433 N EL MEDIO AVE 90272
Certificate Information: 433 N EL MEDIO AVE 90272
- Application / Permit
- 18010-20000-05486
- Plan Check / Job No.
- B18VN19588
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 47'-1" x 79' Irr. Single Family Dwelling with Basement and attached Two-Car Garage.
- Permit Issued
- Issued on 5/13/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2018 | APPLICANT |
| Green Plans Picked Up | 12/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | OMID HEDAYAT |
| Corrections Issued | 12/26/2018 | OMID HEDAYAT |
| Quality Review Completed | 12/28/2018 | STEVEN KIM |
| Building Plans Picked Up | 1/2/2019 | APPLICANT |
| Applicant returned to address corrections | 2/27/2019 | OMID HEDAYAT |
| Plan Check Approved | 5/13/2019 | OMID HEDAYAT |
| Issued | 5/13/2019 | LADBS |
| CofO in Progress | 7/23/2020 | ANDREW NAVE |
| Permit Finaled | 7/28/2020 | VINCENT COTTON |
| CofO Issued | 7/28/2020 | VINCENT COTTON |
| Permit Finaled | 7/28/2020 | VINCENT COTTON |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 1/24/2019 | MELISSA JONES |
| Historic monument | Cleared | 1/24/2019 | MELISSA JONES |
| Address approval | Cleared | 1/29/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 1/29/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 1/29/2019 | JOHN DALLAS |
| Permit | Cleared | 1/29/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/31/2019 | JOHN LIN |
| Trees in Parkway | Cleared | 1/31/2019 | JOHN KIM |
| Low Impact Development | Cleared | 2/8/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 2/8/2019 | JEANIE LAM |
| GPI Written Notices | Cleared | 2/27/2019 | OMID HEDAYAT |
| Grading Pre-Inspection | Cleared | 2/27/2019 | OMID HEDAYAT |
| Coastal Zone | Cleared | 4/23/2019 | NOAH MCCOY |
| Coastal Zone | Cleared | 4/23/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 4/23/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 4/23/2019 | NOAH MCCOY |
| ZA Case | Cleared | 4/23/2019 | NOAH MCCOY |
Contact Information
| Contractor | Artisan Pacific Homes Inc; Lic. No.: 961077-B | 16030 JUNALUSKA WAY PACIFIC PALISADES, CA 90272 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2019 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 7/16/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/20/2019 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 8/21/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 9/13/2019 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 9/13/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/7/2019 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 10/16/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2019 | Corrections Issued | ANDREW NAVE |
| Deputy Steel/Welding | 11/7/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2019 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 11/26/2019 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/27/2019 | Not Ready for Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 12/5/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/10/2019 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 1/7/2020 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 1/10/2020 | Approved | ANDREW NAVE |
| Shower Pan | 1/10/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 1/14/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/15/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/17/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 1/17/2020 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 1/17/2020 | Approved | ANDREW NAVE |
| Insulation | 1/23/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 2/3/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 2/3/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 2/7/2020 | Approved | ANDREW NAVE |
| Shower Pan | 2/7/2020 | Approved | ANDREW NAVE |
| Sewer | 4/29/2020 | Approved | ANDREW NAVE |
| Underground Mechanical | 4/30/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 5/1/2020 | Approved | ANDREW NAVE |
| Underground Mechanical | 5/1/2020 | Approved | ANDREW NAVE |
| Service/Power Release | 5/6/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 6/3/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 6/19/2020 | Approved | ANDREW NAVE |
| Final | 6/30/2020 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 6/30/2020 | Approved | ANDREW NAVE |
| Reinforced Concrete Frame | 6/30/2020 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 6/30/2020 | Approved | ANDREW NAVE |
| Final | 7/7/2020 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 7/7/2020 | Approved | ANDREW NAVE |
| Final | 7/23/2020 | OK to Issue CofO | ANDREW NAVE |