
Final 4/10/2020 Corrections Issued RAYMOND KEHOE
Green Building Final 4/10/2020 Not Ready for Inspection RAYMOND KEHOE
PLUMBING-Final 4/10/2020 Approved RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 4/10/2020 SGSOV Approved RAYMOND KEHOE
Service/Power Release 4/10/2020 Not Ready for Inspection RAYMOND KEHOE
Smoke Detectors 4/10/2020 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 4/10/2020 Approved RAYMOND KEHOE
ELECTRICAL-Final 8/7/2020 Approved CHRIS CHRISTENSEN
Final 8/7/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/7/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 8/7/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 8/7/2020 Approved CHRIS CHRISTENSEN
Service/Power Release 8/7/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Final 9/25/2020 OK to Issue CofO CHARLES POWELL
Service/Power Release 9/25/2020 Approved CHARLES POWELL