10827 W HUSTON ST LOT #7 91601

Certificate Information: 10827 W HUSTON ST LOT #7 91601

Application / Permit
18010-20000-05164
Plan Check / Job No.
B18VN18344
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE & ROOFTOP DECK (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tract Map No. VTT-82138-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded]
Permit Issued
Issued on 9/1/2020
Issuing Office
Metro
Current Status
Issued on 9/1/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/23/2018 APPLICANT
Green Plans Picked Up 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 NILOOFAR MEHRAIN
Corrections Issued 12/6/2018 NILOOFAR MEHRAIN
Quality Review Completed 12/11/2018 CHON CHIO KUO
Building Plans Picked Up 12/11/2018 APPLICANT
Applicant returned to address corrections 1/15/2019 NILOOFAR MEHRAIN
Plan Check Approved 4/15/2019 NILOOFAR MEHRAIN
Issued 9/1/2020 APPLICANT

Permit Application Clearance Information

CPC Cleared 12/11/2018 TOM HENRY
Eng Process Fee Ord 176,300 Cleared 12/11/2018 CHRISTINE REUSCH
Sewer availability Cleared 12/11/2018 CHRISTINE REUSCH
Hydrant and Access approval Cleared 1/4/2019 JOHN DALLAS
Address approval Cleared 1/8/2019 HOWARD COOPER
Miscellaneous Cleared 1/9/2019 RINA LARA
Tract Map conditions Cleared 1/9/2019 RINA LARA
Building over 3-story or 36-ft Cleared 1/15/2019 CALOSHA APPROVED
Low Impact Development Cleared 1/30/2019 MITESH PATEL
Stormwater Pollution Mitigatn Cleared 1/30/2019 MITESH PATEL
Frnt yard landscape/Water mgmt Cleared 2/15/2019 SHEILA GERSHON
Green Code Cleared 2/28/2019 MICHAEL AYERS
Highway dedication Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Permit Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 6/26/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Legaspi Jose Luis; Lic. No.: 1064179-B 1863 GARDENIA AVE      LONG BEACH, CA 90806
Engineer Morris,, Kyle Byron; Lic. No.: C72911 1401 DOVE ST STE 520      NEWPORT BEACH, CA 92660
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/25/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 2/3/2021 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 2/18/2021 Approved DONALD SUNSERI
Deputy Reinf. Concrete 2/22/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Partial Approval HENRY KIM
PLUMBING-Rough 2/16/2022 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/18/2022 Approved HENRY KIM
ELECTRICAL-Rough 2/25/2022 Approved HENRY KIM
PLUMBING-Rough 2/25/2022 Partial Approval HENRY KIM
HVAC-Rough 4/22/2022 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 6/9/2022 Corrections Issued HENRY KIM
HVAC-Rough 6/9/2022 Corrections Issued HENRY KIM
PLUMBING-Rough 6/9/2022 Approved HENRY KIM
Insulation 6/16/2022 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval HENRY KIM
HVAC-Rough 7/27/2022 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 8/10/2022 Corrections Issued HENRY KIM
Green Building Rough 8/10/2022 Corrections Issued HENRY KIM
HVAC-Rough 8/10/2022 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 8/10/2022 Approved HENRY KIM
BUILDING-Rough-Frame 8/12/2022 Approved HENRY KIM
Green Building Rough 8/12/2022 Approved HENRY KIM
HVAC-Rough 8/12/2022 Approved HENRY KIM
Special/Order Compliance 8/12/2022 Corrections Issued HENRY KIM
Insulation 8/25/2022 Not Ready for Inspection HENRY KIM
Insulation 8/29/2022 Approved JEFFREY PARD
Drywall Nailing 9/16/2022 Approved HENRY KIM
Special/Order Compliance 9/16/2022 Approved HENRY KIM
Interior/Exterior Lathing 9/20/2022 Partial Approval HENRY KIM
Shower Pan 9/20/2022 Approved HENRY KIM
Interior/Exterior Lathing 9/22/2022 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 10/3/2022 No Access for Inspection SEAN WIRCH
Interior/Exterior Lathing 10/4/2022 Approved HENRY KIM
Deputy Wood Construction 10/7/2022 Conditional Approval HENRY KIM
Special/Order Compliance 3/18/2025 Corrections Issued JEFFREY PARD