2412 S CLEMENT AVE 90291
Certificate Information: 2412 S CLEMENT AVE 90291
- Application / Permit
- 18010-20000-04780
- Plan Check / Job No.
- B18VN16954
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE & ROOFTOP DECK (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 2/25/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 10/12/2018 | APPLICANT |
| Corrections Issued | 10/16/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/17/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 10/19/2018 | APPLICANT |
| Applicant returned to address corrections | 12/17/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/27/2018 | NILOOFAR MEHRAIN |
| Issued | 2/25/2019 | LADBS |
| Intent to Revoke-Status Void | 3/1/2021 | TAMERA SVETICH |
| Re-Activate Permit | 6/30/2022 | JASON HEALEY |
| CofO in Progress | 8/29/2022 | DAVID FEILER |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 10/29/2018 | JOHN CONNEALLY |
| Permit | Cleared | 10/29/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 10/29/2018 | MICHAEL CASTILLO |
| Miscellaneous | Cleared | 11/6/2018 | JEFF KHAU |
| Specific Plan | Cleared | 11/6/2018 | JEFF KHAU |
| Low Impact Development | Cleared | 11/29/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/29/2018 | STEVE MELGAR |
| CPC | Cleared | 12/5/2018 | SOPHIE GABEL-SCHEINBAU |
| Coastal Zone | Cleared | 12/5/2018 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 12/5/2018 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 12/5/2018 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 12/5/2018 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 12/11/2018 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 7/21/2020 | Partial Approval | DAVID HEINE |
| METHANE-Barrier | 7/21/2020 | Not Ready for Inspection | DAVID HEINE |
| METHANE-Subgrade | 7/21/2020 | Not Ready for Inspection | DAVID HEINE |
| Footing/Foundation/Slab | 7/30/2020 | Approved | DAVID HEINE |
| METHANE-Barrier | 7/30/2020 | Approved | DAVID HEINE |
| METHANE-Subgrade | 7/30/2020 | Approved | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 8/10/2020 | Partial Approval | DAVID HEINE |
| Underground Mechanical | 8/10/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 8/28/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 8/28/2020 | Not Ready for Inspection | DAVID HEINE |
| METHANE-Rough | 8/28/2020 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 8/28/2020 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Partial Approval | DAVID HEINE |
| Pre-Inspection | 9/22/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 11/9/2020 | Not Ready for Inspection | DAVID HEINE |
| ELECTRICAL-Rough | 11/9/2020 | Approved | DAVID HEINE |
| Green Building Rough | 11/9/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 11/9/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 11/9/2020 | Corrections Issued | DAVID HEINE |
| Verify Sprinkler Sign Off | 11/9/2020 | Not Ready for Inspection | DAVID HEINE |
| Pre-Inspection | 11/20/2020 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/25/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 11/25/2020 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Rough | 11/25/2020 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 11/25/2020 | Not Ready for Inspection | DAVID HEINE |
| Wood Frame | 11/25/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 1/5/2021 | Approved | DAVID HEINE |
| Green Building Rough | 1/5/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/5/2021 | Partial Approval | DAVID HEINE |
| Sewer | 1/5/2021 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 1/5/2021 | Approved | DAVID HEINE |
| Insulation | 1/8/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/8/2021 | Partial Approval | DAVID HEINE |
| Shower Pan | 1/8/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 1/21/2021 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | DAVID FEILER |
| Final | 7/7/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 7/7/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 7/7/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 7/7/2022 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 7/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 7/7/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 7/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 7/14/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 7/14/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 7/14/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 7/14/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 7/14/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 7/29/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 7/29/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 7/29/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 8/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 8/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/11/2022 | Approved | DAVID FEILER |
| Smoke Detectors | 8/11/2022 | Approved | DAVID FEILER |
| Final | 8/29/2022 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 8/29/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 8/29/2022 | Approved | DAVID FEILER |