12227 W VALLEYHEART DR 91604
Certificate Information: 12227 W VALLEYHEART DR 91604
- Application / Permit
- 18010-20000-05109
- Plan Check / Job No.
- B18VN18078
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 68'3" x 38' NFPA13-D sprinkler throughout 2-story dwelling with attached garage and trelllis per design. See comment.
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2018 | APPLICANT |
| Green Plans Picked Up | 10/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | ALDOUS CHIC |
| Corrections Issued | 11/5/2018 | ALDOUS CHIC |
| Quality Review Completed | 11/7/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 11/30/2018 | APPLICANT |
| Plan Check Approved | 2/20/2019 | ALDOUS CHIC |
| Issued | 1/6/2020 | LADBS |
| CofO in Progress | 7/28/2021 | ARAM AVEDISIAN |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
| CofO Issued | 8/7/2021 | MICHAEL SMITH |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/24/2019 | RYAN HUDSON |
| Permit | Cleared | 1/24/2019 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 1/24/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 1/24/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/25/2019 | JOHN DALLAS |
| ZI | Cleared | 1/25/2019 | HERMINIGILDO AGUSTIN |
| Trees in Parkway | Cleared | 1/31/2019 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/6/2019 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 2/8/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Lev Construction; Lic. No.: 1027463-B | 340 S CLOVERDALE AVE #404 LOS ANGELES, CA 90036 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/4/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/10/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/13/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/21/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/29/2020 | Approved | ARAM AVEDISIAN |
| Shower Pan | 12/31/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/5/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/7/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/12/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 2/12/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 2/12/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 2/17/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Insulation | 3/11/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 3/12/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 3/12/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/17/2021 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/17/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 3/17/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/17/2021 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Final | 4/16/2021 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 5/25/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/10/2021 | Approved | RONALD COWAN |
| HVAC-Final | 6/10/2021 | Approved | RONALD COWAN |
| Final | 7/12/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/12/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 7/12/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 7/12/2021 | Approved | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 7/12/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 7/12/2021 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 7/12/2021 | Approved | ARAM AVEDISIAN |
| Final | 7/28/2021 | OK to Issue CofO | ARAM AVEDISIAN |