8405 N FUSION WAY 91324

Certificate Information: 8405 N FUSION WAY 91324

Application / Permit
18010-20000-05046
Plan Check / Job No.
B18VN17947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-73641-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY SINGLE FAMILY DWELLING WITH ATT 2-CAR GARAGE, PLAN '4-R'; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-73641-SL).
Permit Issued
Issued on 9/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2018 APPLICANT
Green Plans Picked Up 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 ALEXANDER SBARDELLATI
Corrections Issued 12/7/2018 ALEXANDER SBARDELLATI
Quality Review Completed 12/11/2018 CHON CHIO KUO
Building Plans Picked Up 12/11/2018 APPLICANT
Applicant returned to address corrections 1/4/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/23/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/21/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/5/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/6/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/12/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/14/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/15/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/19/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/20/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/22/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/3/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/11/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/16/2019 ALEXANDER SBARDELLATI
Plan Check Approved 8/28/2019 DAWN MC NULTY
Issued 9/12/2019 LADBS
CofO in Progress 6/22/2020 DONALD SUNSERI
Permit Finaled 6/22/2020 DONALD SUNSERI
CofO Issued 6/22/2020 DONALD SUNSERI
Permit Finaled 6/22/2020 DONALD SUNSERI

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/14/2019 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 1/29/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/29/2019 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 1/29/2019 JOHN KIM
Address approval Cleared 3/18/2019 HOWARD COOPER
Driveway location Cleared 4/2/2019 KEN AITCHISON
Green Code Cleared 4/2/2019 MICHAEL AYERS
Internal circulation Cleared 4/2/2019 KEN AITCHISON
Miscellaneous Cleared 4/3/2019 GUILLERMO PETRA
Highway dedication Cleared 4/4/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 4/4/2019 MARTIN FRAGOSO
Permit Cleared 4/4/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 4/16/2019 ISRAEL TAMIRU
"Q" conditions Cleared 7/3/2019 DAISY BENICIA
"T" removal Cleared 7/3/2019 DAISY BENICIA
CPC Cleared 7/3/2019 DAISY BENICIA
Frnt yard landscape/Water mgmt Cleared 7/3/2019 DAISY BENICIA
Miscellaneous Cleared 7/3/2019 DAISY BENICIA
Miscellaneous Cleared 7/3/2019 DAISY BENICIA
Site Plan review Cleared 7/3/2019 DAISY BENICIA
Tract Map conditions Cleared 7/3/2019 DAISY BENICIA
ZA Case Cleared 7/3/2019 DAISY BENICIA

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Meritage Homes Of California Inc; Lic. No.: 755679-B 860 STILLWATER ROAD STE 200A      WEST SACRAMENTO, CA 95605
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 40810 COUNTY CENTER DR STE 110      TEMECULA, CA 92563
Engineer Russell,, Robert Rush; Lic. No.: GE2042 23916 VIA MADRID      MURRIETA, CA 92562

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/2/2019 Approved DONALD SUNSERI
Underground Mechanical 10/2/2019 Approved DONALD SUNSERI
Deputy Reinf. Concrete 10/15/2019 Approved DONALD SUNSERI
Excavation/Setback/Form/Re-Bar 10/15/2019 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 10/15/2019 Not Ready for Inspection DONALD SUNSERI
Excavation/Setback/Form/Re-Bar 10/16/2019 Approved BRUCE ROZAK
Footing/Foundation/Slab 10/16/2019 Approved BRUCE ROZAK
Underground Mechanical 12/9/2019 Approved BRUCE ROZAK
Underground Mechanical 12/11/2019 Approved BRUCE ROZAK
Underground Mechanical 12/16/2019 Not Ready for Inspection BRUCE ROZAK
Underground Mechanical 12/18/2019 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/26/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 1/8/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/14/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/28/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Partial Approval JOSEPH SAGEN
Deputy Drilled-In Anchors 2/11/2020 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 3/2/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 3/2/2020 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 3/3/2020 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 3/9/2020 Partial Approval JOSEPH SAGEN
Green Building Rough 3/9/2020 Approved JOSEPH SAGEN
HVAC-Rough 3/9/2020 Approved JOSEPH SAGEN
PLUMBING-Rough 3/9/2020 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 3/9/2020 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 3/16/2020 Approved JOSEPH SAGEN
Interior/Exterior Lathing 3/23/2020 Approved JOSEPH SAGEN
Drywall Nailing 3/27/2020 Approved JOSEPH SAGEN
Gas Test 4/15/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 4/28/2020 SGSOV Approved JOSEPH SAGEN
Service/Power Release 5/6/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 5/27/2020 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 5/27/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 6/3/2020 Approved JOSEPH SAGEN
HVAC-Final 6/3/2020 Approved JOSEPH SAGEN
Final 6/12/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 6/12/2020 Approved JOSEPH SAGEN
Smoke Detectors 6/12/2020 Approved JOSEPH SAGEN
Final 6/19/2020 OK to Issue CofO DONALD SUNSERI