15127 W GREENLEAF ST 91403

Certificate Information: 15127 W GREENLEAF ST 91403

Application / Permit
18010-20000-04702
Plan Check / Job No.
B18VN16624
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
PROPOSE 10'X20' RECREATION ROOM WITH HALF-BATH_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA13D [SEE COMMENTS].
Permit Issued
Issued on 10/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 DAWN MC NULTY
Corrections Issued 10/8/2018 DAWN MC NULTY
Green Plans Picked Up 10/11/2018 APPLICANT
Quality Review Completed 10/15/2018 CHON CHIO KUO
Building Plans Picked Up 10/16/2018 APPLICANT
Applicant returned to address corrections 1/22/2019 DAWN MC NULTY
Plan Check Approved 1/29/2019 DAWN MC NULTY
Issued 10/7/2019 LADBS
CofO in Progress 8/11/2022 JACK KARGODORIAN
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/12/2018 DAWN MC NULTY
Address approval Cleared 12/13/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 12/13/2018 MICHAEL CASTILLO
Grading Pre-Inspection Cleared 12/13/2018 PATRICK MISCHLICH
Permit Cleared 12/13/2018 MICHAEL CASTILLO
Sewer availability Cleared 12/13/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 12/21/2018 JOHN CONNEALLY
Low Impact Development Cleared 1/9/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/9/2019 STEVE MELGAR
GPI Written Notices Cleared 1/29/2019 DAWN MC NULTY

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 5/21/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Approved CHARLES POWELL
Verify Sprinkler Sign Off 5/21/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 5/28/2021 Not Ready for Inspection CHARLES POWELL
Green Building Rough 5/28/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 5/28/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 6/24/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/12/2021 Approved CHARLES POWELL
Insulation 8/11/2021 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 10/4/2021 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 10/4/2021 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/12/2021 Approved MISAEL ESPARZA
Drywall Nailing 10/12/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Approved MISAEL ESPARZA
Green Building Rough 10/12/2021 Approved MISAEL ESPARZA
Insulation 10/12/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/12/2021 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 10/12/2021 Approved MISAEL ESPARZA
Shower Pan 11/1/2021 Conditional Approval MICHAEL PELHAM
Interior/Exterior Lathing 11/30/2021 Approved JACK KARGODORIAN
Final 8/10/2022 OK to Issue CofO JACK KARGODORIAN
Footing/Foundation/Slab 8/10/2022 Approved JACK KARGODORIAN
Green Building Final 8/10/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 8/10/2022 Approved JACK KARGODORIAN
Smoke Detectors 8/10/2022 Approved JACK KARGODORIAN