13487 W BROWNELL ST 91340

Certificate Information: 13487 W BROWNELL ST 91340

Application / Permit
18010-20000-04737
Plan Check / Job No.
B18VN16768
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, 1-STORY, 26'-4" X 25'-0" ACCESSORY DWELLING UNIT (ADU) PER AB 494 & SB 229. ALL WORK IS PER WFPP/CITY STANDARDS.
Permit Issued
Issued on 3/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2018 APPLICANT
Green Plans Picked Up 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 ALEXANDER SBARDELLATI
Corrections Issued 11/7/2018 ALEXANDER SBARDELLATI
Quality Review Completed 11/7/2018 CHON CHIO KUO
Building Plans Picked Up 12/13/2018 APPLICANT
Applicant returned to address corrections 3/26/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/27/2019 ALEXANDER SBARDELLATI
Plan Check Approved 3/29/2019 ALEXANDER SBARDELLATI
Issued 3/29/2019 LADBS
CofO in Progress 1/12/2022 MICHEL ABAJAN
CofO Issued 1/29/2022 MICHAEL SMITH
Permit Finaled 1/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/13/2018 PARISA ZAHABI
Address approval Cleared 1/7/2019 KAYLA PEJI
Permit Cleared 1/7/2019 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 1/9/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 1/9/2019 JOHN DALLAS
Low Impact Development Cleared 3/11/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/15/2019 GUILLERMO PETRA
Sewer availability Cleared 3/15/2019 GUILLERMO PETRA
CPC Cleared 3/27/2019 HERMINIGILDO AGUSTIN
Trees in Parkway Cleared 3/27/2019 JOHN KIM
ZA Case Cleared 3/27/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/8/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/17/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 8/13/2021 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 8/13/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/16/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/16/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 8/16/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 8/16/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/16/2021 Approved JENNIFER RABUCHIN
Insulation 8/27/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 8/27/2021 Partial Inspection WILLIAM KUEHN
Drywall Nailing 9/9/2021 Approved ADAM ESCOTO
Green Building Rough 9/9/2021 Approved ADAM ESCOTO
ELECTRICAL-Final 11/23/2021 Approved MICHEL ABAJAN
Final 11/23/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 11/23/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 11/23/2021 Approved MICHEL ABAJAN
PLUMBING-Final 11/23/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/23/2021 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/23/2021 Approved MICHEL ABAJAN
Pre-Inspection 12/16/2021 Partial Inspection MICHEL ABAJAN
Final 1/11/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 1/11/2022 Approved MICHEL ABAJAN
Service/Power Release 1/11/2022 Approved MICHEL ABAJAN