10349 N HILLHAVEN AVE 91042
Certificate Information: 10349 N HILLHAVEN AVE 91042
- Application / Permit
- 18010-20000-04758
- Plan Check / Job No.
- B18VN16840
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE (20' X 24'-2") ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER ENGINEERING. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2018 | APPLICANT |
| Green Plans Picked Up | 10/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | RAPHAEL ROSAS |
| Corrections Issued | 10/13/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 10/19/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/23/2018 | APPLICANT |
| Applicant returned to address corrections | 2/4/2019 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/5/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 4/17/2019 | RAPHAEL ROSAS |
| Issued | 7/26/2021 | APPLICANT |
| CofO in Progress | 8/12/2025 | WILLIAM WREN |
| CofO Issued | 9/16/2025 | RUBEN SALAS |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2019 | JOHN LIN |
| Sewer availability | Cleared | 2/12/2019 | JOHN LIN |
| Green Code | Cleared | 3/4/2019 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 3/4/2019 | JOHN DALLAS |
| Miscellaneous | Cleared | 3/4/2019 | DAISY BENICIA |
| Specific Plan | Cleared | 3/21/2019 | RICK TORRES |
| ZA Case | Cleared | 3/21/2019 | RICK TORRES |
| Low Impact Development | Cleared | 3/28/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/3/2019 | ISRAEL TAMIRU |
| GPI Written Notices | Cleared | 4/16/2019 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 4/16/2019 | RAPHAEL ROSAS |
Contact Information
| Contractor | Olyaee Bahman; Lic. No.: 842261-B | 4926 CHIMINEAS AVE TARZANA, CA 91356 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 1/27/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 8/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/29/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/29/2022 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/2/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 9/2/2022 | Approved | MATTHEW NELSON |
| Reinforced Concrete Frame | 9/2/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/18/2022 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 10/18/2022 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/18/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/18/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/3/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/3/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/8/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/6/2022 | Approved | WILLIAM WREN |
| Insulation | 12/15/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 12/23/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/30/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 12/30/2022 | Approved | WILLIAM WREN |
| Sewer | 9/19/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 9/19/2023 | Approved | WILLIAM WREN |
| Service/Power Release | 10/17/2023 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | WILLIAM WREN |
| Final | 6/13/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 6/13/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 6/13/2025 | Approved | WILLIAM WREN |
| Smoke Detectors | 6/13/2025 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 6/13/2025 | Approved | WILLIAM WREN |
| Final | 6/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 8/8/2025 | OK to Issue CofO | WILLIAM WREN |