10347 N HILLHAVEN AVE 91042

Certificate Information: 10347 N HILLHAVEN AVE 91042

Application / Permit
18010-20000-04756
Plan Check / Job No.
B18VN16840
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (31'-10" X 32'-5") IRREGULAR SHAPED 2-STORY SFD W/ ATTACHED GARAGE PER ENGINEERING. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 7/26/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2018 APPLICANT
Green Plans Picked Up 10/10/2018 APPLICANT
Assigned to Plan Check Engineer 10/11/2018 RAPHAEL ROSAS
Corrections Issued 10/13/2018 RAPHAEL ROSAS
Quality Review Completed 10/19/2018 OMID HEDAYAT
Building Plans Picked Up 10/23/2018 APPLICANT
Applicant returned to address corrections 2/4/2019 RAPHAEL ROSAS
Applicant returned to address corrections 3/5/2019 RAPHAEL ROSAS
Plan Check Approved 4/17/2019 RAPHAEL ROSAS
Issued 7/26/2021 APPLICANT
CofO in Progress 8/12/2025 WILLIAM WREN
CofO in Progress 8/12/2025 WILLIAM WREN
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/12/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 2/12/2019 JOHN LIN
Sewer availability Cleared 2/12/2019 JOHN LIN
Green Code Cleared 3/4/2019 DAVID MATSON
Hydrant and Access approval Cleared 3/4/2019 JOHN DALLAS
Miscellaneous Cleared 3/4/2019 DAISY BENICIA
Specific Plan Cleared 3/21/2019 RICK TORRES
ZA Case Cleared 3/21/2019 RICK TORRES
Low Impact Development Cleared 3/28/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/3/2019 ISRAEL TAMIRU
GPI Written Notices Cleared 4/17/2019 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 4/17/2019 RAPHAEL ROSAS

Contact Information

Contractor Olyaee Bahman; Lic. No.: 842261-B 4926 CHIMINEAS AVE      TARZANA, CA 91356

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2021 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 6/15/2022 Corrections Issued MATTHEW NELSON
Pre-Inspection 6/15/2022 No Access for Inspection MATTHEW NELSON
PLUMBING-Rough 7/8/2022 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/11/2022 Approved MATTHEW NELSON
Footing/Foundation/Slab 7/11/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Partial Approval MATTHEW NELSON
Green Building Rough 8/1/2022 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 8/1/2022 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 8/22/2022 Conditional Approval MATTHEW NELSON
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 8/29/2022 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 8/29/2022 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval MATTHEW NELSON
Green Building Rough 9/7/2022 Not Ready for Inspection MATTHEW NELSON
Pre-Inspection 9/7/2022 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 9/7/2022 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Inspection MATTHEW NELSON
ELECTRICAL-Rough 10/18/2022 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 10/18/2022 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 10/18/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/18/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 11/8/2022 Corrections Issued MATTHEW NELSON
HVAC-Rough 11/8/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 11/8/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 11/15/2022 Corrections Issued WILLIAM WREN
HVAC-Rough 11/15/2022 Approved WILLIAM WREN
PLUMBING-Rough 11/15/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/21/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 11/21/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/6/2022 Approved WILLIAM WREN
Insulation 2/2/2023 Approved WILLIAM WREN
Drywall Nailing 3/17/2023 Approved WILLIAM WREN
Green Building Rough 3/17/2023 Approved WILLIAM WREN
Sewer 9/12/2023 Approved WILLIAM WREN
Underground Mechanical 9/12/2023 Partial Approval WILLIAM WREN
Service/Power Release 10/17/2023 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 10/24/2023 Partial Approval WILLIAM WREN
Pre-Inspection 2/29/2024 Not Ready for Inspection WILLIAM WREN
Final 6/13/2025 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Approved WILLIAM WREN
Service/Power Release 6/13/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/18/2025 Approved WILLIAM WREN
Final 6/18/2025 OK to Issue CofO WILLIAM WREN
Green Building Final 6/18/2025 Approved WILLIAM WREN
Service/Power Release 6/18/2025 Approved WILLIAM WREN
Smoke Detectors 6/18/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 6/18/2025 Approved WILLIAM WREN
Final 8/8/2025 OK to Issue CofO WILLIAM WREN