10603 N COZYCROFT AVE 91311

Certificate Information: 10603 N COZYCROFT AVE 91311

Application / Permit
18010-20000-04839
Plan Check / Job No.
B18VN17306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-0" x 24'-0" TWO STORY DETACHED GARAGE WITH ACCESSORY DWELLING UNIT ABOVE PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 8/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 SARKIS HARABEDIAN
Corrections Issued 10/20/2018 SARKIS HARABEDIAN
Quality Review Completed 10/23/2018 OMID HEDAYAT
Green Plans Picked Up 12/3/2018 APPLICANT
Applicant returned to address corrections 3/10/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 3/3/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 6/17/2022 SARKIS HARABEDIAN
Building Plans Picked Up 6/21/2022 APPLICANT
Plan Check Approved 8/26/2022 SARKIS HARABEDIAN
Issued 8/30/2022 APPLICANT
CofO in Progress 3/31/2023 JUSTIN HAWLEY
Permit Finaled 4/14/2023 JOHN JANSON
CofO Issued 4/14/2023 JOHN JANSON
Permit Finaled 4/14/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/3/2021 GABRIEL ROBLES
Permit Cleared 3/3/2021 GABRIEL ROBLES
Sewer availability Cleared 3/3/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/21/2021 MATTHEW CRAIG
Construction within easement Cleared 5/10/2021 RIDWAN HARDY
GPI Written Notices Cleared 3/3/2022 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 3/3/2022 SARKIS HARABEDIAN
Low Impact Development Cleared 3/25/2022 MARTIN FRAGOSO
Address approval Cleared 6/28/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/29/2022 JOSE DUARTE-DIAZ
Trees in Parkway Cleared 8/2/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Richard,, Jon Wills; Lic. No.: C67927 6120 PEMBERTON WAY      COLORADO SPRINGS, CO 80919

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Approved DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 10/3/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 10/3/2022 Approved JOHN KIDWELL
Grounding or Bonding 10/3/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/3/2022 Partial Approval JOHN KIDWELL
Gas Test 10/19/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/19/2022 Partial Approval JOHN KIDWELL
Sewer 10/19/2022 Approved JOHN KIDWELL
Gas Test 10/20/2022 Partial Inspection JOHN KIDWELL
ELECTRICAL-Rough 10/31/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/8/2022 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Conditional Approval JOHN KIDWELL
Green Building Rough 11/8/2022 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 11/28/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval DAVID SCANTLIN
Green Building Rough 11/28/2022 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 11/28/2022 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 11/28/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 12/23/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/6/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 1/6/2023 Approved JOHN KIDWELL
Gas Test 1/6/2023 Partial Approval JOHN KIDWELL
Green Building Rough 1/6/2023 Approved JOHN KIDWELL
HVAC-Rough 1/6/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/6/2023 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 1/6/2023 Approved JOHN KIDWELL
Drywall Nailing 1/12/2023 Approved JOHN KIDWELL
Insulation 1/12/2023 Approved JOHN KIDWELL
Shower Pan 1/12/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/17/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 3/2/2023 Not Ready for Inspection SEAN HAUPT
Final 3/2/2023 Corrections Issued SEAN HAUPT
Gas Test 3/2/2023 Approved SEAN HAUPT
Green Building Final 3/2/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Final 3/2/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 3/2/2023 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved SEAN HAUPT
Service/Power Release 3/2/2023 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 3/2/2023 Approved SEAN HAUPT
PLUMBING-Final 3/7/2023 Approved DAVID SCANTLIN
Green Building Final 3/9/2023 Approved DAVID SCANTLIN
HVAC-Final 3/9/2023 Approved DAVID SCANTLIN
ELECTRICAL-Final 3/30/2023 Approved JUSTIN HAWLEY
Final 3/30/2023 OK to Issue CofO JUSTIN HAWLEY
Pre-Inspection 3/30/2023 Approved DAVID SCANTLIN
Service/Power Release 3/30/2023 Approved JUSTIN HAWLEY