12227 W VALLEYHEART DR 91604

Certificate Information: 12227 W VALLEYHEART DR 91604

Application / Permit
18010-20000-05111
Plan Check / Job No.
B18VN18078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 18' X 12' DETACHED RECREATION ROOM WITH 1/2 BATHROOM AND EXTERIOR ACCESS SHOWER PER DESIGN.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2018 APPLICANT
Green Plans Picked Up 10/30/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 ALDOUS CHIC
Corrections Issued 11/5/2018 ALDOUS CHIC
Quality Review Completed 11/7/2018 OMID HEDAYAT
Building Plans Picked Up 11/30/2018 APPLICANT
Plan Check Approved 5/13/2019 ALDOUS CHIC
Plan Check Approved 5/13/2019 RARES BODEA
Issued 3/18/2021 APPLICANT
CofO in Progress 7/28/2021 ARAM AVEDISIAN
Permit Finaled 8/7/2021 MICHAEL SMITH
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/24/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 1/24/2019 APEKSHYA BAJRACHARYA
ZI Cleared 1/25/2019 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 2/6/2019 MARKOS PEREZ-BRAN
Green Code Cleared 2/8/2019 MICHAEL AYERS
Construction near power lines Cleared 5/1/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/22/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/31/2021 Approved ARAM AVEDISIAN
HVAC-Rough 3/31/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/31/2021 Corrections Issued ARAM AVEDISIAN
Shower Pan 3/31/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 4/1/2021 Conditional Approval ARAM AVEDISIAN
Green Building Rough 4/1/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 4/1/2021 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 4/5/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 4/5/2021 Approved ARAM AVEDISIAN
Insulation 4/8/2021 Approved JESUS RODRIGUEZ
Drywall Nailing 4/9/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/30/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Final 6/10/2021 Approved RONALD COWAN
HVAC-Final 6/10/2021 Approved RONALD COWAN
PLUMBING-Final 7/7/2021 Corrections Issued ARAM AVEDISIAN
Final 7/12/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 7/12/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 7/12/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 7/12/2021 Approved ARAM AVEDISIAN
Smoke Detectors 7/12/2021 Approved ARAM AVEDISIAN
Final 7/28/2021 OK to Issue CofO ARAM AVEDISIAN