17310 W WESTBURY DR 91344

Certificate Information: 17310 W WESTBURY DR 91344

Application / Permit
18010-20000-05524
Plan Check / Job No.
B18VN19726
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'X30' 2-STORY ADU PER AB 494 AND SB 229
Permit Issued
Issued on 1/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 MARVEL DELACRUZ
Corrections Issued 11/23/2018 MARVEL DELACRUZ
Quality Review Completed 11/29/2018 STEVEN KIM
Building Plans Picked Up 12/17/2018 APPLICANT
Green Plans Picked Up 12/17/2018 APPLICANT
Plan Check Approved 1/29/2019 MARVEL DELACRUZ
Issued 1/29/2019 LADBS
CofO in Progress 3/31/2021 DAVID SCANTLIN
Permit Finaled 4/21/2021 JOHN JANSON
CofO Issued 4/21/2021 JOHN JANSON
Permit Finaled 4/21/2021 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 1/10/2019 HERMINIGILDO AGUSTIN
Distance to fire station Cleared 1/11/2019 JOHN DALLAS
Hydrant and Access approval Cleared 1/11/2019 JOHN DALLAS
Low Impact Development Cleared 1/24/2019 MITESH PATEL
Green Code Cleared 1/25/2019 PARISA ZAHABI
Address approval Cleared 1/29/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/29/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/29/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/29/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/29/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/29/2019 LEE GUILBEAUX
Sewer availability Cleared 1/29/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/15/2019 Corrections Issued SEAN WIRCH
PLUMBING-Rough 3/15/2019 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 4/3/2019 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 4/15/2019 Approved JOHN KIDWELL
Wood Frame 5/10/2019 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/28/2019 Partial Approval JOHN KIDWELL
Wood Frame 5/28/2019 Partial Inspection JOHN KIDWELL
ELECTRICAL-Rough 6/14/2019 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 8/8/2019 Approved DAVID SCANTLIN
Sewer 8/8/2019 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/15/2019 Approved DAVID SCANTLIN
HVAC-Rough 8/15/2019 Approved DAVID SCANTLIN
PLUMBING-Rough 8/15/2019 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/30/2019 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 2/27/2020 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Approved DAVID SCANTLIN
Green Building Rough 2/27/2020 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 2/27/2020 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 3/10/2020 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 3/10/2020 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 3/10/2020 Approved DAVID SCANTLIN
HVAC-Rough 3/10/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 3/10/2020 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 3/10/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/13/2020 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/13/2020 Approved DAVID SCANTLIN
Insulation 3/13/2020 Approved DAVID SCANTLIN
Drywall Nailing 3/19/2020 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 3/19/2020 Not Ready for Inspection DAVID SCANTLIN
Drywall Nailing 4/3/2020 Approved DAVID SCANTLIN
Shower Pan 4/3/2020 Approved DAVID SCANTLIN
ELECTRICAL-Rough 6/25/2020 Partial Approval DAVID SCANTLIN
Sewer 6/25/2020 Partial Approval DAVID SCANTLIN
Sewer 7/9/2020 Approved DAVID SCANTLIN
Service/Power Release 9/25/2020 Not Ready for Inspection DAVID SCANTLIN
Final 3/12/2021 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 3/12/2021 Approved DAVID SCANTLIN
Green Building Final 3/12/2021 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved DAVID SCANTLIN
Service/Power Release 3/12/2021 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 3/12/2021 Approved DAVID SCANTLIN
Final 3/19/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 3/19/2021 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 3/19/2021 Not Ready for Inspection DAVID SCANTLIN
Final 3/30/2021 OK to Issue CofO DAVID SCANTLIN
Green Building Final 3/30/2021 Approved DAVID SCANTLIN
Service/Power Release 3/30/2021 Approved DAVID SCANTLIN