2957 N ALLESANDRO ST #1-25 90039

Certificate Information: 2957 N ALLESANDRO ST #1-25 90039

Application / Permit
18010-20000-04950
Plan Check / Job No.
B18VN17692
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
(N) 25-UNIT 3-STORY LIVE/WORK AFFORDABLE HOUSING APARTMENT BUILDING W/ PARKING GARAGE & RETAIL SPACE (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 3/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2018 APPLICANT
Green Plans Picked Up 10/24/2018 APPLICANT
Assigned to Plan Check Engineer 10/25/2018 NILOOFAR MEHRAIN
Corrections Issued 10/29/2018 NILOOFAR MEHRAIN
Quality Review Completed 10/31/2018 CHON CHIO KUO
Building Plans Picked Up 11/7/2018 APPLICANT
Applicant returned to address corrections 11/27/2018 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 11/29/2018 APPLICANT
Applicant returned to address corrections 12/7/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/26/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/9/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/10/2022 NILOOFAR MEHRAIN
Plan Check Approved 5/12/2022 NILOOFAR MEHRAIN
Issued 5/19/2022 APPLICANT
TCO Issued (Expire Date: 12-30-2024) 7/3/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 06-21-2025) 12/23/2024 ERNESTO CORRAL
CofO in Progress 3/27/2025 RAFAEL ESPINOZA
Permit Finaled 3/27/2025 ERNESTO CORRAL
CofO Issued 3/27/2025 ERNESTO CORRAL
Permit Finaled 3/27/2025 ERNESTO CORRAL

Permit Application Clearance Information

DAS Clearance Cleared 1/2/2019 NILOOFAR MEHRAIN
Low Impact Development Cleared 3/9/2020 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 3/9/2020 AMMAR ELTAWIL
CPC Cleared 3/18/2020 ANACANY HURTADO
CPC Cleared 3/18/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 3/18/2020 CECILIO NAVARRO
Highway dedication Cleared 3/18/2020 CECILIO NAVARRO
Permit Cleared 3/18/2020 CECILIO NAVARRO
Green Code Cleared 7/24/2020 DAVID MATSON
Hydrant and Access approval Cleared 8/3/2020 WILLIAM JOHNS
Sewer availability Cleared 10/20/2020 PAMELA TENEZA
DCP conditions approval Cleared 12/2/2020 KENNETH LE
Density Bonus 12.22.A.25 Cleared 12/2/2020 KENNETH LE
Housing rent stabilization Cleared 12/17/2020 PHILLIP MUNGUIA
Roof/Waste drainage to street Cleared 12/18/2020 CECILIO NAVARRO
Work Adjacent to Public Way Cleared 8/17/2021 ROSA SILVA
Address approval Cleared 10/8/2021 CECILIO NAVARRO
Fire Marshall Fire Life Safety Cleared 3/30/2022 DOMINIQUE MEDINA
"Q" conditions Cleared 5/3/2022 KENTON TRINH
Frnt yard landscape/Water mgmt Cleared 5/3/2022 KENTON TRINH
Miscellaneous Cleared 5/3/2022 KENTON TRINH
ZI Cleared 5/3/2022 KENTON TRINH
Opn space landscape/Water mgmt Cleared 5/4/2022 KENTON TRINH
ZI Cleared 5/4/2022 KENTON TRINH
Building over 3-story or 36-ft Cleared 5/10/2022 CALOSHA APPROVED

Contact Information

Contractor J B Contractors Inc; Lic. No.: 797840-B 133 E BONITA AVE #201      SAN DIMAS, CA 91773

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/2/2022 Approved TED RIES
Excavation/Setback/Form/Re-Bar 10/12/2022 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/20/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/27/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/27/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/21/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/22/2022 Partial Approval GREGORY POMISH
Deputy Other (see comments) 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/24/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/5/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 4/20/2023 Not Ready for Inspection LARRY ARNICK
Insulation 4/24/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/25/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Approved RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/21/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/14/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 8/14/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 8/16/2023 Approved RAFAEL ESPINOZA
Insulation 8/16/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/16/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 8/16/2023 Partial Approval RAFAEL ESPINOZA
Insulation 8/18/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 8/24/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/24/2023 Corrections Issued LARRY ARNICK
Insulation 8/28/2023 Partial Approval LARRY ARNICK
Drywall Nailing 8/30/2023 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Not Ready for Inspection LARRY ARNICK
Insulation 8/30/2023 Not Ready for Inspection LARRY ARNICK
Insulation 8/31/2023 Partial Approval LARRY ARNICK
Insulation 9/7/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/7/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 9/7/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/8/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 9/13/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 9/19/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/19/2023 Partial Approval RAFAEL ESPINOZA
Insulation 9/22/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/22/2023 Partial Approval RAFAEL ESPINOZA
Insulation 9/27/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/27/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/29/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/2/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/3/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/11/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/11/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/18/2023 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 10/18/2023 Approved RAFAEL ESPINOZA
Insulation 10/24/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/24/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/1/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/14/2023 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 2/2/2024 Partial Inspection RAFAEL ESPINOZA
Final 2/6/2024 Corrections Issued RAFAEL ESPINOZA
Light Gage Steel Frame 2/14/2024 Partial Approval RAFAEL ESPINOZA
Final 3/8/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/8/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Final 3/8/2024 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready JEFFREY FULTON
SUSMP-Std. Urban Storm Water 3/8/2024 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 3/8/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/8/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/8/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 4/10/2024 Approved RAFAEL ESPINOZA
Pre-Inspection 6/27/2024 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/3/2024 Approved RAFAEL ESPINOZA
Final 3/27/2025 OK to Issue CofO RAFAEL ESPINOZA
Footing/Foundation/Slab 3/27/2025 Approved RAFAEL ESPINOZA
Green Building Final 3/27/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Approved RAFAEL ESPINOZA
SUSMP-Std. Urban Storm Water 3/27/2025 Approved RAFAEL ESPINOZA
Smoke Detectors 3/27/2025 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/27/2025 Approved RAFAEL ESPINOZA
Wood Frame 3/27/2025 Approved RAFAEL ESPINOZA