8414 N FUSION WAY 91324

Certificate Information: 8414 N FUSION WAY 91324

Application / Permit
18010-20000-05038
Plan Check / Job No.
B18VN17947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-73641-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY SINGLE FAMILY DWELLING WITH ATT 2-CAR GARAGE, PLAN '2X-R'; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-73641-SL).
Permit Issued
Issued on 6/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2018 APPLICANT
Green Plans Picked Up 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 ALEXANDER SBARDELLATI
Corrections Issued 12/7/2018 ALEXANDER SBARDELLATI
Quality Review Completed 12/11/2018 CHON CHIO KUO
Building Plans Picked Up 12/11/2018 APPLICANT
Applicant returned to address corrections 1/4/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/23/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/21/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/5/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/6/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/12/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/14/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/15/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/19/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/20/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/22/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/3/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/11/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/16/2019 ALEXANDER SBARDELLATI
Plan Check Approved 6/5/2019 DAWN MC NULTY
Issued 6/7/2019 LADBS
CofO in Progress 3/2/2020 JOSEPH SAGEN
Permit Finaled 3/3/2020 DONALD SUNSERI
CofO Issued 3/3/2020 DONALD SUNSERI
Permit Finaled 3/3/2020 DONALD SUNSERI

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/14/2019 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 1/25/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/25/2019 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 1/29/2019 JOHN KIM
Address approval Cleared 3/18/2019 HOWARD COOPER
Driveway location Cleared 4/2/2019 KEN AITCHISON
Green Code Cleared 4/2/2019 MICHAEL AYERS
Internal circulation Cleared 4/2/2019 KEN AITCHISON
Miscellaneous Cleared 4/3/2019 GUILLERMO PETRA
Permit Cleared 4/3/2019 GUILLERMO PETRA
Highway dedication Cleared 4/4/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 4/4/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/16/2019 ISRAEL TAMIRU
ZA Case Cleared 4/23/2019 DAISY BENICIA
"Q" conditions Cleared 5/28/2019 DAISY BENICIA
CPC Cleared 5/28/2019 DAISY BENICIA
Frnt yard landscape/Water mgmt Cleared 5/28/2019 DAISY BENICIA
Miscellaneous Cleared 5/28/2019 DAISY BENICIA
Site Plan review Cleared 5/28/2019 DAISY BENICIA
Tract Map conditions Cleared 5/28/2019 DAISY BENICIA
"T" removal Cleared 5/29/2019 DAISY BENICIA
Miscellaneous Cleared 5/29/2019 DAISY BENICIA

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Meritage Homes Of California Inc; Lic. No.: 755679-B 860 STILLWATER ROAD STE 200A      WEST SACRAMENTO, CA 95605
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 40810 COUNTY CENTER DR STE 110      TEMECULA, CA 92563
Engineer Russell,, Robert Rush; Lic. No.: GE2042 23916 VIA MADRID      MURRIETA, CA 92562

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/24/2019 Not Ready for Inspection BRUCE ROZAK
Underground Mechanical 6/25/2019 Approved BRUCE ROZAK
Sewer 6/26/2019 Approved BRUCE ROZAK
Excavation/Setback/Form/Re-Bar 7/12/2019 Approved BRUCE ROZAK
Footing/Foundation/Slab 7/12/2019 Approved BRUCE ROZAK
Deputy Reinf. Concrete 7/16/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 7/26/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 7/30/2019 Partial Approval BRUCE ROZAK
Deputy Wood Construction 8/8/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 8/9/2019 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 8/12/2019 Not Ready for Inspection BRUCE ROZAK
Deputy Wood Construction 8/15/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/16/2019 Partial Approval BRUCE ROZAK
Underground Mechanical 8/16/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Partial Approval BRUCE ROZAK
Underground Mechanical 8/27/2019 Approved BRUCE ROZAK
Deputy Wood Construction 8/28/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/28/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/29/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 8/30/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 9/16/2019 Partial Approval BRUCE ROZAK
Deputy Drilled-In Anchors 9/18/2019 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 9/19/2019 Approved BRUCE ROZAK
Deputy Wood Construction 10/7/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 10/9/2019 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Not Ready for Inspection DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Partial Approval DONALD SUNSERI
PLUMBING-Rough 10/16/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 10/23/2019 Approved BRUCE ROZAK
ELECTRICAL-Rough 10/23/2019 Approved BRUCE ROZAK
Green Building Rough 10/23/2019 Approved BRUCE ROZAK
HVAC-Rough 10/23/2019 Approved BRUCE ROZAK
Verify Sprinkler Sign Off 10/23/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 10/28/2019 Approved BRUCE ROZAK
Drywall Nailing 11/1/2019 Approved BRUCE ROZAK
Gas Test 11/19/2019 Approved BRUCE ROZAK
ELECTRICAL-Final 12/6/2019 Not Ready for Inspection JOSEPH SAGEN
Service/Power Release 12/6/2019 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 12/13/2019 Approved BRUCE ROZAK
SGSOV-Seismic Gas S/O Valve 12/13/2019 SGSOV Approved BRUCE ROZAK
ELECTRICAL-Final 12/27/2019 Partial Approval BRUCE ROZAK
Service/Power Release 12/27/2019 Not Ready for Inspection BRUCE ROZAK
ELECTRICAL-Final 1/2/2020 Not Ready for Inspection JOSEPH SAGEN
Service/Power Release 1/2/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 2/11/2020 Approved JOSEPH SAGEN
HVAC-Final 2/11/2020 Approved JOSEPH SAGEN
PLUMBING-Final 2/11/2020 Approved JOSEPH SAGEN
Final 2/21/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 2/21/2020 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 2/21/2020 Approved JOSEPH SAGEN
Structural Steel Frame 2/21/2020 Not Ready for Inspection JOSEPH SAGEN
Final 2/28/2020 OK to Issue CofO JOSEPH SAGEN
Green Building Final 2/28/2020 Approved JOSEPH SAGEN
Structural Steel Frame 2/28/2020 Approved JOSEPH SAGEN