8360 N CANBY PL 91324
Certificate Information: 8360 N CANBY PL 91324
- Application / Permit
- 18010-20000-05049
- Plan Check / Job No.
- B18VN17947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-73641-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY "MODEL DWELLING W/ SALES OFFICE" SFD, PLAN '3X'; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-73641-SL).
- Permit Issued
- Issued on 4/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2018 | APPLICANT |
| Green Plans Picked Up | 11/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2018 | ALEXANDER SBARDELLATI |
| Corrections Issued | 12/7/2018 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 12/11/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 12/11/2018 | APPLICANT |
| Applicant returned to address corrections | 1/4/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/23/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/21/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/5/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/6/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/12/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/14/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/15/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/19/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/20/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/22/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 4/3/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 4/11/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 4/16/2019 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 4/19/2019 | ALEXANDER SBARDELLATI |
| Issued | 4/19/2019 | LADBS |
| CofO in Progress | 4/26/2021 | JOSEPH SAGEN |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
| CofO Issued | 4/26/2021 | MICHAEL SMITH |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/14/2019 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/29/2019 | APEKSHYA BAJRACHARYA |
| Trees in Parkway | Cleared | 1/29/2019 | ADRIAN SANCHEZ |
| Address approval | Cleared | 3/18/2019 | HOWARD COOPER |
| Driveway location | Cleared | 4/2/2019 | KEN AITCHISON |
| Green Code | Cleared | 4/2/2019 | MICHAEL AYERS |
| Internal circulation | Cleared | 4/2/2019 | KEN AITCHISON |
| Miscellaneous | Cleared | 4/3/2019 | GUILLERMO PETRA |
| Highway dedication | Cleared | 4/4/2019 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 4/4/2019 | MARTIN FRAGOSO |
| Permit | Cleared | 4/4/2019 | GUILLERMO PETRA |
| "Q" conditions | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| "T" removal | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| CPC | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Frnt yard landscape/Water mgmt | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Site Plan review | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Tract Map conditions | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| ZA Case | Cleared | 4/11/2019 | MARITZA PRZEKOP |
| Roof/Waste drainage to street | Cleared | 4/15/2019 | ISRAEL TAMIRU |
Contact Information
| Architect | Texter,, Christopher S; Lic. No.: C25901 | 2 BUELLTON IRVINE, CA 92602 |
| Contractor | Meritage Homes Of California Inc; Lic. No.: 755679-B | 860 STILLWATER ROAD STE 200A WEST SACRAMENTO, CA 95605 |
| Engineer | Lothrop,, Shawn Duane; Lic. No.: S5627 | 40810 COUNTY CENTER DR STE 110 TEMECULA, CA 92563 |
| Engineer | Russell,, Robert Rush; Lic. No.: GE2042 | 23916 VIA MADRID MURRIETA, CA 92562 |
Inspector Information
| HENRY KIM, (818) 774-4334 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2019 | Approved | BRUCE ROZAK |
| Sewer | 4/29/2019 | Approved | BRUCE ROZAK |
| Underground Mechanical | 4/29/2019 | Approved | BRUCE ROZAK |
| Deputy Reinf. Concrete | 5/8/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/9/2019 | Approved | BRUCE ROZAK |
| Grounding or Bonding | 5/9/2019 | Approved | BRUCE ROZAK |
| Deputy Reinf. Concrete | 5/10/2019 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 5/16/2019 | Approved | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2019 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Deputy Wood Construction | 6/11/2019 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2019 | Approved | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2019 | Not Ready for Inspection | BRUCE ROZAK |
| BUILDING-Rough-Frame | 7/2/2019 | Not Ready for Inspection | BRUCE ROZAK |
| ELECTRICAL-Rough | 7/2/2019 | Approved | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2019 | Corrections Issued | BRUCE ROZAK |
| Green Building Rough | 7/2/2019 | Approved | BRUCE ROZAK |
| HVAC-Rough | 7/2/2019 | Approved | BRUCE ROZAK |
| PLUMBING-Rough | 7/2/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Verify Sprinkler Sign Off | 7/2/2019 | Approved | BRUCE ROZAK |
| BUILDING-Rough-Frame | 7/3/2019 | Approved | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2019 | Approved | BRUCE ROZAK |
| PLUMBING-Rough | 7/3/2019 | Approved | BRUCE ROZAK |
| Interior/Exterior Lathing | 7/9/2019 | Approved | BRUCE ROZAK |
| Insulation | 7/11/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Insulation | 7/12/2019 | Approved | BRUCE ROZAK |
| Drywall Nailing | 7/15/2019 | Approved | BRUCE ROZAK |
| Gas Test | 7/29/2019 | Not Ready for Inspection | BRUCE ROZAK |
| Underground Mechanical | 7/29/2019 | Approved | BRUCE ROZAK |
| Underground Mechanical | 7/31/2019 | Approved | DONALD SUNSERI |
| Gas Test | 8/19/2019 | Approved | BRUCE ROZAK |
| SGSOV-Seismic Gas S/O Valve | 8/21/2019 | SGSOV Approved | BRUCE ROZAK |
| ELECTRICAL-Final | 8/26/2019 | Approved | BRUCE ROZAK |
| Service/Power Release | 1/17/2020 | Approved | DONALD SUNSERI |
| Special/Order Compliance | 11/6/2020 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Rough | 12/3/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 12/3/2020 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Rough | 12/9/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Approved | JOSEPH SAGEN |
| Insulation | 12/9/2020 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 12/9/2020 | Approved | JOSEPH SAGEN |
| Final | 4/9/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 4/9/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 4/9/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Final | 4/15/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Final | 4/15/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Final | 4/15/2021 | Approved | JOSEPH SAGEN |
| Final | 4/16/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 4/16/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Final | 4/16/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 4/16/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Final | 4/21/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 4/21/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Final | 4/21/2021 | Approved | JOSEPH SAGEN |
| Final | 4/22/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 4/22/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 4/22/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 4/22/2021 | Approved | JOSEPH SAGEN |
| Final | 4/23/2021 | OK to Issue CofO | JOSEPH SAGEN |