15105 W WEDDINGTON ST 91411
Certificate Information: 15105 W WEDDINGTON ST 91411
- Application / Permit
- 18010-20000-05328
- Plan Check / Job No.
- B18VN18863
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD W/ GARAGE
- Permit Issued
- Issued on 1/10/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/15/2018 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 11/26/2018 | APPLICANT |
| Green Plans Picked Up | 11/26/2018 | APPLICANT |
| Quality Review Completed | 11/27/2018 | CHON CHIO KUO |
| Plan Check Approved | 1/8/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 1/10/2019 | LADBS |
| CofO in Progress | 12/1/2025 | JACK KARGODORIAN |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
| CofO Issued | 1/27/2026 | RUBEN SALAS |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2018 | RUDY TERRIQUEZ. |
| Hydrant and Access approval | Cleared | 12/5/2018 | GILBERT URREA |
| Sewer availability | Cleared | 12/5/2018 | RUDY TERRIQUEZ. |
| Green Code | Cleared | 12/20/2018 | MICHAEL AYERS |
| ZA Case | Cleared | 1/2/2019 | TOM HENRY |
| ZA Case | Cleared | 1/2/2019 | TOM HENRY |
| ZI | Cleared | 1/3/2019 | RICK TORRES |
| Low Impact Development | Cleared | 1/4/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/8/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/14/2019 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/20/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/20/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/28/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 3/1/2019 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2019 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/19/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/19/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/14/2020 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/14/2020 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/14/2020 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Corrections Issued | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 6/25/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Partial Approval | DANIEL DREW |
| Green Building Rough | 6/25/2020 | Not Ready for Inspection | DANIEL DREW |
| Verify Sprinkler Sign Off | 6/25/2020 | Approved | DANIEL DREW |
| Insulation | 9/10/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 9/23/2020 | Corrections Issued | WILLIAM KUEHN |
| Drywall Nailing | 10/6/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 10/21/2020 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 10/21/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/28/2020 | Approved | CHARLES POWELL |
| Pre-Inspection | 2/8/2022 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Special/Order Compliance | 5/3/2023 | Corrections Issued | DAVID MATSON |
| Pre-Inspection | 11/20/2024 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 11/22/2024 | Corrections Issued | JACK KARGODORIAN |
| Pre-Inspection | 12/4/2024 | Partial Approval | JACK KARGODORIAN |
| Special/Order Compliance | 3/27/2025 | Partial Approval | JACK KARGODORIAN |
| Special/Order Compliance | 3/28/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/20/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 5/20/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/25/2025 | Approved | JUAN VALENZUELA |
| Service/Power Release | 9/5/2025 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | JACK KARGODORIAN |
| Final | 10/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/17/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 10/17/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/17/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/17/2025 | Approved | JACK KARGODORIAN |
| Final | 10/27/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/20/2025 | Corrections Issued | JACK KARGODORIAN |
| Final | 11/25/2025 | Conditional Approval | WILLIAM WREN |
| Final | 12/1/2025 | OK to Issue CofO | JACK KARGODORIAN |