18056 W SANTA RITA ST 91316
Certificate Information: 18056 W SANTA RITA ST 91316
- Application / Permit
- 18010-20000-05138
- Plan Check / Job No.
- B18VN18243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE IRREG. TWO STORY SFD WITH ATTACHED GARAGE _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | DAWN MC NULTY |
| Corrections Issued | 11/13/2018 | DAWN MC NULTY |
| Green Plans Picked Up | 11/14/2018 | APPLICANT |
| Quality Review Completed | 11/15/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 11/15/2018 | APPLICANT |
| Plan Check Approved | 11/4/2020 | DAWN MC NULTY |
| No Progress | 11/4/2020 | DAWN MC NULTY |
| Plan Check Approved | 5/19/2021 | DAWN MC NULTY |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 4/1/2024 | JOHN KIDWELL |
| Permit Finaled | 4/8/2024 | JOHN JANSON |
| CofO Issued | 4/8/2024 | JOHN JANSON |
| Permit Finaled | 4/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2018 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 11/19/2018 | APEKSHYA BAJRACHARYA |
| ZA Case | Cleared | 11/19/2018 | SHEILA GERSHON |
| Low Impact Development | Cleared | 12/5/2018 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2018 | JOHN LIN |
| Frnt yard landscape/Water mgmt | Cleared | 12/6/2018 | ANNA VIDAL |
| Hydrant and Access approval | Cleared | 12/6/2018 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 12/6/2018 | JOHN LIN |
| Sewer availability | Cleared | 12/6/2018 | JOHN LIN |
| Green Code | Cleared | 12/10/2018 | PARISA ZAHABI |
| Construction near power lines | Cleared | 3/29/2019 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 6/26/2019 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 6/26/2019 | DAWN MC NULTY |
| Miscellaneous | Cleared | 6/26/2019 | DAWN MC NULTY |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2021 | Corrections Issued | DAVID SANDOVAL |
| Sewer | 9/8/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/14/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 9/29/2021 | Conditional Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 10/5/2021 | Conditional Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/15/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/19/2021 | Approved | DAVID SANDOVAL |
| Deputy Steel/Welding | 11/3/2021 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 2/11/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 4/12/2022 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 4/12/2022 | Approved | SEAN WIRCH |
| Shower Pan | 4/12/2022 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 6/1/2022 | Corrections Issued | PETER FOLLING |
| ELECTRICAL-Rough | 6/1/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 6/1/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 6/22/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 6/22/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 6/22/2022 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 6/28/2022 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 7/14/2022 | Partial Approval | JEFFREY BULL |
| Insulation | 7/14/2022 | Corrections Issued | JEFFREY BULL |
| Interior/Exterior Lathing | 7/14/2022 | Approved | JEFFREY BULL |
| Insulation | 7/20/2022 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 8/1/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/1/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 8/1/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 6/23/2023 | Approved | SEAN HAUPT |
| Final | 6/23/2023 | Corrections Issued | SEAN HAUPT |
| Gas Test | 6/23/2023 | Approved | SEAN HAUPT |
| HVAC-Final | 6/23/2023 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 6/23/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 8/8/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 3/26/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 3/26/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 3/26/2024 | Approved | JOHN KIDWELL |
| Smoke Detectors | 3/26/2024 | Approved | JOHN KIDWELL |
| Final | 3/29/2024 | OK to Issue CofO | JOHN KIDWELL |