15105 W WEDDINGTON ST 91411

Certificate Information: 15105 W WEDDINGTON ST 91411

Application / Permit
18010-20000-05328
Plan Check / Job No.
B18VN18863
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD W/ GARAGE
Permit Issued
Issued on 1/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 11/15/2018 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 11/26/2018 APPLICANT
Green Plans Picked Up 11/26/2018 APPLICANT
Quality Review Completed 11/27/2018 CHON CHIO KUO
Plan Check Approved 1/8/2019 VLADIMIR ARUTYUNYAN
Issued 1/10/2019 LADBS
CofO in Progress 12/1/2025 JACK KARGODORIAN
Permit Finaled 1/27/2026 RUBEN SALAS
CofO Issued 1/27/2026 RUBEN SALAS
Permit Finaled 1/27/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/5/2018 RUDY TERRIQUEZ.
Hydrant and Access approval Cleared 12/5/2018 GILBERT URREA
Sewer availability Cleared 12/5/2018 RUDY TERRIQUEZ.
Green Code Cleared 12/20/2018 MICHAEL AYERS
ZA Case Cleared 1/2/2019 TOM HENRY
ZA Case Cleared 1/2/2019 TOM HENRY
ZI Cleared 1/3/2019 RICK TORRES
Low Impact Development Cleared 1/4/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/8/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/14/2019 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/20/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/20/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/28/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/28/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 3/1/2019 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/15/2019 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2019 No Access for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2019 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/19/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 12/19/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/14/2020 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/14/2020 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/14/2020 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Corrections Issued DANIEL ORRANTE
BUILDING-Rough-Frame 6/25/2020 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Partial Approval DANIEL DREW
Green Building Rough 6/25/2020 Not Ready for Inspection DANIEL DREW
Verify Sprinkler Sign Off 6/25/2020 Approved DANIEL DREW
Insulation 9/10/2020 Approved WILLIAM KUEHN
Drywall Nailing 9/23/2020 Corrections Issued WILLIAM KUEHN
Drywall Nailing 10/6/2020 Approved DANIEL DREW
Interior/Exterior Lathing 10/21/2020 Partial Approval BRENDAN LOONEY
Shower Pan 10/21/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/28/2020 Approved CHARLES POWELL
Pre-Inspection 2/8/2022 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/25/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 4/25/2023 Not Ready for Inspection THOMAS FINNILA
Special/Order Compliance 5/3/2023 Corrections Issued DAVID MATSON
Pre-Inspection 11/20/2024 Corrections Issued VINCENT HANLEY
Pre-Inspection 11/22/2024 Corrections Issued JACK KARGODORIAN
Pre-Inspection 12/4/2024 Partial Approval JACK KARGODORIAN
Special/Order Compliance 3/27/2025 Partial Approval JACK KARGODORIAN
Special/Order Compliance 3/28/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 5/20/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Final 5/20/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 8/25/2025 Approved JUAN VALENZUELA
Service/Power Release 9/5/2025 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 10/17/2025 Approved JACK KARGODORIAN
Final 10/17/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 10/17/2025 Approved JACK KARGODORIAN
Green Building Final 10/17/2025 Approved JACK KARGODORIAN
Green Building Rough 10/17/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 10/17/2025 Approved JACK KARGODORIAN
Final 10/27/2025 Not Ready for Inspection JACK KARGODORIAN
Final 11/20/2025 Corrections Issued JACK KARGODORIAN
Final 11/25/2025 Conditional Approval WILLIAM WREN
Final 12/1/2025 OK to Issue CofO JACK KARGODORIAN