19115 N LEMAY ST 91335

Certificate Information: 19115 N LEMAY ST 91335

Application / Permit
18010-20000-05515
Plan Check / Job No.
B18VN19705
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 45' X 16'1" DETACHED SINGLE STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER design
Permit Issued
Issued on 6/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 ALDOUS CHIC
Corrections Issued 12/17/2018 ALDOUS CHIC
Quality Review Completed 12/17/2018 ABDUL CHEGENI
Building Plans Picked Up 12/18/2018 APPLICANT
Green Plans Picked Up 1/24/2019 APPLICANT
Plan Check Approved 6/11/2019 ALDOUS CHIC
Issued 6/12/2019 LADBS
CofO in Progress 12/5/2019 DAVID SANDOVAL
Permit Finaled 6/25/2021 JOHN JANSON
CofO Issued 6/25/2021 JOHN JANSON
Permit Finaled 6/25/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/30/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/30/2019 GUILLERMO PETRA
Green Code Cleared 5/30/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 5/30/2019 GEORGE SUCHAND
Sewer availability Cleared 5/30/2019 GUILLERMO PETRA
Low Impact Development Cleared 6/4/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/5/2019 ARMEN SARKISIAN
ZI Cleared 6/5/2019 STEVEN WECHSLER
Construction near power lines Cleared 6/8/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2019 Not Ready for Inspection DAVID SANDOVAL
Underground Mechanical 7/2/2019 Corrections Issued DAVID SANDOVAL
Underground Mechanical 7/5/2019 Approved DAVID SANDOVAL
Footing/Foundation/Slab 7/9/2019 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 7/11/2019 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Approved DAVID SANDOVAL
Sewer 8/1/2019 Partial Approval DAVID SANDOVAL
Underground Mechanical 8/1/2019 Partial Approval DAVID SANDOVAL
Verify Sprinkler Sign Off 8/1/2019 Approved DAVID SANDOVAL
Sewer 8/8/2019 Corrections Issued DAVID SANDOVAL
Sewer 8/12/2019 Approved DAVID SANDOVAL
Underground Mechanical 8/16/2019 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 8/26/2019 Approved DAVID SANDOVAL
ELECTRICAL-Rough 8/26/2019 Approved DAVID SANDOVAL
Green Building Rough 8/26/2019 Approved DAVID SANDOVAL
HVAC-Rough 8/26/2019 Approved DAVID SANDOVAL
PLUMBING-Rough 8/26/2019 Approved DAVID SANDOVAL
Insulation 8/27/2019 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/27/2019 Partial Approval DAVID SANDOVAL
Drywall Nailing 8/30/2019 Approved DAVID SANDOVAL
Interior/Exterior Lathing 9/4/2019 Approved DAVID SANDOVAL
Shower Pan 9/4/2019 Approved DAVID SANDOVAL
Final 11/21/2019 Corrections Issued DAVID SANDOVAL
Green Building Final 11/21/2019 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 11/21/2019 SGSOV Approved DAVID SANDOVAL
Service/Power Release 11/21/2019 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 11/21/2019 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 12/3/2019 Approved DAVID SANDOVAL
Final 12/3/2019 OK to Issue CofO DAVID SANDOVAL
HVAC-Final 12/3/2019 Approved DAVID SANDOVAL
PLUMBING-Final 12/3/2019 Approved DAVID SANDOVAL
Service/Power Release 12/3/2019 Approved DAVID SANDOVAL
Smoke Detectors 12/3/2019 Approved DAVID SANDOVAL