8750 N BAIRD AVE 91324
Certificate Information: 8750 N BAIRD AVE 91324
- Application / Permit
- 18010-20000-04865
- Plan Check / Job No.
- B18VN17441
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- (N) 1-STORY TYPE V-B STORAGE BUILDING (68'-8" X 49'-4")
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 11/2/2018 | APPLICANT |
| Green Plans Picked Up | 11/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/13/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/13/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 11/19/2018 | APPLICANT |
| Plan Check Approved | 2/5/2019 | NILOOFAR MEHRAIN |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 8/25/2022 | DANNY RODRIGUEZ |
| Permit Finaled | 8/30/2022 | JEFFREY DURAN |
| CofO Issued | 8/30/2022 | JEFFREY DURAN |
| Permit Finaled | 8/30/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2018 | APEKSHYA BAJRACHARYA |
| CPC | Cleared | 12/17/2018 | RINA LARA |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2018 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 12/17/2018 | GILBERT URREA |
| Sewer availability | Cleared | 12/17/2018 | APEKSHYA BAJRACHARYA |
| "Q" conditions | Cleared | 12/19/2018 | RINA LARA |
| DAS Clearance | Cleared | 12/19/2018 | OLLIE CARTER |
| Green Code | Cleared | 12/19/2018 | DAVID MATSON |
| Permit | Cleared | 12/19/2018 | JEANETTE VONG |
| Low Impact Development | Cleared | 1/10/2019 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 1/10/2019 | ADRIAN SANCHEZ |
| "T" removal | Cleared | 8/8/2019 | RINA LARA |
Contact Information
| Architect | Giaimo,, Alain Olivier; Lic. No.: C24001 | 23546 NEWHALL AVENUE # 5 NEWHALL, CA 91321 |
| Contractor | Kash Construction & Management Services; Lic. No.: 948617-B | 533 S LOS ANGELES STREET #504 LOS ANGELES, CA 90013 |
| Engineer | Wahba,, Wahba Faris; Lic. No.: C33667 | 10041 SYLVIA AVE NORTHRIDGE, CA 91324 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2020 | Approved | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/19/2021 | Corrections Issued | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/21/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 1/22/2021 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 2/2/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 4/30/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 5/6/2021 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 5/6/2021 | Approved | HAMID PISHEHVAR |
| Masonry Wall/Backfill | 5/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/12/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/13/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/13/2021 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/18/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/19/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/19/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/24/2021 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 6/14/2021 | Conditional Approval | RICKEY JACKSON |
| Deputy Steel/Welding | 7/16/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 7/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 7/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Wood Construction | 7/21/2021 | Conditional Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Partial Approval | DANNY RODRIGUEZ |
| Pre-Inspection | 7/22/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 11/18/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Final | 3/29/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 3/29/2022 | Approved | DANNY RODRIGUEZ |
| Green Building Rough | 3/29/2022 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 3/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV No Gas | DANNY RODRIGUEZ |
| Smoke Detectors | 3/29/2022 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/29/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 5/24/2022 | OK to Issue CofO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/24/2022 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 5/24/2022 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 5/24/2022 | Approved | DANNY RODRIGUEZ |