8360 N CANBY PL 91324

Certificate Information: 8360 N CANBY PL 91324

Application / Permit
18010-20000-05049
Plan Check / Job No.
B18VN17947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-73641-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY "MODEL DWELLING W/ SALES OFFICE" SFD, PLAN '3X'; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-73641-SL).
Permit Issued
Issued on 4/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2018 APPLICANT
Green Plans Picked Up 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 ALEXANDER SBARDELLATI
Corrections Issued 12/7/2018 ALEXANDER SBARDELLATI
Quality Review Completed 12/11/2018 CHON CHIO KUO
Building Plans Picked Up 12/11/2018 APPLICANT
Applicant returned to address corrections 1/4/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/23/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/21/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/5/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/6/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/12/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/14/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/15/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/19/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/20/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/22/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/3/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/11/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/16/2019 ALEXANDER SBARDELLATI
Plan Check Approved 4/19/2019 ALEXANDER SBARDELLATI
Issued 4/19/2019 LADBS
CofO in Progress 4/26/2021 JOSEPH SAGEN
Permit Finaled 4/26/2021 MICHAEL SMITH
CofO Issued 4/26/2021 MICHAEL SMITH
Permit Finaled 4/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/14/2019 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 1/29/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/29/2019 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 1/29/2019 ADRIAN SANCHEZ
Address approval Cleared 3/18/2019 HOWARD COOPER
Driveway location Cleared 4/2/2019 KEN AITCHISON
Green Code Cleared 4/2/2019 MICHAEL AYERS
Internal circulation Cleared 4/2/2019 KEN AITCHISON
Miscellaneous Cleared 4/3/2019 GUILLERMO PETRA
Highway dedication Cleared 4/4/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 4/4/2019 MARTIN FRAGOSO
Permit Cleared 4/4/2019 GUILLERMO PETRA
"Q" conditions Cleared 4/11/2019 MARITZA PRZEKOP
"T" removal Cleared 4/11/2019 MARITZA PRZEKOP
CPC Cleared 4/11/2019 MARITZA PRZEKOP
Frnt yard landscape/Water mgmt Cleared 4/11/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/11/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/11/2019 MARITZA PRZEKOP
Site Plan review Cleared 4/11/2019 MARITZA PRZEKOP
Tract Map conditions Cleared 4/11/2019 MARITZA PRZEKOP
ZA Case Cleared 4/11/2019 MARITZA PRZEKOP
Roof/Waste drainage to street Cleared 4/15/2019 ISRAEL TAMIRU

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Meritage Homes Of California Inc; Lic. No.: 755679-B 860 STILLWATER ROAD STE 200A      WEST SACRAMENTO, CA 95605
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 40810 COUNTY CENTER DR STE 110      TEMECULA, CA 92563
Engineer Russell,, Robert Rush; Lic. No.: GE2042 23916 VIA MADRID      MURRIETA, CA 92562

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2019 Approved BRUCE ROZAK
Sewer 4/29/2019 Approved BRUCE ROZAK
Underground Mechanical 4/29/2019 Approved BRUCE ROZAK
Deputy Reinf. Concrete 5/8/2019 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/9/2019 Approved BRUCE ROZAK
Grounding or Bonding 5/9/2019 Approved BRUCE ROZAK
Deputy Reinf. Concrete 5/10/2019 Partial Approval JOHN KIDWELL
Deputy Wood Construction 5/16/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/16/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/17/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/20/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/23/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 5/24/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 5/28/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/4/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/6/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Not Ready for Inspection BRUCE ROZAK
Deputy Wood Construction 6/11/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/12/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/20/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/28/2019 Not Ready for Inspection BRUCE ROZAK
BUILDING-Rough-Frame 7/2/2019 Not Ready for Inspection BRUCE ROZAK
ELECTRICAL-Rough 7/2/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 7/2/2019 Corrections Issued BRUCE ROZAK
Green Building Rough 7/2/2019 Approved BRUCE ROZAK
HVAC-Rough 7/2/2019 Approved BRUCE ROZAK
PLUMBING-Rough 7/2/2019 Not Ready for Inspection BRUCE ROZAK
Verify Sprinkler Sign Off 7/2/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 7/3/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 7/3/2019 Approved BRUCE ROZAK
PLUMBING-Rough 7/3/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 7/9/2019 Approved BRUCE ROZAK
Insulation 7/11/2019 Not Ready for Inspection BRUCE ROZAK
Insulation 7/12/2019 Approved BRUCE ROZAK
Drywall Nailing 7/15/2019 Approved BRUCE ROZAK
Gas Test 7/29/2019 Not Ready for Inspection BRUCE ROZAK
Underground Mechanical 7/29/2019 Approved BRUCE ROZAK
Underground Mechanical 7/31/2019 Approved DONALD SUNSERI
Gas Test 8/19/2019 Approved BRUCE ROZAK
SGSOV-Seismic Gas S/O Valve 8/21/2019 SGSOV Approved BRUCE ROZAK
ELECTRICAL-Final 8/26/2019 Approved BRUCE ROZAK
Service/Power Release 1/17/2020 Approved DONALD SUNSERI
Special/Order Compliance 11/6/2020 Approved JOSEPH SAGEN
ELECTRICAL-Rough 12/3/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 12/3/2020 Approved JOSEPH SAGEN
ELECTRICAL-Rough 12/9/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Approved JOSEPH SAGEN
Insulation 12/9/2020 Approved JOSEPH SAGEN
PLUMBING-Rough 12/9/2020 Approved JOSEPH SAGEN
Final 4/9/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 4/9/2021 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 4/9/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 4/15/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 4/15/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/15/2021 Approved JOSEPH SAGEN
Final 4/16/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 4/16/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/16/2021 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 4/16/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 4/21/2021 Approved JOSEPH SAGEN
HVAC-Final 4/21/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/21/2021 Approved JOSEPH SAGEN
Final 4/22/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 4/22/2021 Approved JOSEPH SAGEN
HVAC-Final 4/22/2021 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 4/22/2021 Approved JOSEPH SAGEN
Final 4/23/2021 OK to Issue CofO JOSEPH SAGEN
HVAC-Final 4/23/2021 Approved JOSEPH SAGEN